2.1.5 Drainage Elements

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.5 Drainage Elements

Water is the common factor in almost every substructure failure. FRA Track Safety Standards require that drainage and other water-carrying facilities under or immediately adjacent to the roadbed be maintained and kept free of obstruction (49 CFR 213.33). The geotechnical consultant evaluates whether the drainage system can do its job and what happens to the substructure if it cannot.

2.1.5.1 Ditches and Underdrains
  • Side ditches should keep the water table below the subgrade surface. As a practical check, the ditch flow line should sit below the bottom of subballast, with a positive grade to an outlet.
  • Underdrains (perforated pipe in filter aggregate, or geocomposite edge drains) are used where ditches cannot be deep enough. That includes cuts, tight right-of-way, yards, and platforms. Filter compatibility and outlet maintenance govern performance (Chapter 2.3, Section 2.3.8).
  • In multiple-track territory, intertrack drainage is frequently the weak point. Water trapped between tracks saturates the shared subgrade.

Build the drainage first

On new construction and rehabilitation, finish ditches, culverts, subdrains and other earthwork near the track before final subgrade preparation begins. Working in that order keeps equipment off the finished subgrade and soil out of the ballast. It also gives the contractor a site that drains while the track goes in.

  • Inspect subdrains (pipe, filter aggregate, fabric wrap and outlet) before they are covered.
  • Check ditch flow-line elevations and cross sections against the plans before track work starts. A ditch that is too shallow or too flat is far cheaper to correct before ballast is dumped.
  • Direct surface runoff away from geotextile that is placed but not yet covered, so fines do not blind it.

Construction-phase checks for these items are listed in Chapter 5.3, Table 15-S1.

After UFC 4-860-01FA (2004), ch. 9, §4b and §4c. Full reference under Supplemental References.

Choosing the drain type

  • Embankment side slope. This is the most effective side drain when the top of the subgrade is sloped to it and the ballast toe is close by. It handles outlet only, and the shoulder needs protection from erosion.
  • Open ditches. They are economical and carry large storms. Set the grade steep enough to avoid sedimentation but flat enough to avoid erosion, and line the ditch where velocity requires it. They are often neglected. A shallow or lined ditch does nothing for subgrade water.
  • French drains. There are three types: a single fine filter (low capacity), coarse aggregate wrapped in geotextile with AOS ≤ D85 of the protected soil, and a two-zone graded filter. Fabric sized for silt and clay is hard to find.
  • Pipe drains. The filter D85 should be more than 1.2–2 times the slot width and more than 1.0 times the hole diameter. Otherwise, wrap the pipe.
  • Geocomposite fin (edge) drains. They install continuously in a narrow slot and discharge to a carrier pipe. Three wet-subgrade sites on a southeastern railroad, installed in 1984, were performing well after 2 years.
  • Cross drains. They are rarely needed in sand and gravel. In fine soils the spacing they need is uneconomic, so raising the track on a granular blanket or replacing the subgrade is usually better.

Cuts with seepage. Make the side drains deep enough to lower the phreatic surface at least 3–6 ft below the subgrade. The depth depends on permeability, fissuring and pervious seams. Intercept ditches above a cut must not leak into the slope or cut across a critical slip surface.

Figure 2.1-24. Side ditches intercept and divert water and lower the water table.
Figure 2.1-24. Side ditches intercept and divert water and lower the water table.

Ballast pockets that hold water. If severe, reconstruct the substructure. If less severe, reshape the subgrade and replace the subballast and ballast.

After Selig & Waters (1994), ch. 13. Full reference under Supplemental References.

