2.1.4 Foundation Soils Beneath Embankments

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.4 Foundation Soils Beneath Embankments

The foundation is the natural ground on which the embankment rests. Its behavior controls long-term settlement, deep-seated stability, and the response to new loading such as heavier cars, a second track or a grade raise.

Foundation ConditionWhy It MattersKey TestsSee
Soft to medium clayConsolidation settlement; undrained failure under new fillASTM D2435 (consolidation), D2166 / D4767 (strength), field vane D2573, CPTu D5778Chapters 6.2, 6.3
Organic soil, peat, muskegLarge primary and secondary compression; "muskeg punching"ASTM D2974 (organic content), D2435Chapters 1.1, 6.2
Sensitive and quick claysBrittle failure with little warning; retrogressive slidesField vane (peak and remolded), D4648 laboratory miniature vaneChapters 1.1, 6.3
Loose saturated sands and siltsLiquefaction and cyclic softeningSPT D1586, CPT D5778, fines content D1140Chapter 6.5
Collapsible soils (loess, some alluvium)Sudden settlement on wettingASTM D4546 (collapse potential)Chapter 3.8
Karst (soluble bedrock)Sinkholes, raveling voids above bedrockGeophysics (ASTM D6429 guide), probe borings, rock coringChapters 3.8, 5.1
Undermined groundMine subsidence (sag and pit)Mine maps, borings to mine level, monitoringChapter 3.8

Borings for embankment evaluation should extend through the embankment and at least through the compressible or weak foundation layers into competent material. Use the depth criteria in Chapter 3.9.

Embankments on peat, muskeg and soft clay

A peat bog forms as vegetation fills a dying lake, and part of it may float on lacustrine soil. Its limited strength comes from intertwined fibers, so ditching or cable plowing that cuts them can turn a quiet section into a problem site. Old track over muskeg often sits on a corduroy mattress of crosswise logs; where it has decayed, peat pumps up through the gaps under traffic. Organic soils can compress by up to about 40%: 12 ft of peat can mean 5 ft of settlement. Excavate thin peat; build over thick peat and let it settle.

Figure 2.1-16. Peat bog formation as a lake fills with vegetation from the fringe inward.
Figure 2.1-16. Peat bog formation as a lake fills with vegetation from the fringe inward.
Figure 2.1-18. Track deflecting over muskeg (illustrative risk rating: High).
Figure 2.1-18. Track deflecting over muskeg (illustrative risk rating: High).
Figure 2.1-19. Track through deep muskeg on a Canadian main line.
Figure 2.1-19. Track through deep muskeg on a Canadian main line.

On soft clay or peat, an embankment can fail at its base as soft soil squeezes out from under the load. On peat, a stabilizing berm should be about twice as wide as the peat is deep, built in thin lifts over geogrid or woven geotextile, and never placed after removing the peat crust.

Figure 2.1-17. Base failure: soft clay squeezing out from under the embankment.
Figure 2.1-17. Base failure: soft clay squeezing out from under the embankment.

After Geotechnology for Railroaders Program, Module 2, Module 3, Module 5, Module 6.1; Module 2 §07, §08; Module 5 §06; Module 6.1 §03. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).