↑ Parent Menu⌂ Main Menu
← Chapter 2.1 Track Foundation Elements
GHRM
Railway Ground Hazard Risk Management · 2.0 · The Underworld
Sections · click a car to open it

2.1.9 Utility and Pipeline Crossings

Everything beneath the subgrade surface that the track depends on — embankments, cuts, foundation soils, drainage structures, bridge approaches and the structural foundations that share the right-of-way.
Authors: Daniel P. Colwell and Mario Ruel
2.1.9 Utility and Pipeline Crossings

Pipelines and utilities crossing beneath the track are third-party foundation elements. AREMA MRE Chapter 1 and client utility-crossing standards govern casing, depth of cover, installation method and inspection. From a ground hazard standpoint:

  • Leaking water and sewer lines erode fines and create voids. This is a recognized cause of sudden subsidence beneath track (Chapter 1.1, Section 1.1.3).
  • Poorly compacted open-cut trench backfill settles and produces a local geometry defect.
  • Trenchless installations (bore and jack, horizontal directional drilling, microtunneling) can cause heave or loss of ground if face pressure, overcut or grouting are not controlled. Require settlement monitoring points on the track during installation (Chapter 5.3).

A fiber-optic installation done wrong

A fiber-optic cable installation along a shoulder destabilized the slope by breaking nearly every rule at once. Crews excavated at the toe, overloaded the shoulder with spoil, and then left the ditch unmaintained because the cable running through it discouraged cleaning. Support later placed only at the shoulder, with none at the toe, made it worse. For any utility work in the right-of-way: do not excavate at the toe, do not overload the shoulder, keep ditches drained whatever runs through them, and do not let water seep into the shoulder or fill.

Figure 2.1-34. Fiber installation: toe excavation and shoulder overload both apply.
Figure 2.1-34. Fiber installation: toe excavation and shoulder overload both apply.
Figure 2.1-35. A problematic fiber-optic cable slot along the shoulder.
Figure 2.1-35. A problematic fiber-optic cable slot along the shoulder.
Figure 2.1-36. Riprap at the shoulder with none toward the toe: the wrong way around.
Figure 2.1-36. Riprap at the shoulder with none toward the toe: the wrong way around.

After Geotechnology for Railroaders Program, Module 5, Module 6.1; Module 5 §10; Module 6.1 §03. Full reference under Supplemental References.

Case study: 2.1.16.4 As-constructed drawings that were wrong (Look 2023), in §3.16 Case Studies.

← Previous · 1.0 Introduction Chapter 1.1 — Introduction to Railway Ground Hazard Risk Management
Next · 2.0 The Underworld → Chapter 2.2 — Soil and Rock Classification