6.4.3 Steady Seepage and Flow Nets

How rainfall and water move into and through railroad fills, slopes and subgrade, how that is measured, and what it does to stability.
Author: Daniel P. Colwell
6.4.3 Steady Seepage and Flow Nets

Where water stands against a fill for long enough (a blocked culvert, a pond, a river stage that lasts days), flow through the fill approaches steady state. Darcy's law governs the flow, and a flow net (or a seepage model) gives the head everywhere in the fill, the exit gradient at the toe and the quantity of seepage.

Equation 6.4-3. Darcy's law and seepage quantity

q = k i A    Q = k H (Nf / Nd) per unit length

where k is hydraulic conductivity, i the hydraulic gradient, A the area, H the head difference, and Nf, Nd the numbers of flow channels and equipotential drops in the flow net.

Seepage exerts a force on the soil skeleton equal to the gradient times the unit weight of water, acting in the direction of flow. At the downstream toe the flow turns upward and outward, which is why the toe softens, sloughs and is the first place to show distress. For dam and levee-type fills the Kozeny parabola gives a quick phreatic line through a homogeneous section.

Foundation soilEmbankment fillWater ponded against the fill (blocked culvert)Culvert, inlet blockedPhreatic lineSeepage exits at the toe: softening, sloughing, pipingTrack on the crest
Figure 6.4-2. Railroad fill with water ponded against one side behind a blocked culvert. The phreatic line drops through the fill and exits near the downstream toe, where seepage forces soften the toe and can start piping.
Permeability and seepage. Flow nets and seepage forces explain why the toe of a fill with water against it is where distress first appears.
Figure 6.4-3. Permeability and seepage. Flow nets and seepage forces explain why the toe of a fill with water against it is where distress first appears.