3.5.11 Riprap for Embankments, Channels and Culvert Outlets

Describing the physical setting of a site (ground, water, structures and track) so that everyone working on it starts from the same picture.
Author: Daniel P. Colwell
3.5.11 Riprap for Embankments, Channels and Culvert Outlets

Washouts are among the most frequent and costly ground hazards on a railroad: flood flow along an embankment toe, overtopping at a low point, and scour at a culvert outlet or bridge abutment can remove the support from under the track in hours. Riprap is the usual protection. The site conditions review (Sections 3.5.3 and 3.5.10) gives the design flow and velocity; this section turns them into a stone size, a stone weight and a layer thickness, so a field team can tell whether existing riprap is adequate and an estimate can carry the right stone class.

3.5.11.1 Method

Equation 3.5-2. Bank and channel riprap (FHWA HEC-11)

D50 = 0.001 CsgCsfVa³ / (davg0.5K11.5);   K1 = √(1 − sin²θ/sin²φ);   Csg = 2.12/(Ss − 1)1.5;   Csf = (SF/1.2)1.5

D50 and davg in ft, Va = average velocity in ft/s; θ = bank angle; φ = angle of repose of the stone (about 40° to 42° for angular rock); SF = stability factor (Table 3.5-10).

Equation 3.5-3. High-turbulence locations (Isbash)

D50 = V² / [2gC²(Ss − 1)],   C = 0.86 (high turbulence) or 1.20 (low turbulence)

For abutments, overtopping flow at the crest and shoulder, spur dikes and other locations where the local velocity is known but the flow is not uniform.

Equation 3.5-4. Culvert outlet apron (FHWA HEC-14 Eq. 10.4)

D50 = 0.2D [Q/(√g D2.5)]4/3 (D/TW)

D = culvert diameter (ft); Q in cfs; TW = tailwater depth, not less than 0.4D. Above a discharge intensity of about 6 use a riprap basin or energy dissipator.

Table 3.5-10. HEC-11 stability factor SF
ConditionSF
Uniform flow, straight or mildly curving reach (radius/width above about 30), little debris or wave impact1.0–1.2
Gradually varying flow, moderate bends (radius/width 10 to 30), some debris or waves1.3–1.6
Rapidly varying flow, sharp bends, flow impinging on the bank, heavy debris or ice1.6–2.0

A typical gradation has D100 about 2D50 and D15 about 0.5D50. The layer should be at least the larger of D100, 1.5D50 and 12 in., increased by half where it is placed under water, and it needs a granular or geotextile filter beneath it and a toe keyed below the expected scour depth. The stone weight is W50 = (π/6)γsD50³.

3.5.11.2 Worked example

Example 3.5-1: Riprap at an Embankment Toe on the Outside of a Bend

A fill on a Class I railroad located in Missouri runs along a river at the outside of a bend. The design flood gives an average velocity of 10 ft/s at a depth of 6 ft against the 2H:1V embankment slope. The existing protection is a scatter of 6-in. stone.

Va = 10 ft/sd = 6 ft2H:1Voutside of a bend: SF = 1.5D50 = ?GivenVa = 10 ft/s, d = 6 ftSlope 2H:1V; repose 41°SF = 1.5 (bend); Ss = 2.65Existing stone 6 in.RequiredD50 and W50Gradation and thicknessIs 6-in. stone adequate?
Embankment toe on the outside of a river bend during the design flood.

Given

VariableValueDescription
Va10 ft/sAverage velocity, design flood
davg6 ftAverage depth
Slope2H:1V (θ = 26.6°)Embankment
φ41°Angle of repose, angular stone
SF1.5Outside of a moderate bend (Table 3.5-10)
Ss2.65Quarried limestone

Required

  • Median stone size and weight
  • Gradation and layer thickness
  • Whether the existing 6-in. stone is adequate

Equations

  1. Eq. 3.5-2: K1 = √(1 − sin²θ/sin²φ)
  2. Eq. 3.5-2: Csg = 2.12/(Ss − 1)1.5; Csf = (SF/1.2)1.5
  3. Eq. 3.5-2: D50 = 0.001CsgCsfVa³/(davg0.5K11.5)
  4. W50 = (π/6)γsD50³; t = max(D100, 1.5D50, 12 in.)

Steps

Step 1 · Slope factor
sin 26.6° = 0.447; sin 41° = 0.656; 1 − (0.447/0.656)²
K1 = 0.732
↓
Step 2 · Corrections
2.12/1.651.5; (1.5/1.2)1.5
Csg = 1.00; Csf = 1.40
↓
Step 3 · Stone size (Eq. 3.5-2)
0.001 × 1.00 × 1.40 × 1,000 / (2.449 × 0.626)
D50 = 0.91 ft = 10.9 in.
Spot check: With SF = 1.2 (a straight reach) D50 would be 0.65 ft (7.8 in.); the bend raises it by the Csf factor of 1.40.
↓
Step 4 · Weight
0.524 × 165.4 × 0.912³
W50 = 66 lb
↓
Step 5 · Gradation and thickness
D100 = 2 × 10.9; D15 = 0.5 × 10.9; t = max(21.9, 16.4, 12)
D100 ≈ 22 in.; D15 ≈ 5 in.; t = 22 in.
↓
Solution
D50 about 11 in. (66 lb), a 22-in. layer on a filter; the existing 6-in. stone is undersized.

Solution

The toe needs riprap with a median size of about 11 in. (66 lb), graded to about 22 in., in a 22-in. layer on a filter, keyed below the scour depth.

The existing 6-in. stone is about half the required size and would move in the design flood; at 6 in. the slope is protected only to about 8 ft/s (the calculator’s chart). Rate the site in the risk assessment accordingly (Chapter 3.8), and specify the nearest standard stone class at or above D50 = 11 in. in the estimate.

Open the riprap calculator →
HEC-11 bank and channel riprap, the Isbash relation for turbulent locations, and HEC-14 culvert outlet aprons, with stone weight, gradation, layer thickness and a stone-size chart.

3.5.11.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • FHWA HEC-11, Design of Riprap Revetment (1989): riprap size equation with specific-gravity and stability-factor corrections; gradation and thickness.Find source ↗
  • FHWA HEC-14, Hydraulic Design of Energy Dissipators for Culverts and Channels (2006): Eq. 10.4, riprap aprons.Find source ↗
  • FHWA HEC-23, Bridge Scour and Stream Instability Countermeasures (2009): riprap at abutments; the Isbash relation.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1: roadway drainage and culverts.Find source ↗