3.5.1 Topography and Landform

Describing the physical setting of a site (ground, water, structures and track) so that everyone working on it starts from the same picture.
Author: Daniel P. Colwell
3.5.1 Topography and Landform

Describe the shape of the ground: elevations, relief, slopes, benches and drainage paths. Lidar (USGS 3DEP 1-m, about 3-ft, DEM) gives elevations at every boring and along every access route for planning; surveyed elevations at the time of drilling replace them in the report.

Example. Ground at the borings of a filled marsh site ranged from El. 581.8 ft to El. 598.5 ft, a relief of about 17 ft. The highest ground was a track-side drive; the wooded center was a hummocky fill surface at about El. 586 to 594 ft; ground fell to about El. 582 to 586 ft along an abandoned spur, where a ditch held standing water. Those few feet decided which borings needed mats and dry weather.

State the source and date of the elevations. Lidar collected years before the work will not show recent fill, stockpiles or ruts, and phone GPS altitudes can differ from lidar by several feet.