2.1.11 Performance Criteria

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.11 Performance Criteria

Foundation elements are ultimately judged by their effect on track geometry. FRA 49 CFR 213.63 sets surface (profile, cross-level and warp) limits by track class. A foundation that causes geometry to exceed those limits between normal maintenance cycles is not performing, whatever its calculated factor of safety.

CriterionCommon Target (confirm with client)Where Evaluated
Static slope stability, embankments and cutsFS ≥ 1.5 with design train surchargeChapter 6.3
Subgrade and foundation bearing under cyclic loadFS ≥ 3.0 on undrained bearing (Chapter 2.3 method)Chapters 2.3, 6.1
Post-construction settlement of new fillLimited so that geometry remains correctable by routine surfacing; client-specificChapter 6.2
Differential settlement at transitionsMinimized; evaluate over the transition length rather than as a single numberChapters 2.3, 6.2
Culvert and structure foundationsPer AREMA MRE Ch. 8 and the client's structure standardsChapter 6.1

European track-geometry limits for comparison

European practice sets three tiers of geometry limits: intervention values that trigger scheduled maintenance, acceptance values allowed to remain after maintenance, and emergency values that require an immediate speed restriction. FRA Track Safety Standards (49 CFR Part 213) and client standards govern in North America; the European figures are given to show how tight track-support performance has to be.

Table 2.1-3. Emergency values of track defects and maximum permitted speed
Longitudinal defect LD (in.)Horizontal defect HD (in.)Maximum speed (mph)
≥ 0.71≥ 0.5987
≥ 0.79≥ 0.6775
≥ 0.91≥ 0.7562
≥ 1≥ 0.8750
≥ 1.1≥ 137
≥ 1.2≥ 1.125
Figure 2.1-11. Intervention limits for longitudinal, transverse and horizontal defects, twist and gauge, by speed, for DB, SNCF, NS, BR and UIC. Profillidis Table 16.2.
Figure 2.1-11. Intervention limits for longitudinal, transverse and horizontal defects, twist and gauge, by speed, for DB, SNCF, NS, BR and UIC. Profillidis Table 16.2.

33-ft measurement base. LD = surface (profile), HD = alignment.

Table 2.1-4. Limits on track-gauge variation, European interoperability specifications
Speed (mph)Minimum gauge deviation (in.)Maximum gauge deviation (in.)
V ≤ 50−0.35+1.4
50 < V ≤ 75−0.35+1.4
75 < V ≤ 99−0.31+1.4
99 < V ≤ 143−0.28+1.1
V > 143−0.2+1.1

The European interoperability specifications also limit twist to 0.084 in./ft for speeds up to 124 mph and 0.06 in./ft above, adjusted for measurement base length (Figure 2.1-12), and limit the difference between nominal and actual cant to ±0.79 in..

Figure 2.1-12. Twist limit vs. measurement base length, conventional and high-speed track. Profillidis Fig. 16.7.
Figure 2.1-12. Twist limit vs. measurement base length, conventional and high-speed track. Profillidis Fig. 16.7.

After Profillidis (2014), §16.6, Tables 16.2, 16.4, 16.5, Fig. 16.7. Full reference under Supplemental References.