2.1.10 Investigation Matrix for Foundation Elements

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.10 Investigation Matrix for Foundation Elements

Use this matrix together with the investigation planning criteria in Chapter 3.9 and the laboratory program in Chapter 5.2.

ElementField ExplorationLaboratory Tests (ASTM)Deliverable Focus
Embankment bodyBorings through crest and shoulders (SPT D1586), CPT D5778, test pits; GPR for bed layering (ASTM D6432 guide)D2487 / D2488 classification, D4318 limits, D6913 gradation, D2216 moistureFill composition, ballast pockets, water in fill, stability
Cut floor and slopesBorings or test pits at formation, groundwater observation wellsD4318, D4546 swell, D4829 expansion index, D3080 direct shearSoftening potential, seepage, slope stability
Foundation soilsBorings to competent layer; undisturbed sampling (D1587); field vane D2573; CPTuD2435 consolidation, D2166 / D4767 strength, D2974 organic content, D4546 collapseSettlement, deep stability, improvement need
CulvertsBorings at inlet, outlet and centerline; camera inspection of barrel; void detection (GPR or probing)Classification; pH, resistivity, chloride and sulfate (G51, G187, D4327)Bearing, backfill condition, corrosion, piping
Bridge approaches and structuresBorings at each substructure unit; rock coring (D7012 for strength); scour-related samplingStrength, consolidation, rock strength and RQDFoundation type and capacity, approach settlement, scour
Utility crossingsLocate and verify depth; borings along the alignment; monitoring pointsClassification, moisture, groundwaterSettlement and heave limits, monitoring plan