Fouled ballast is the most common reason a track section stops draining. The fines come mostly from ballast breakdown, with contributions from infiltration from the surface (coal, ore, wind-blown soil), the subballast and the subgrade (pumping). Coarse broken particles do little harm and may even stiffen the ballast, but as fines accumulate they hold water, the voids clog, and geometry deteriorates fastest where fouled ballast and poor drainage occur together.
Equation 6.4-5. Fouling indices
P = percent passing the sieve (sizes in mm; No. 4 and No. 200 in FI).
Equation 6.4-6. Void contaminant index and fouled conductivity
e = void ratio, Gs = specific gravity, M = dry mass; b = fresh ballast, f = fouling material.
| Category | FI | Passing 3/4 in. (one railroad's single-sieve criterion) |
|---|---|---|
| Clean | < 1 | – |
| Moderately clean | 1 to < 10 | < 25% |
| Moderately fouled | 10 to < 20 | 25 to 40% |
| Fouled | 20 to < 40 | 40 to 50% |
| Highly fouled | ≥ 40 | > 50% |
Intervention levels: FI 30 (drainage reduction) and 40 (highly fouled); four-sieve index 80; 40% passing 3/4 in.; European agencies use 30% passing 14 mm or 22.4 mm.
| kb/k | Drainage |
|---|---|
| ≤ 3 | Free |
| 3 to 30 | Very good |
| 30 to 300 | Good |
| 300 to 3,000 | Acceptable |
| 3,000 to 300,000 | Poor |
| 300,000 to 30,000,000 | Very poor |
| > 30,000,000 | Relatively impervious |
The fouling index counts the fines twice because they control permeability, but sieving to the No. 200 in the field is impractical, so single-sieve criteria are used for field decisions. Mass-based indices also ignore the type of fines. The VCI measures the share of the ballast voids actually filled, and it is the only one of these measures that accounts for the low specific gravity of coal. At the same 15% fouling by mass, laboratory tests gave about 78% VCI for coal, 65% for clay and 52% for sand, while FI barely separated coal from sand. Above about 40% VCI, geogrid reinforcement adds little and ballast strength falls noticeably.
| Result | Value |
|---|---|
| Fouling index | 16.0 (moderately fouled) |
| Four-sieve index | 20.3 |
| Void contaminant index | 21.0 % |
| Drainage, silty or coal fines (kf = 2.8 ft/day) | Poor drainage (kb/k = 8,547) |
| Drainage, clay fines (kf = 0.03 ft/day) | Very poor drainage |
None of the mass-based indices calls for cleaning, yet with clay fines filling a fifth of the voids the ballast drains very poorly. Where wet spots persist, test the fines (Atterberg limits, specific gravity) before deciding between shoulder cleaning, undercutting and subgrade work.
Open the ballast fouling calculator →
Fouling index, four-sieve index, single-sieve category, void contaminant index, fouled conductivity and drainage class.
These documents are in the reference library. The method summaries above are paraphrased; equations are standard or published forms.