2.1.5.2 Culverts

Culverts pass water beneath the embankment and are foundation elements in their own right. AREMA MRE Chapter 1 covers culvert types, installation, bedding, backfill and cover. The geotechnical scope typically includes:

  • Bearing and settlement of the culvert foundation, especially at the embankment centerline where fill height is greatest.
  • Bedding and backfill specification and compaction adjacent to the barrel. Poorly compacted backfill beside the haunches is a common cause of track settlement over culverts.
  • Corrosion and abrasion potential for metal and concrete pipe. Test soil and water for pH, resistivity, chlorides and sulfates (e.g., ASTM G51, G187, D4327, or the AASHTO T 288–T 291 series as the client requires).
  • Piping and seepage along the outside of the barrel, and through open joints or corrosion holes. Backfill loss into the pipe leaves voids that collapse suddenly under load (Chapter 3.8, Section 3.8.5).
  • Hydraulic adequacy is normally the hydraulic engineer's responsibility. The consequence of overtopping and embankment washout belongs in the ground hazard risk evaluation, though (Chapter 1.1).
Figure 2.1-28. Joint separation and deterioration inside a concrete culvert.
Figure 2.1-28. Joint separation and deterioration inside a concrete culvert.

Sizing drainage: runoff methods and a lesson from the TGV Méditerranée

Water that can reach the subgrade must leave quickly. Give the top of subgrade a 3–5% crossfall toward transverse and longitudinal drainage devices. The book distinguishes two flows to design for: runoff from the track itself (in cut or on fill) and runoff from the contributing catchment. By the rational method:

Figure 2.1-5. Drainage devices along the railway subgrade. Profillidis Fig. 9.4.
Figure 2.1-5. Drainage devices along the railway subgrade. Profillidis Fig. 9.4.
Qp (ft³/s) = c · I · A     (I in in./hr, A in acres)
Table 2.1-2. Runoff coefficients quoted for railway drainage
Surfacec
Track formation0.85
Embankment slope0.3–0.4
Impermeable surfaces0.9–1.1
Cultivated soils0.4–0.8
Sandy soils0.3
Forest0.2

The runoff coefficient is the least certain input and needs judgment. Semi-empirical formulas must be checked against observed flows. For the TGV Méditerranée high-speed line, rainfall-based formulas gave about 90–460 ft³/s per mi² for the 100-year flow, but observed extremes were about 900 ft³/s per mi². The methods were recalibrated to the observations and the minimum diameter of cross-drainage under the track was set at 39 in.. Because rainfall intensity is increasing, the book suggests return periods well beyond the traditional 50–100 years, up to 1,000 years, with the probable maximum flood as the reference flow.

After Profillidis (2014), §9.14.2–9.14.3, Eq. 9.12, Fig. 9.4. Full reference under Supplemental References.

Cardinal rules of drainage, ditch capacity and culvert inspection

Water enters the substructure in three ways: precipitation, surface water (slope runoff and blocked or flooded ditches and culverts), and subsurface seepage. Poor drainage can increase surfacing frequency up to tenfold, increase track buckling 10–30% through loss of shoulder strength, and multiply slow orders. It is deferred because its effects are gradual and are easy to blame on rail, tamping or “soft track.”

Figure 2.1-23. The three entry paths: precipitation, surface water, subsurface seepage.
Figure 2.1-23. The three entry paths: precipitation, surface water, subsurface seepage.
  • Move water across the track at every opportunity and away from the right-of-way quickly; minimize how far it flows in upslope ditches.
  • Keep culvert inlets clear for at least 20 ft, and keep ditches free of vegetation and debris.
  • Maintain ditch gradients of at least 0.5%; keep cutoff ditches at 1–2%.
  • Leave vegetation on slopes; large trees drain and bind the ground.
  • Act on ditch and culvert obstruction long before it looks full: a quarter- or half-blocked channel has already lost much of its capacity.
Figure 2.1-25. Progressive ditch obstruction: capacity falls well before the ditch looks full.
Figure 2.1-25. Progressive ditch obstruction: capacity falls well before the ditch looks full.

