D.8 Follow-Up Testing to Replace Typical Values

Starting values for each soil type, read from the three numbers every boring gives: the SPT blow count, the natural moisture content and the liquid limit. Each table names where its values came from, what they cannot be used for, and which tests should replace them.
Author: Daniel P. Colwell
D.8 Follow-Up Testing to Replace Typical Values

List every Appendix D value used in a calculation, then schedule the test that replaces it. The table is ordered from the cheapest screening tests to the definitive tests.

Table D-14: Recommended Follow-Up Testing
Parameter estimated from Appendix DScreening test (every boring)Definitive testWhen the definitive test is needed
Soil classificationVisual-manual (ASTM D2488)Grain size (D6913, D7928) and Atterberg limits (D4318); classification (D2487)Always, for each stratum
Moisture content, unit weightMoisture content (D2216)Unit weight of tube samples (D7263); specific gravity (D854)Settlement, stability and earth pressure analyses
Relative density, φ′ of sandSPT with energy measurement (D1586, D4633)CPTu (D5778); direct shear (D3080) or CD triaxial (D7181) on reconstituted samplesFoundations, walls, liquefaction checks
su of clayPocket penetrometer, torvaneUU triaxial (D2850), unconfined compression (D2166), field vane (D2573), CPTuEmbankments on soft ground; end-of-construction stability; bearing on clay
Effective-stress strength of clayAtterberg limits (Eq. D-7)CU triaxial with pore pressure (D4767); direct shear (D3080)Long-term slope and wall design
Fully softened and residual strengthAtterberg limits and clay fractionRing shear (D6467, D7608)Cut slopes in clay, slide repairs
Compressibility and stress historyMoisture, LL, LIConsolidation (D2435, D4186); CPTu with dissipationFills, structures and embankments on fine-grained soils
Modulus and subgrade reactionSPT, DCP (D6951)Plate load test (D1196), pressuremeter (D4719), seismic methods (MASW)Track modulus, slabs, crane rails, machine foundations
PermeabilityGrain size (Hazen-type estimates)Slug or pumping tests; laboratory permeability (D5084, D2434)Dewatering, seepage, drainage design
Subgrade support (CBR, Mr)DCP (D6951)Laboratory CBR (D1883), resilient modulus (AASHTO T 307)Track subgrade and pavement design (Chapter 7.3)
Organic soilsColor, odor, moistureOrganic content (D2974); long-term consolidationAny fill or structure over organic soil

See Chapter 5.2, Section 5.2.3 for test procedures and Chapter 5.1 for in situ testing.