3.5.6 Track and Traffic

Describing the physical setting of a site (ground, water, structures and track) so that everyone working on it starts from the same picture.
Author: Daniel P. Colwell
3.5.6 Track and Traffic

Describe what the track carries, because it sets the consequence of failure (severity in Chapter 3.8) and the loads for design: main or siding, number of tracks, track class and speed, tonnage, passenger and hazardous materials traffic, and the importance of the route (redundancy, detours). Note the geometry-defect and slow-order history at the site and the condition of ballast, shoulder and ditches.