3.5.12 Flood Hydrographs, Routing and Flood Frequency

Describing the physical setting of a site (ground, water, structures and track) so that everyone working on it starts from the same picture.
Author: Daniel P. Colwell
3.5.12 Flood Hydrographs, Routing and Flood Frequency

Section 3.5.10 gives the peak flow for a small basin. Larger basins, embankments that pond water behind them, and any crossing where the volume or timing of a flood matters need a flood hydrograph: losses, transformation of rainfall excess to runoff, routing through channels and storage, and a frequency for the result. The USACE manual Flood-Runoff Analysis (EM 1110-2-1417) sets out these methods and how to choose among them.

Table 3.5-11. Components of a flood-runoff model (after EM 1110-2-1417)
ComponentCommon methodsNotes for railroad basins
PrecipitationDesign storm from NOAA Atlas 14; historical storm; probable maximum precipitation (PMP) for dam-related studiesUse the storm duration that gives the highest peak for the basin, usually at least the time of concentration.
LossesInitial and constant loss rate; NRCS curve number; Green-Ampt; continuous soil-moisture accountingFrozen ground, saturated antecedent conditions and burned areas cut losses sharply.
Runoff transformationUnit hydrographs: Snyder, Clark, NRCS dimensionless; kinematic waveCalibrate parameters to gauged floods in the region where possible.
Channel routingMuskingum, Muskingum-Cunge, modified PulsFloodplain storage lowers and delays the peak downstream.
Storage routingLevel-pool (modified Puls) through the storage behind an embankment or reservoirAn embankment with a culvert is a small dam: ponding lowers the outflow peak but raises the headwater.
FrequencyGauged flood frequency (Log-Pearson Type III per USGS Bulletin 17C); regional regression (USGS StreamStats); frequency of the design stormCompare model results with regional regression estimates.

Snyder synthetic unit hydrograph HY-02

Eq. 3.5-5: tl = Ct (L Lca)0.3 (hr), the lag from the center of the rainfall excess to the peak, with L = main watercourse length to the divide (mi) and Lca = length to the point opposite the basin centroid (mi).

Eq. 3.5-6: tr = tl / 5.5 (standard duration); for another duration tR, tlR = tl + 0.25 (tR − tr).

Eq. 3.5-7: Qp = 640 Cp A / tlR (cfs per inch of excess), with A in mi².

Snyder’s original Ct and Cp came from the Appalachian region; values elsewhere differ substantially, so calibrate them with regional data or use a regional regression for lag (EM 1110-2-1417, Ch. 7).

Embankments as dams

Where a culvert is small compared with the flood, water ponds behind the embankment. Level-pool routing uses the storage-elevation curve upstream and the culvert rating curve to find the outflow hydrograph and the maximum headwater. The outflow peak is lower than the inflow peak, which helps downstream, but the embankment then holds water like a dam: it saturates, seeps, and can pipe or fail by rapid drawdown when the pond falls (Chapter 6.3, Section 6.3.8). If the culvert blocks with debris or ice, the pond can overtop the track. Dams near the line are covered in Chapter 2.8, Section 2.8.15.

Flood frequency

At a gauged site, fit annual peak flows with the Log-Pearson Type III distribution following USGS Bulletin 17C (published in 2018, current version 1.1 of 2019, the successor to Bulletin 17B). At ungauged sites, use the USGS regional regression equations through StreamStats, and transfer gauged results to the site by drainage-area ratio where a nearby gauge is on the same stream. A rainfall-runoff model run with a 100-year storm does not automatically give the 100-year flood; check it against the frequency estimates.

