3.7.8 Contingency and Escalation

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.8 Contingency and Escalation

Carry contingency as named items rather than as padding: train standby, refusal offsets, coring, extra mobilizations, mats and clearing (Chapter 3.3, Table 3.3-10). For construction estimates of alternatives add a percentage contingency that matches the stage of design, and escalate to the expected construction year.

Project cost control. An estimate is only useful if actual costs are tracked against it; budget tracking by task (Section 3.7.9) closes the loop.
Figure 3.7-3. Project cost control. An estimate is only useful if actual costs are tracked against it; budget tracking by task (Section 3.7.9) closes the loop.