2.1.16 Case Studies

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S5 under Supplemental References.

Case Study 3.16.1 — Thirty-year-old expansive clay embankments: where the moisture really settles
Case study · Look (2023) §10.15

Related section: 2.1.2 Embankments

Earthworks for the 4.4 mi Cooroy Bypass, north of Brisbane, were in highly reactive clays (weighted plasticity index 2200–3200). In 1990, time domain reflectometry (TDR) probes were installed in two trenches about 4.3 mi apart in existing 30-year-old embankments of the same clay, built at MDD and OMC to the specification of their day (Look and Reeves, 1992). Findings:

  • The seasonally active zone reached below 5.9 ft, not the 5 ft assumed. Swell tests showed that movement at that depth is suppressed by overburden, so the “stable zone” is a no-movement zone even with minor moisture change.
  • In service, stable-zone moisture was 1.2–1.3 times standard OMC, and density had dropped to 92%–94% of standard MDD although the fills were built at MDD. Clay placed drier will wet up, swell and lose strength.
  • Peak moisture tracked the 50-day moving average of rainfall; the low point of the drying phase tracked the 300-day average.

Recommended design: subgrade CBR 3%; target density 92%–94% of standard MDD with characteristic limits of 90%–96%; target moisture 110%–130% of standard OMC. A three-section trial embankment placed at 1.0, 1.2 and “as wet as possible” times OMC converged to a similar moisture within nine months, again 110%–130% of OMC, confirming the approach. During construction, TDR probes and horizontal profile gauges set the curing period before the pavement went on.

Key lessons: zone the clay, with a 8.2 ft side zone matching the measured movement from the batter; specify an upper density limit so that compaction at or above 100% MDD fails for these clays where rainfall exceeds about 39 in a year; target the equilibrium moisture; and allow curing before final layers.

For railroad work: fat-clay embankments on many North American lines show the same seasonal movement, expressed as recurring surface and cross-level defects. When rebuilding or widening such fills, compacting the clay hard and dry is not conservative.

Moisture in the stable zone at about 6 ft depth in two trenches 4.3 mi apart, against daily rainfall (Look 1996).
Figure 3-LK1. Moisture in the stable zone at about 6 ft depth in two trenches 4.3 mi apart, against daily rainfall (Look 1996). Source: Look (2023), Figure 10.15-4, p. 363.
Trial embankment: all three placement moistures converged to a similar moisture within about 9 months (Look 1996).
Figure 3-LK2. Trial embankment: all three placement moistures converged to a similar moisture within about 9 months (Look 1996). Source: Look (2023), Figure 10.15-5, p. 365.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §10.15, pp. 360–366. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 3.16.2 — Four materials in one 1,300 ft cutting
Case study · Look (2023) §8.9

Related section: 2.1.3 Cut Sections and Cut Slopes

A cutting of about 392,000 yd³ was to supply embankment fill. Over 1,310 ft its cross sections showed four material types, defined so estimators could plan equipment:

  1. residual soil and extremely weathered rock: easy digging
  2. highly weathered rock: hard digging; seismic velocity typically 3,600–5,250 ft/s
  3. moderately to slightly weathered rock: easy to hard ripping; velocities up to 7,900 ft/s
  4. a microdiorite dike and fresh volcanolithic sandstone at depth: hard ripping with a D11, point load index typically above 580 psi

The preliminary borings no longer lined up with the final alignment. Transport bulking ranged from 20% to 70%, and from 0% to 30% after compaction. Types 1–3 behaved as “soil” once compacted, controlled by density testing. Type 4 was suitable as rock fill and could have been crushed on site for drainage or pavement material, but a nearby quarry made that uneconomic.

For railroad work: the same breakdown suits a rail cut balanced into fill. Re-check the borings against the final alignment and have each material type carry its own excavation method, bulking factor and end use. The tender view of this same cut is in the next box.

Cut 3 cross sections over 1,300 ft; preliminary borings are offset from the final alignment and a microdiorite dike crosses at Ch. 75,550.
Figure 3-LK3. Cut 3 cross sections over 1,300 ft; preliminary borings are offset from the final alignment and a microdiorite dike crosses at Ch. 75,550. Source: Look (2023), Figure 8.9-1, p. 269.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §8.9, pp. 268–270. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 3.16.3 — Earthworks tender assessment for a balanced cut-to-fill job
Case study · Look (2023) §14.14

Related section: 2.1.3 Cut Sections and Cut Slopes

Look follows the same Cut 3 into the tender stage of a “balanced” job with six cuttings feeding the embankments. The quantities were bank volumes. Each cut had its own rock type, quantity and quality, and had to be assessed on its own merit from source to destination. For each material type the contractor set out depth, class and the best equipment, from scrapers in the top 6.6 ft to a D9 for rock fill between about 16 and 43 ft.

The assessment ran in three steps: excavation; bulking and transport; and placement. Transport bulking and post-compaction bulking have to be treated separately. The balance quantity for each source, its location, matching sources to nearby fills, and zoning of the embankments all formed part of the assessment.

For railroad work: a rail grading contract that is “balanced” on bank volumes can still come up short once bulking, breakdown and material zoning are counted. Ask bidders to show the assessment by source and material type.

Tender assessment for Cut 3: material types, approximate depths, class and suitable equipment (scraper, D7, D9).
Figure 3-LK4. Tender assessment for Cut 3: material types, approximate depths, class and suitable equipment (scraper, D7, D9). Source: Look (2023), Figure 14.14-2, p. 553.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §14.14, pp. 550–552. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 3.16.4 — As-constructed drawings that were wrong
Case study · Look (2023) §3.7

Related section: 2.1.9 Utility and Pipeline Crossings

As-constructed drawings are assembled at the end of a project, from second- and third-hand notes, when funds are nearly spent. Look gives three examples from his early site-investigation career:

  • Bridge boring. The water authority’s plans and a joint inspection placed a sewer main on the east side of the bridge. A farmer who had worked the adjacent land for 40 years stopped as the rig set up on the west side and pointed out two buried access chamber covers: the sewer bowed to the west and back. His knowledge was better than the asset owner’s.
  • Empty industrial lot. The owner’s plans showed all services south of his building, and he was sure one 3 in boring could go anywhere in the 330 ft × 197 ft lot. Within 15 minutes the rig hit a high-pressure water main. On area alone the odds were under 0.001%; repairs took half a day.
  • City site. Records checks, sign-off by every service authority and a locator produced an approved 49 ft service-free triangle. A pre-1950 gas main without a tracer band was not on the plans and could not be located. It was hit within 15 minutes; five blocks were evacuated and the city was closed to traffic for hours.

For railroad work: railroad corridors carry fiber, signal cable and pipelines installed by others over a century or more, often under old permits with poor location data. Treat records as a starting point, pothole or vacuum-excavate before drilling within the right-of-way, and ask track and signal forces what they know about the location.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §3.7, pp. 90–92. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.