2.1.7 Structural Foundations Supporting or Adjacent to the Track

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.7 Structural Foundations Supporting or Adjacent to the Track

Bridges, retaining walls, ballast retainers, signal and communication structures and overhead catenary supports all have foundations within the zone influenced by train loading. AREMA MRE Chapter 8 covers the design of concrete structures and foundations for railway loading, and client standards add their own requirements.

2.1.7.1 Foundation Types
Foundation TypeTypical Railroad UseKey Geotechnical InputsSee
Spread footingsAbutments and piers on competent soil or rock; walls; signal basesBearing capacity, settlement, frost depth, scour depthChapters 6.1, 6.2
Driven piles (steel H, pipe, precast concrete, timber)Bridge abutments and piers; trestle replacementAxial and lateral capacity, drivability, downdragChapter 6.1
Drilled shaftsPiers, catenary and signal foundations, wallsSide and tip resistance, lateral response, groundwater and cavingChapter 6.1
Micropiles and helical pilesLimited access and under-track work; retrofit of existing structuresGrout-to-ground bond, buckling in soft soilsChapter 7.2 (7.2.16)
Sheet piles and soldier piles with laggingBallast retainers, temporary and permanent shoringEarth pressure with train surcharge, embedment, drainageChapter 7.1
2.1.7.2 Train Surcharge and the Influence Zone

Any excavation or structure close to an operating track must be designed for train surcharge. Class I railroads publish shoring guidelines that define a live-load influence zone projected from the track. Excavations and temporary works within it require railroad-reviewed design and monitoring (e.g., the guidelines for temporary shoring issued jointly by two Class I railroads). Treat the client's current guideline as governing. Lateral earth pressure from the surcharge is evaluated using the methods in Chapter 7.1.

2.1.7.3 Scour at Structure Foundations

Scour at piers and abutments is one of the leading causes of bridge failure. Foundations in waterways must be evaluated for total scour (long-term degradation, contraction and local scour) following FHWA HEC-18 and the bridge owner's scour program. The geotechnical deliverable should state the soil or rock erodibility, the scour depth used, and whether the foundation remains stable at that depth.

Overhead catenary pole foundations

Catenary poles (cast or galvanized steel, prestressed or reinforced concrete) are spaced 164–246 ft, depending on pantograph oscillation, locomotive sway and climate. Excavation and backfill must be done carefully to keep ground settlement to a minimum (Figure 2.1-7).

Figure 2.1-7. Erection of electric traction poles at a double track in cut and on fill. Profillidis Fig. 20.15.
Figure 2.1-7. Erection of electric traction poles at a double track in cut and on fill. Profillidis Fig. 20.15.

On good subgrade the pole is set in an embedded block whose overturning moment is resisted by lateral soil pressure, M = c · B · L3, where B is the block width, L the embedment depth and c a coefficient that depends on the soil (Figure 2.1-8). On poor subgrade the poles are founded on a concrete slab, typically 6.6 ft × 11 ft at a depth of 3.6–4 ft.

Figure 2.1-8. Pole foundation on good-quality subgrade: lateral pressure distribution and M = c·B·L3. Profillidis Fig. 20.16.
Figure 2.1-8. Pole foundation on good-quality subgrade: lateral pressure distribution and M = c·B·L3. Profillidis Fig. 20.16.

Pole foundations sit in the shoulder, often on embankment edges. They should be included in slope-stability and settlement checks when a shoulder is steepened or a fill is widened.

After Profillidis (2014), §20.9, Figs. 20.15–20.16. Full reference under Supplemental References.