Example 3.5-2: Snyder Unit Hydrograph Check on a Culvert Basin

Problem Statement

A Class I railroad located in Kentucky is replacing a 72-in. culvert under a 30-ft embankment. The rational method of Section 3.5.10 is not suitable for the 4.2-mi² basin, so the engineer builds a Snyder unit hydrograph as a check on the hydrology consultant’s model. Regional studies give Ct = 2.0 and Cp = 0.60, and the 100-year storm gives 2.9 in. of rainfall excess by the curve number method.

centroid Embankmentand culvert L = 6.0 mi (to divide)Lca = 2.8 miA = 4.2 mi² GivenA = 4.2 mi²L = 6.0 mi, Lca = 2.8 miCt = 2.0, Cp = 0.60tR = 1.0 hr100-yr excess 2.9 in. Required(a) Lag tl and tr(b) 1-hr UH peak(c) Peak check value
Figure 3.5-5. Example 3.5-2: basin draining to a railroad embankment culvert (not to scale).

Given

VariableValueDescription
A4.2 mi²Drainage area
L6.0 miMain watercourse length to the divide
Lca2.8 miLength to the point opposite the centroid
Ct, Cp2.0, 0.60Regional Snyder coefficients
tR1.0 hrDesired unit hydrograph duration
Q2.9 in.100-year rainfall excess (curve number method)

Required

  • (a) Lag tl and standard duration tr
  • (b) Peak of the 1-hour unit hydrograph
  • (c) An upper-bound check on the 100-year peak

Equations

  1. Eq. 3.5-5: tl = Ct(L Lca)0.3
  2. Eq. 3.5-6: tr = tl/5.5; tlR = tl + 0.25(tR − tr)
  3. Eq. 3.5-7: Qp = 640 Cp A / tlR

Steps

Step 1 · (a) Lag
L Lca = 6.0 × 2.8 = 16.8; 16.80.3 = e0.3 × 2.821 = 2.331; 2.0 × 2.331
tl = 4.66 hr
↓
Step 2 · (a) Standard duration
4.66 / 5.5
tr = 0.85 hr
↓
Step 3 · (b) Adjust to 1 hr
4.66 + 0.25 (1.0 − 0.85)
tlR = 4.70 hr
↓
Step 4 · (b) Unit peak
640 × 0.60 × 4.2 / 4.70 = 1,613 / 4.70
Qp ≈ 343 cfs per inch
Spot check: 343 × 4.70 / 4.2 = 384 = 640 × 0.60 ✓.
↓
Step 5 · (c) Upper bound
343 × 2.9 (all excess in one hour)
≈ 995 cfs
↓
Solution
tl = 4.66 hr; the 1-hour unit hydrograph peaks at about 343 cfs per inch; the 100-year peak cannot exceed about 1,000 cfs, and will be lower because the excess falls over several hours.

Solution

tl = 4.66 hr; the 1-hour unit hydrograph peaks at about 343 cfs per inch; the 100-year peak cannot exceed about 1,000 cfs, and will be lower because the excess falls over several hours.

If all 2.9 in. of excess fell in one hour, the peak would be about 1,000 cfs. Real storms spread the excess over several hours, so the convolved peak will be lower; a value from the consultant’s model much above 1,000 cfs points to an error, and one far below (say under half) needs explaining. Compare the result with the USGS regional regression estimate for the site. Then route the hydrograph through the storage behind the 30-ft embankment: the pond may lower the outflow peak enough to allow a smaller pipe, but the design must then account for the headwater on the embankment and the risk of blockage.

Example 3.5-4: Ponding Behind an Embankment: Storage Routing Through a Culvert

Problem Statement

A Class I railroad located in Iowa has a 60-in. culvert under a 14-ft embankment in a broad valley. Base of rail is 12 ft above the culvert invert, so the railroad’s criterion of headwater at least 2 ft below base of rail limits headwater to 10 ft. The design flood hydrograph is triangular. Water ponds behind the fill, so the engineer must route the flood through the storage to find the peak outflow and the maximum headwater, and check what happens if debris blocks half of the culvert.

02004000246Time (hr)Flow (cfs)Inflow I (peak 400 cfs)Outflow O = ?GivenTriangular inflow: peak400 cfs at 2 hr, ends 5 hrStorage S = 30,000 H² ft³Culvert O = 25 H¹·⁵ cfsΔt = 0.5 hr; H limit 10 ftRequired(a) Peak outflow and time(b) Maximum headwater H(c) Culvert half blocked
Figure 3.5-7. Example 3.5-4: inflow hydrograph and routed outflow through the storage behind a railroad embankment.

