6.4.7 Field Infiltration Testing

How rainfall and water move into and through railroad fills, slopes and subgrade, how that is measured, and what it does to stability.
Author: Daniel P. Colwell
6.4.7 Field Infiltration Testing

Where a design depends on water going into the ground (an infiltration basin, a storm chamber system), measure it. The borehole (single-ring) test below follows a municipal stormwater ordinance procedure that is widely used in the Midwest.

Table 6.4-5. Borehole infiltration test procedure (summary)
StepRequirement
Soil boringExtend at least 5 ft below groundwater; bag samples of each layer between the system bottom and the water table for sieve analysis; density and moisture of each layer; water at drilling and 24 hours; log by USDA texture
Test locationAt least 5 ft from the boring, or a horizontal distance equal to the depth from test bottom to water table, whichever is greater
SetupDrill to the test depth; push a PVC pipe 3 in. below the bottom; bentonite seal in the annulus; clean, uniform bottom; cap the pipe
Pre-soakFill the pipe and let it drain to saturate the soil; record the volume added
ReadingsRecord time and depth at intervals that give about 3 in. or less of decline; when within 12 in. of the bottom, refill to 24 in. above the bottom
EndRepeat until the rate of decline is constant, then two more cycles
TimingSome agencies do not allow testing within 24 hours after rain
06012018024002468Elapsed time (min)Rate (in./hr)Long-term rate K, ordinance methodFalling-head estimate (Hvorslev-type)
Figure 6.4-5. Results of a 4.4-hour borehole infiltration test in sand. The observed rate of decline stayed between about 13 and 24 in./hr late in the test; the ordinance method gave a long-term rate of about 2 to 3 in./hr, and the falling-head estimate settled at about 0.4 to 0.7 in./hr. The spread is why the method, the water table correction and the factor of safety must be stated with any design value.

The ordinance equations assume the wetting front stays above the water table; where it reaches the water table, the equations must be modified, as the worksheet does. Check the field value against grain-size correlations from the sieve analyses; where the correlation gives a higher permeability, the field value is the conservative one to use.

Design value. Apply a factor of safety of 2.0 to the field-tested permeability for capacity design (design permeability equal to one half of the field value), extend the system bottom into the clean sand found in the borings, and carry a bid item for over-excavation of any clay, silt or dirty sand pocket below it. Compacting the natural sand under the system reduces its permeability, sometimes dramatically, so specify how the base is prepared.

Do not test infiltration where groundwater is within a few feet of the surface; the result is meaningless and the site is not suited to infiltration. One recent client request banned infiltration tests outright for that reason.