3.7.7 Stabilization Construction Costs

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.7 Stabilization Construction Costs

For ground hazard work the estimate also prices the stabilization alternatives, so that the risk reduction of each (Section 3.8.37) can be weighed against its cost. Build these from quantities by reach (shot rock, over-excavation, geotextile, geogrid, piles, lagging, drainage) and unit costs, and report a range rather than a single figure until the design is done.

Table 3.7-6. Typical stabilization cost items
AlternativeMain quantities
Shot-rock toe key and buttressOver-excavation, shot rock, geotextile, by reach
Geogrid-reinforced slopeGeogrid by layer, select fill, facing
Soldier pile and lagging wallPiles (length and size), lagging, tiebacks if needed, drainage
Drainage improvementsCulvert replacement or cleaning, ditches, subdrains, outlet protection
Undercut and replaceExcavation, haul, select fill, geosynthetics
Rockfall measuresScaling, bolting, mesh, catchment ditch
Compare like with like. When a client is weighing stabilization against buying land or easements, give quantities and a cost range for each alternative on the same basis, and say what each one leaves as residual risk.