2.1.1 Defining Track Foundation Elements

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.1 Defining Track Foundation Elements

For this manual, the track substructure is divided into the track bed (ballast, subballast and the prepared top of subgrade, covered in Chapter 2.3) and the foundation elements beneath and alongside it. The distinction matters because the two groups are maintained, inspected and funded differently.

Foundation ElementFunction for the TrackGoverning ReferencesTypical Geotechnical Concern
Embankment (fill) bodyRaises the formation to grade; carries track load to the foundationAREMA MRE Ch. 1 (Roadbed); client earthwork specsUncompacted historic fill, ballast pockets, side-slope instability
Cut section and cut slopesLowers formation to grade through high groundAREMA MRE Ch. 1 (Roadbed)Seepage, softening of cut floor, slope raveling, rockfall
Foundation soils beneath fillsSupports the embankment and train loadAREMA MRE Ch. 1; Chapters 5.1–5.3Soft clay, organics, sensitive or collapsible soils, karst
Drainage elements (ditches, underdrains, culverts)Keep water out of and away from the substructureAREMA MRE Ch. 1 (Culverts); 49 CFR 213.33Blockage, piping along barrels, corrosion, overtopping
Bridge approaches and transition zonesTransition between ballasted track and a rigid structureAREMA MRE Ch. 1 and Ch. 8; 49 CFR Part 237Differential settlement ("bump"), stiffness change, backfill loss
Structural foundations adjacent to trackSupport bridges, walls, retainers, signal and catenary structuresAREMA MRE Ch. 8; client standardsSurcharge from train load, scour, settlement, lateral movement
Crossings, turnouts and special trackworkCarry concentrated and impact loadsAREMA MRE Ch. 1 and Ch. 5; client standardsPoor drainage, pumping, rapid geometry loss
Utility and pipeline crossingsThird-party facilities within the substructureAREMA MRE Ch. 1 (Pipelines); client utility-crossing rulesSettlement or voids from leaks, trench backfill, casing failure
Railway Track Foundation and Structure
Railway Track Foundation and Structure
Foundation Settlement
Foundation Settlement

The consultant's responsibility is to identify which of these elements are present at a site, which one governs performance, and whether its condition is changing. A site that "just needs surfacing" every year is rarely a ballast problem — it is usually one of the elements in this table.

Ballasted track and slab track

Ballasted track is a flexible support; slab track (concrete slab or asphalt over a ballast-concrete layer and an anti-frost layer) is an inflexible support. Ballasted track remains the norm because it tolerates differential settlement, costs much less to build and gives good lateral resistance even at high speed. Slab track is most effective in tunnels, where it allows a smaller cross-section and reduces maintenance, but it is noisier.

Figure 2.1-1. Ballasted track (a) and slab track (b): layer sequence from tie to subsoil. Profillidis Fig. 7.4.
Figure 2.1-1. Ballasted track (a) and slab track (b): layer sequence from tie to subsoil. Profillidis Fig. 7.4.

The choice turns on construction cost (much higher for slab), maintenance cost (much higher for ballast) and the technical needs of the site. German figures from 2008 put slab track at €175–207 per foot against €111 per foot for ballasted track, before the extra earthwork and subgrade work that slab track needs. Slab-track maintenance was reported at about 10% (Germany) to 20–30% (Japan) of the ballasted-track figure. For a slab the subgrade must be essentially settlement-free, which moves the geotechnical risk from maintenance into design and construction.

After Profillidis (2014), §7.3, §17.8, Fig. 7.4. Full reference under Supplemental References.