2.1.2 Embankments
Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Most North American main lines were built between 1850 and 1920 on embankments that were end-dumped or
wagon-placed with little or no compaction, then raised repeatedly by adding ballast. The result is a layered, variable
fill that bears little resemblance to a modern engineered embankment.
2.1.2.1 Characteristics of Historic Railroad Embankments
Composition: Locally borrowed soil, often from side ditches, with inclusions of cinders, slag, ash,
timber (old trestles buried in place), boulders and debris.
Ballast pockets and "ballast bulbs": Decades of surfacing drive ballast down into soft fill, forming
water-holding pockets that soften the surrounding soil (Chapter 2.3, Section 2.3.5).
Low density: SPT N-values in uncompacted cohesive fill are commonly low and erratic; do not assume
the body is uniform from a single boring.
Buried structures: Old culverts, abandoned trestle bents and timber cribbing may exist inside the fill
and are a recognized source of sudden subsidence as they decay (Chapter 1.1, Section 1.1.3).
2.1.2.2 New Embankments and Widening
New fill for sidings, second main track or grade raises should be placed and compacted to the client specification.
Typical practice, to be confirmed against the governing client standard:
Loose lift thickness typically 8 in. (thinner for hand-operated equipment).
Compaction to a specified percentage of maximum dry density by ASTM D698 (standard Proctor) or ASTM D1557
(modified Proctor), with higher density usually required in the upper few feet beneath the subballast.
Moisture within a specified range of optimum, verified by ASTM D6938 (nuclear gauge) or ASTM D1556 (sand cone)
testing at a stated frequency (Chapter 5.3).
When widening an existing embankment, bench the new fill into the existing slope so the new material
does not sit on a smooth, weak interface. Remove vegetation, topsoil and loose sloughed material first.
Match or improve on the drainage characteristics of the existing fill. A less permeable widening placed against a
free-draining old fill can trap water and raise the phreatic surface in the original embankment.
2.1.2.3 Embankment Stability and Deformation Checks
Evaluate embankment side-slope stability using Chapter 6.3 methods, with the design train surcharge applied
(Cooper E-80 converted to an equivalent strip load, per client criteria). A minimum static factor of safety of 1.5 is the
common target (Chapter 1.1, Section 1.1.2); confirm with the client. Evaluate settlement of new fill on the foundation using
Chapter 6.2 methods, and design ground improvement where needed using Chapter 7.2, including the Section 7.2.16 technology library.
Embankment slopes, benching and overbuild
Commonly used embankment side slopes (horizontal : vertical) quoted from Bowles: 1.5–2 : 1 for usual soils and 2 : 1 for gravel and sand and for erosion-prone soils. Slopes must follow from the geotechnical study, and the foundation beneath the embankment must be evaluated as well as the fill.
Where the original ground slopes steeper than 1 : 10, bench (step) the base before placing fill (Figure 2.1-2).
Overbuild the initial width and height to allow for post-construction compaction of the fill (Figure 2.1-3).
For very tall embankment sides, use a retaining wall or reinforced soil designed for earth pressure and train surcharge (Figure 2.1-4; see Chapter 7.1).
Compact a formation layer, where used, to 100% Standard Proctor and the embankment body to 95% (Chapter 2.3, §2.3.4).
Figure 2.1-2. Benching (stepping) the embankment base on steep ground. Profillidis Fig. 9.14.Figure 2.1-3. Increased initial width (Δb) and height (Δh) to allow for compaction of the fill. Profillidis Fig. 9.15.Figure 2.1-4. Retaining wall at the toe of a very tall embankment side. Profillidis Fig. 9.16.
After Profillidis (2014), §9.12.2, Figs. 9.14–9.16; slope values after Bowles (2001). Full reference under Supplemental References.
Century-old fill: what is actually under the track
Most mainline track is over 100 years old. It was often built without sub ballast, for lighter and slower traffic, by observational methods with a low factor of safety and compaction below modern standards. The core of the original fill can still be loose. Because train loads act mainly to about 5–10 ft below the ties, only the upper few feet reflect later work, and the rest is as built. Construction history is therefore worth recovering before planning a subgrade repair.
Figure 2.1-13. Original embankment construction: the core of many mainline fills.Figure 2.1-14. Horse-drawn construction methods, well over a century ago.Figure 2.1-15. Track construction in the transcontinental era.
After Geotechnology for Railroaders Program, Module 3; §03. Full reference under Supplemental References.