Given

VariableValueDescription
I(t)0 to 400 cfs at 2.0 hr, back to 0 at 5.0 hrTriangular inflow hydrograph
S(H)30,000 H² ft³Storage upstream of the embankment, from the topography
O(H)25 H1.5 cfsCulvert rating (inlet control) fitted to HDS-5 headwater values
Δt0.5 hr (1,800 s)Routing time step
Hmax10 ftAllowable headwater

Required

  • (a) Peak outflow and its time
  • (b) Maximum headwater, compared with the 10-ft limit
  • (c) Peak outflow and headwater with the culvert half blocked (O = 12.5 H1.5)

Equations

  1. Eq. 3.5-11 (storage indication, modified Puls): 2S2/Δt + O2 = I1 + I2 + (2S1/Δt − O1)
  2. S = 30,000 H2; O = 25 H1.5

Steps

Step 1 · Storage-indication table
For a range of H, compute S, O and 2S/Δt + O (Table 3.5-13). At H = 5 ft: S = 750,000 ft³; O = 25 × 11.18 = 279.5 cfs; 2 × 750,000/1,800 + 279.5 = 1,112.8 cfs.
Table of 2S/Δt + O against H
↓
Step 2 · Route each step (Eq. 3.5-11)
Example, 2.0 to 2.5 hr: at 2.0 hr H = 4.64 ft, S = 645,900 ft³, O = 250.2 cfs, so 2S/Δt − O = 717.7 − 250.2 = 467.5. Then 400 + 333 + 467.5 = 1,200.5 cfs, which lies just above the H = 5.2-ft value of 1,197.8 in the table.
At 2.5 hr: H ≈ 5.21 ft, O ≈ 297 cfs
Spot check: 25 × 5.211.5 = 25 × 11.89 = 297 cfs ✓.
↓
Step 3 · (a) and (b) Complete the routing
Repeat for every step (Table 3.5-12)
Peak outflow ≈ 298 cfs at about 3.0 hr; maximum H ≈ 5.2 ft
Spot check: the outflow peak falls on the receding limb of the inflow, where the two hydrographs cross, as it must for level-pool storage.
↓
Step 4 · (c) Half-blocked culvert
Repeat with O = 12.5 H1.5
Peak outflow ≈ 227 cfs at about 3.5 hr; maximum H ≈ 6.9 ft
↓
Solution
Storage cuts the 400-cfs inflow peak to about 300 cfs and delays it an hour; headwater reaches 5.2 ft (6.9 ft half blocked), within the 10-ft limit.
Table 3.5-12. Example 3.5-4 routing results (storage-indication method, Δt = 0.5 hr)
t (hr)Inflow I (cfs)Outflow O (cfs)Headwater H (ft)
0.5100391.35
1.02001032.56
1.53001743.64
2.04002504.64
2.53332975.21
3.02672985.22
3.52002734.92
4.01332294.37
4.5671723.62
5.001052.61
5.50461.50
6.00140.68
Table 3.5-13. Storage-indication table: 2S/Δt + O against H
H (ft)S (ft³)O (cfs)2S/Δt + O (cfs)
130,00025.058.3
2120,00070.7204.0
3270,000129.9429.9
4480,000200.0733.3
5750,000279.51,112.8
61,080,000367.41,567.4

Solution

(a) About 298 cfs at about 3.0 hr, 25% below the inflow peak. (b) About 5.2 ft, within the 10-ft limit. (c) Half blocked: about 227 cfs and 6.9 ft, still within the limit but with about 1.4 million ft³ held against the fill.

