3.7.12 Track Section Quantities for Estimates

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.12 Track Section Quantities for Estimates

Most of the cost of new or rebuilt track below the ties lies in four items: ballast, subballast, undercut of unsuitable subgrade, and its replacement. All four follow from the typical section and the boring results. Railroad sidetrack standards fix the section (12 in. of ballast below the tie on main track, ballast sloped 2:1, subballast to a set width and depth) and the undercut rules. A common rule removes plastic soils (AASHTO A-2-6, A-2-7, A-4 to A-7) in cuts to at least 2 ft below subgrade from ditch line to ditch line. It also removes organic muck (A-8) under fills within the toes of slope, to a width of three times the fill height where the fill exceeds 10 ft, and removes rock 18 in. below subgrade and refills it.

3.7.12.1 Section geometry

Equation 3.7-1. Net ballast area per foot of track

Ab = (W1 + W2)/2 × (hb + td) − n Lt bt td / s

W1 = tie length + 2 shoulders (+ track centers for multiple tracks); W2 = W1 + 2 × slope × height; hb = ballast below tie; td, bt, Lt = tie depth, width and length; s = tie spacing.

3.7.12.2 Worked example: one mile of single track

Table 3.7-8. 8.5 ft ties at 19.5 in., 12 in. ballast, 12 in. shoulders, 2:1; 12 in. subballast 24 ft wide; 800 ft of plastic cut (calculator output)
ItemQuantity
Net ballast area19.35 sq ft per ft
Ballast5,109 tons (3,784 cu yd)
Subballast9,660 tons (5,084 cu yd)
Undercut and replace, plastic subgrade in cut1,896 cu yd

Unit weights (1.35 and 1.9 tons per cu yd) are entries, not standards; use the supplier's or railroad's conversion. Quantities are neat-line.

The undercut is often the item that the boring program changes most: if the borings show plastic soil over the whole of a cut rather than 800 ft of it, the undercut quantity and the haul double. Linking the estimate to the boring logs (Chapter 4.1) is the best protection against change orders (Chapter 8.2).

Open the track quantities calculator →
Ballast and subballast volume and tonnage from the typical section, with undercut and replacement of plastic subgrade and rock in cuts.

3.7.12.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • A Class I railroad's standard specifications for private sidetracks (2016), Carriers folder: roadbed and ballast sections, unsuitable material, embankments, subballast and ballast gradations.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1 (2019 edition), Part 2: ballast depth below tie and sub-ballast practice.Official page ↗
  • A Class I railroad's public projects manual (2020), Carriers folder.Find source ↗