3.5.2 Geology and Stratigraphy

Describing the physical setting of a site (ground, water, structures and track) so that everyone working on it starts from the same picture.
Author: Daniel P. Colwell
3.5.2 Geology and Stratigraphy

Give the regional geology in two or three sentences (bedrock formation and depth, surficial deposits) and then the expected or confirmed profile as a table. Where conditions change along a linear project, describe them by reach, each with its nearest data and its main design concern.

Track section placed on the prepared subgradeTopsoil, gravel or asphaltoften mixed with cindersSlag, cinder and urban fillvery dense to cemented; auger refusal possibleOrganic clay and peat (local)w over 100%; settlementLacustrine sand and siltvery loose to medium dense; saturated; N 2 to 8Glacial tillstiff to very stiff lean to fat clay; Qu 1.0 to 3.7 tsf05101520253035Depth (ft)
Figure 3.5-1. Idealized profile of a filled lake-plain site compiled from 43 legacy borings. Groundwater is typically 1 to 6 ft below grade. Depths are typical; the fill and organic layers vary over short distances.
Table 3.5-2. Example conditions by reach along a siding
ReachNearest dataExpected under the new slopeMain design concern
AHand auger: stiff sandy lean clay with gravel, N 8 to 25, dryLean clay embankment fill over alluvial clay; rock depth unknownNo data under the toe of the steepened slope
BBoring: thin cinder fill; very soft organic clay at 2.5 to 3 ft (N 3); stiff clay; limestone fragments at 8 ftSoft organic clay in the upper 2 to 4 ft; breccia from about 8 to 20 ft, highly variableUndercut depth; variable rock; possible voids
CHand auger: soft gray fat clay from 2 to 6+ ft (N 1 to 2); water at 4 ft; next to a wetlandSoft fat clay at least 6 ft thick, bottom not found; pondingCritical reach: stability on soft clay, settlement, undercut versus buttress
DShallow stiff lean clay; culvert under the trackThin clay over rock; ditch cuts may hit rockDitch grade in rock
Fractured rock exposed in a cut. Exposures like this one are the cheapest geology data on a site and belong in the site conditions section with their location.
Figure 3.5-2. Fractured rock exposed in a cut. Exposures like this one are the cheapest geology data on a site and belong in the site conditions section with their location.