3.7.6 Checking the Estimate

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.6 Checking the Estimate
Table 3.7-5. Checks before an estimate goes out
CheckWhy
The quote matches the RFP quantitiesQuotes often carry different footage, tube or test counts
Laboratory carried onceAvoids double billing
The total in the email equals the workbook totalSmall differences cause questions later; correct them in writing
Within any budget limitPrice separate locations as separate lines so the client can authorize one
Assumptions listedStandby, access, flagging, utilities, cuttings, lab quantities (Chapter 3.1)
Revision historyEach revision dated, with the change and the net effect
35%43%18%TotalConsultant laborDrillingLaboratoryTravel and expensesLocation 1 estimate: about $93,000; with the second location: about $156,000 (over the $100,000 limit)
Figure 3.7-2. Make-up of a recent field investigation estimate. Pricing the two locations separately let the client authorize the one that fit its budget limit.