D.1 Blow Count Corrections and Description Terms

Starting values for each soil type, read from the three numbers every boring gives: the SPT blow count, the natural moisture content and the liquid limit. Each table names where its values came from, what they cannot be used for, and which tests should replace them.
Author: Daniel P. Colwell
D.1 Blow Count Corrections and Description Terms

The tables in this appendix are based on N60, the blow count corrected to 60% of the theoretical hammer energy. Field blow counts must be corrected first; an automatic hammer delivers 80% to 95% energy, so its raw N reads low against the correlations.

N60 = Nfield · Em60 · CB · CS · CR      (N1)60 = CN N60,   CN = √(2,117/σ′v) ≤ 1.7

Eq. D-1 (Skempton 1986; Liao and Whitman 1986; σ′v in psf)

Table D-1: SPT Correction Factors
FactorConditionValue
Em (hammer efficiency, %)Donut hammer / safety hammer (rope and cathead) / automatic trip hammer45 / 60 / 80–95 (measure per ASTM D4633, withdrawn 2025 where possible)
CB (borehole diameter)2.5–4.5 in. / 6 in. / 8 in.1.00 / 1.05 / 1.15
CS (sampler)Standard sampler / sampler without liners1.0 / 1.1–1.3
CR (rod length)< 13 ft / 13–20 ft / 20–33 ft / > 33 ft0.75 / 0.85 / 0.95 / 1.0

Source: Skempton (1986); Youd et al. (2001); ASTM D1586 and D4633 (withdrawn 2025). Full procedure in Chapter 4.1, Section 4.1.3.

Table D-2: Relative Density of Coarse-Grained Soils from N60
DescriptionN60 (blows/ft)(N1)60Relative density, Dr (%)Field feel
Very loose0–40–30–15Easily penetrated with a ½-in. bar pushed by hand
Loose5–103–815–35Easily penetrated with a ½-in. bar
Medium dense11–308–2535–65Penetrated about 1 ft with a ½-in. bar driven by a 5-lb hammer
Dense31–5025–4265–85Penetrated a few inches with a driven ½-in. bar
Very dense> 50> 4285–100Penetrated only a fraction of an inch with a driven bar

Source: Terzaghi and Peck (1948, 1967); (N1)60 bands after Skempton (1986). Dr can also be estimated from Dr = √[(N1)60/46] (Idriss and Boulanger 2008).

Table D-3: Consistency of Fine-Grained Soils from N60
ConsistencyN60 (blows/ft)Unconfined compressive strength, qu (psf)Undrained shear strength, su (psf)Field feel
Very soft0–2< 500< 250Extrudes between fingers when squeezed
Soft3–4500–1,000250–500Molded by light finger pressure
Medium stiff5–81,000–2,000500–1,000Molded by strong finger pressure
Stiff9–152,000–4,0001,000–2,000Indented by thumb
Very stiff16–304,000–8,0002,000–4,000Indented by thumbnail
Hard> 30> 8,000> 4,000Difficult to indent with thumbnail

Source: Terzaghi and Peck (1967); field descriptions per ASTM D2488. su = qu/2.

Limitations. SPT blow counts in clay are a crude measure of strength: the scatter between N and su is commonly a factor of two in either direction. Blow counts in gravel are inflated by large particles, and in saturated silt and fine sand they are affected by pore pressure during driving. Blow counts from a borehole that was not kept full of fluid below the water table can read very low because of heave at the bottom of the hole.