Culverts are the most failure-prone drainage element. Check the inlet for scour, small slope failures, sand fill and open joints; the outlet for erosion, ice plugs and seepage; and the barrel for obstructions (beavers, sand, snow, trees) and sink holes over open joints. Open joints in concrete pipe let soil migrate out, leaving a void that collapses as a sink hole (“turtle hole”). Stone-box and blind-stone drains fail the same way through uncemented joints. Crawling the barrel is the only reliable condition check. Older 100-year sizing is being superseded; the course recommends sizing closer to a 500-year storm at many locations and never using pipe smaller than 36 in.

Figure 2.1-26. What to check at a culvert inlet, barrel and outlet.
Figure 2.1-26. What to check at a culvert inlet, barrel and outlet.
Figure 2.1-27. A sink hole opening beneath the ties over a culvert (illustrative risk rating: High).
Figure 2.1-27. A sink hole opening beneath the ties over a culvert (illustrative risk rating: High).
Figure 2.1-29. An old masonry stone culvert with uncemented joints.
Figure 2.1-29. An old masonry stone culvert with uncemented joints.

After Geotechnology for Railroaders Program, Module 4, Module 2; Module 4 §02–04, §07, §09; Module 2 §06. Full reference under Supplemental References.

Supplemental reference · Goswami (2015), Ch. 204

Earth and Train Loads on Culvert Pipes: Rigid and Flexible Pipe Checks

A buried pipe behaves in one of two ways. Rigid pipe (reinforced concrete, clay) does not deflect noticeably and fails by cracking or crushing, so it is rated by strength. Flexible pipe (corrugated metal, HDPE, PVC) deflects, pushes the soil at its sides outward, and relies on that soil for most of its capacity, so it is rated by deflection. The two are checked differently.

Rigid pipe: indirect design. The earth load is found by Marston’s theory, the live load is added, and the total is converted to the load the pipe must carry in a three-edge bearing test. That load, per foot of length per foot of inside diameter, is the D-load used to order the pipe class:

Wd = Cd γ Bd2 (trench condition)    D0.01 = [ WE/Bf + WL/BfLL ] × FS / Di

  • Wd, WE = earth load on the pipe (lb/ft); Cd = load coefficient, which depends on trench depth to width, the friction of the backfill on the trench walls and the bedding; γ = backfill unit weight (pcf); Bd = trench width at the top of the pipe (ft).
  • WL = live load on the pipe (lb/ft); Bf, BfLL = bedding factors for earth and live load, which relate the field load to the three-edge test load and rise with better bedding; FS = factor of safety; Di = inside diameter (ft).

Rigid pipe: direct design. The pipe is designed in its installed condition for bending moment, thrust and shear, checking reinforcement tension, concrete compression, radial tension, diagonal tension and crack width. It is more flexible than indirect design and avoids the conservatism built into the bedding factors.

Flexible pipe: deflection. Deflection is estimated with the Modified Iowa equation, in a simplified form:

Δy / D = K (DL P + W′) / (0.149 PS + 0.061 E′)

  • P = prism (overburden) load at the crown (psi); W′ = live load at the crown (psi); DL = deflection lag factor (1.0 to 1.5) for long-term consolidation of the side soil; K = bedding constant (about 0.1); PS = pipe stiffness (psi); E′ = modulus of soil reaction of the side fill (psi), which rises sharply with the degree of compaction.
  • Plastic pipe reaches reverse curvature of the crown, taken as failure, at about 30% deflection; the usual industry limits of 5% to 7.5% therefore carry a safety factor of roughly 4 to 6.

For railroad work: Culverts under track carry Cooper E-80 axle loads at shallow cover, so the live load term usually governs the rigid-pipe D-load and the flexible-pipe deflection. Compute the E-80 load at the crown with impact (Chapter 7.1, Section 7.1.3), use the owner’s minimum cover under base of rail, which is far greater than highway minimums (Chapter 3.3, Section 3.3.10), and specify the bedding class and side-fill compaction the design assumes, because both change the result more than the pipe class does. A flexible culvert under track should also be checked for deflection measured in the field after backfill (Chapter 5.3).

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 204, Load on Buried Pipes. Full reference under Supplemental References.