The pond helps the culvert: the outflow peak is a quarter lower and an hour later than the inflow peak. The cost is that the embankment holds 5 to 7 ft of water for several hours. Check the fill for seepage and piping along the culvert barrel at that head, and for rapid drawdown as the pond falls (Chapter 6.3, Section 6.3.8). The half-blocked case shows how much headroom is left for debris or ice; full blockage would raise the pond toward the track, so keep the inlet clear and add a trash rack or debris deflector if the basin delivers woody debris. Real storage curves and culvert ratings come from survey and HDS-5 or HY-8; the fitted power-law forms here keep the hand calculation short.

Muskingum channel routing HY-05

Where the flood is measured or modeled upstream and the crossing is some distance down the valley, the hydrograph changes along the reach: storage in the channel and floodplain lowers the peak and delays it. The Muskingum method treats reach storage as S = K[XI + (1 − X)O], where K is the travel time of the flood wave through the reach and X (0 to 0.5) weights inflow against outflow. X near 0 means strong floodplain storage and attenuation; X near 0.5 means the wave passes almost unchanged. Solving the storage equation over a time step gives the routing equation:

Eq. 3.5-12: O2 = C0I2 + C1I1 + C2O1, with C0 = (Δt − 2KX)/D, C1 = (Δt + 2KX)/D, C2 = [2K(1 − X) − Δt]/D and D = 2K(1 − X) + Δt. The coefficients sum to 1.

Eq. 3.5-13: 2KX ≤ Δt ≤ 2K(1 − X), the time-step range that keeps all three coefficients positive. K and X are best calibrated from upstream and downstream gauged hydrographs; without them, K can be estimated as reach length divided by flood-wave celerity (about 1.5 times the mean velocity for a wide channel), and Muskingum-Cunge computes K and X from the channel geometry, slope and roughness (EM 1110-2-1417, Ch. 9).

Example 3.5-5: Muskingum Routing from an Upstream Gauge to a Railroad Bridge

Problem Statement

A Class I railroad located in Ohio crosses a creek on a ballast-deck bridge 3.0 mi downstream of a USGS stream gauge. During a storm the gauge records the hydrograph in Table 3.5-14, peaking at 1,000 cfs 4 hr after the start of the rise. The bridge waterway passes 900 cfs with 2 ft of freeboard to low chord. The railroad’s storm watch needs to know the peak flow and its arrival time at the bridge, and whether a slow order or closure is warranted.

Bridge waterway 900 cfs05001,0000481216Time (hr)Flow (cfs)Gauge inflow I (peak 1,000 cfs)Bridge outflow O = ?GivenReach 3.0 mi, gauge to bridgeWave celerity c = 2.2 ft/sWeighting factor X = 0.2Δt = 1 hr; base flow 100 cfsBridge passes 900 cfs with2 ft freeboardRequired(a) K, C0, C1, C2 and theΔt check(b) Peak at the bridge and time(c) Warning time and waterway
Figure 3.5-8. Example 3.5-5: flood hydrograph at an upstream gauge and the routed hydrograph at a railroad bridge 3 miles downstream.

Given

VariableValueDescription
L3.0 mi (15,840 ft)Reach length, gauge to bridge
c2.2 ft/sFlood-wave celerity (from the gauge rating and channel survey)
X0.2Weighting factor, moderate floodplain storage
Δt1 hrRouting time step (gauge reports hourly)
I(t)100 cfs base; peak 1,000 cfs at 4 hrGauge hydrograph (Table 3.5-14)
Qcap900 cfsBridge waterway capacity with 2 ft freeboard

Required

  • (a) K, the routing coefficients C0, C1, C2, and the Δt check
  • (b) Peak flow at the bridge and its time
  • (c) Warning time after the gauge peak, and whether the bridge waterway is exceeded

