The consultant's field cost is mostly the field engineer's time with the rig: every drilling day, plus mobilization, utility clearance and demobilization. The drilling subconsultant's quote is entered as a lump sum and checked against the RFP quantities line by line (footage, coring, tubes, standby hours, mobilizations).
| Item | Basis |
|---|---|
| Utility clearance | Hours for one-call coordination and railroad signal and utility locates |
| Mobilization and demobilization | Travel time each way; one per separate setup |
| On-site exploration | Drilling days x hours per day (10-hour days are common with union crews) |
| Drilling subconsultant | Quote: mobilization, footage, coring, tubes, DCP, backfill, standby, per diem |
| Field expenses | Travel, lodging, vehicle, supplies |