Equations

  1. K = L / c
  2. Eq. 3.5-12: O2 = C0I2 + C1I1 + C2O1
  3. Eq. 3.5-13: 2KX ≤ Δt ≤ 2K(1 − X)

Steps

Step 1 · (a) Travel time K
15,840 ft / 2.2 ft/s = 7,200 s
K = 2.0 hr
↓
Step 2 · (a) Time-step check (Eq. 3.5-13)
2KX = 2 × 2.0 × 0.2 = 0.8 hr; 2K(1 − X) = 2 × 2.0 × 0.8 = 3.2 hr
0.8 ≤ 1.0 ≤ 3.2 hr ✓
↓
Step 3 · (a) Coefficients
D = 3.2 + 1.0 = 4.2; C0 = (1.0 − 0.8)/4.2; C1 = (1.0 + 0.8)/4.2; C2 = (3.2 − 1.0)/4.2
C0 = 0.048; C1 = 0.429; C2 = 0.524
Spot check: 0.048 + 0.429 + 0.524 = 1.000 ✓.
↓
Step 4 · (b) Route hour by hour (Table 3.5-14)
Start with O = 100 cfs (base flow). At 6 hr: 0.048 × 650 + 0.429 × 850 + 0.524 × 809.2 = 31.0 + 364.3 + 423.9
Peak O ≈ 819 cfs at 6 hr
Spot check: the routed peak falls on the receding limb of the inflow, and its delay (2 hr) equals K, as expected for moderate X.
↓
Step 5 · (c) Warning time and waterway
Gauge peak at 4 hr, bridge peak at 6 hr; 819 against 900 cfs
About 2 hr of warning; peak 81 cfs (9%) below the waterway capacity
↓
Solution
The reach lowers the 1,000-cfs gauge peak to about 820 cfs at the bridge, arriving about 2 hr later, below the 900-cfs waterway.
Table 3.5-14. Example 3.5-5 Muskingum routing (K = 2.0 hr, X = 0.2, Δt = 1 hr)
t (hr)Inflow I (cfs)C0I2C1I1C2O1Outflow O (cfs)
0100–––100
130014.342.952.4110
260028.6128.657.4215
390042.9257.1112.4412
41,00047.6385.7216.0649
585040.5428.6340.1809
665031.0364.3423.9819
748022.9278.6429.0730
835016.7205.7382.6605
926012.4150.0316.9479
102009.5111.4251.1372
111607.685.7194.9288
121306.268.6151.0226
131105.255.7118.2179
141004.847.193.9146

Solution

(a) K = 2.0 hr; C0 = 0.048, C1 = 0.429, C2 = 0.524; a 1-hr step lies within 0.8 to 3.2 hr. (b) About 819 cfs at 6 hr, 18% below the gauge peak. (c) About 2 hr of warning after the gauge peaks; the routed peak stays 81 cfs below the 900-cfs waterway capacity.

The gauge gives the storm watch a real lead time: a gauge peak near 1,000 cfs means the bridge sees about 820 cfs two hours later, so the bridge can stay in service with an inspector watching for drift and scour at the piers. Routing the reach shows how much margin is left: a gauge peak of about 1,100 cfs would bring the bridge to its waterway capacity, and that is a practical trigger for a slow order or closure in the storm-watch plan (Chapter 7.4). Drift lodged on the piers reduces the waterway, so the capacity used for the trigger should allow for it. Muskingum routing assumes the reach has no large tributary inflow between the gauge and the bridge; add local inflow from the intervening area if it is more than a few percent of the gauged area. Where the reach is long, ungauged or the floodplain changes along it, use Muskingum-Cunge or HEC-RAS unsteady flow.

For railroad work: Ask for the full hydrograph, not only the peak, for any culvert or bridge draining more than a few hundred acres, and for any crossing where the embankment ponds water. Review the loss and unit hydrograph parameters against regional values and the frequency result against regional regression. Treat a high embankment with a small culvert as a dam: check seepage, piping and rapid drawdown at the maximum pond level, and plan for blockage by debris or ice.

Sources: USACE (1994), Flood-Runoff Analysis, EM 1110-2-1417, Chs. 6–9, 11 and 13. Official page ↗ England, J. F. et al. (2019), Guidelines for Determining Flood Flow Frequency, Bulletin 17C, USGS Techniques and Methods 4-B5. Official page ↗ USGS StreamStats. Official page ↗ Summarized and paraphrased.