This chapter sets out the desktop study: the public and railroad data sources to review, how to read the history of a site from old maps and imagery, how to screen ground hazards from the office, and how the result sets the reconnaissance and drilling scope. It builds on the desktop study sections of Chapter 3.8, which apply the same sources to the risk rating of a single site.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Failure case histories show why a desk study at the concept stage pays for itself; hydrologic screening values for the desktop review. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Rational method runoff coefficient | Business – downtown | ASCE (1960) | 0.7 | 0.825 | 0.95 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Business – neighborhood | ASCE (1960) | 0.5 | 0.6 | 0.7 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Residential – single-family | ASCE (1960) | 0.3 | 0.4 | 0.5 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Residential – suburban | ASCE (1960) | 0.25 | 0.325 | 0.4 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Industrial – light | ASCE (1960) | 0.5 | 0.65 | 0.8 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Industrial – heavy | ASCE (1960) | 0.6 | 0.75 | 0.9 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Railroad yard areas | ASCE (1960) | 0.2 | 0.3 | 0.4 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Parks, cemeteries | ASCE (1960) | 0.1 | 0.175 | 0.25 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Unimproved areas | ASCE (1960) | 0.1 | 0.2 | 0.3 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Lawn, sandy soil, flat < 2% | ASCE (1960) | 0.05 | 0.075 | 0.1 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Lawn, sandy soil, 2–7% | ASCE (1960) | 0.1 | 0.125 | 0.15 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Lawn, sandy soil, steep > 7% | ASCE (1960) | 0.15 | 0.175 | 0.2 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Lawn, heavy soil, flat < 2% | ASCE (1960) | 0.13 | 0.15 | 0.17 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Lawn, heavy soil, 2–7% | ASCE (1960) | 0.18 | 0.2 | 0.22 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Lawn, heavy soil, steep > 7% | ASCE (1960) | 0.25 | 0.3 | 0.35 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Asphalt pavement | ASCE (1960) | 0.7 | 0.825 | 0.95 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Concrete pavement | ASCE (1960) | 0.8 | 0.875 | 0.95 | – | HDS2 T5.7, p.5-33 | |
| Rational method runoff coefficient | Roofs | ASCE (1960) | 0.75 | 0.85 | 0.95 | – | HDS2 T5.7, p.5-33 | |
| Highway design storm return period | Rural principal arterial | AASHTO (1999) | 50 | yr | HDS2 T1.1, p.1-5 | |||
| Highway design storm return period | Rural minor arterial | AASHTO (1999) | 25 | 37.5 | 50 | yr | HDS2 T1.1, p.1-5 | |
| Highway design storm return period | Rural major collector | AASHTO (1999) | 25 | yr | HDS2 T1.1, p.1-5 | |||
| Highway design storm return period | Rural minor collector | AASHTO (1999) | 10 | yr | HDS2 T1.1, p.1-5 | |||
| Highway design storm return period | Rural local road | AASHTO (1999) | 5 | 7.5 | 10 | yr | HDS2 T1.1, p.1-5 | |
| Highway design storm return period | Urban principal arterial | AASHTO (1999) | 25 | 37.5 | 50 | yr | HDS2 T1.1, p.1-5 | |
| Highway design storm return period | Urban minor arterial | AASHTO (1999) | 25 | yr | HDS2 T1.1, p.1-5 | |||
| Highway design storm return period | Urban collector | AASHTO (1999) | 10 | yr | HDS2 T1.1, p.1-5 | |||
| Highway design storm return period | Urban local street | AASHTO (1999) | 5 | 7.5 | 10 | yr | HDS2 T1.1, p.1-5 | |
| Risk the design flood is equaled or exceeded during service life | 2-year design flood | Service life 1 yr | 50 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 5-year design flood | Service life 1 yr | 20 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 10-year design flood | Service life 1 yr | 10 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 25-year design flood | Service life 1 yr | 4 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 50-year design flood | Service life 1 yr | 2 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 100-year design flood | Service life 1 yr | 1 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 2-year design flood | Service life 5 yr | 96.9 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 5-year design flood | Service life 5 yr | 67.2 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 10-year design flood | Service life 5 yr | 41 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 25-year design flood | Service life 5 yr | 18.5 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 50-year design flood | Service life 5 yr | 9.6 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 100-year design flood | Service life 5 yr | 4.9 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 2-year design flood | Service life 10 yr | 99.9 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 5-year design flood | Service life 10 yr | 89.3 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 10-year design flood | Service life 10 yr | 65.1 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 25-year design flood | Service life 10 yr | 33.5 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 50-year design flood | Service life 10 yr | 18.3 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 100-year design flood | Service life 10 yr | 9.6 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 5-year design flood | Service life 20 yr | 98.8 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 10-year design flood | Service life 20 yr | 87.8 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 25-year design flood | Service life 20 yr | 55.8 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 50-year design flood | Service life 20 yr | 33.2 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 100-year design flood | Service life 20 yr | 18.2 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 10-year design flood | Service life 50 yr | 99.5 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 25-year design flood | Service life 50 yr | 87 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 50-year design flood | Service life 50 yr | 63.6 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 100-year design flood | Service life 50 yr | 39.5 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 25-year design flood | Service life 100 yr | 98.3 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 50-year design flood | Service life 100 yr | 86.7 | % | HDS2 T4.25, p.4-90 | |||
| Risk the design flood is equaled or exceeded during service life | 100-year design flood | Service life 100 yr | 63.4 | % | HDS2 T4.25, p.4-90 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Primary cause of geotechnical failure (share of cases) | Shortcomings in design | ISSMGE TC302 Task Force 10, ~100 case histories | 45 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Inadequate site investigation | ISSMGE TC302 Task Force 10, ~100 case histories | 20 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Unforeseen phenomena and occurrences | ISSMGE TC302 Task Force 10, ~100 case histories | 20 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Shortcomings in construction | ISSMGE TC302 Task Force 10, ~100 case histories | 14 | % | FGE text, p.274 | |||
| Site investigation spend worth making | Project cost | U.S. study (Threadgold 2002) | 3 | % of project cost | FGE text, p.272 | |||
| Site investigation spend on projects with > 50% cost overrun | Outturn project cost | UK projects (Clayton 2001) | 2.5 | % of project cost | FGE text, p.272 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
A desktop study answers three questions before the field program is fixed: what is the ground likely to be, what has happened here before, and what could go wrong. Done well, it moves borings to where the answers are, removes borings that legacy data already cover, and warns the field crew about slag, peat, karst or a buried creek before the rig arrives. It is also the cheapest part of any job; a day in the office routinely saves a day of standby or a return trip.
The output is a short summary and a map file, not a report. Its value is in the expected subsurface profile and the list of questions it hands to the reconnaissance (Chapter 3.4) and the drilling scope (Chapter 3.3).
| Source | What it gives | Use and cautions |
|---|---|---|
| Historical and current USGS topographic maps (15-minute from the 1890s; 7.5-minute editions) | Original ground, former channels, marshes, ponds, quarries, early rail lines | Compare editions to find filled ground and buried channels; the earliest edition is often the most useful |
| State geological survey maps and reports | Bedrock formation, surficial deposits, faults, karst, drift thickness | Formation names explain residual soils (a shale that weathers to fat clay; a carbonate that dissolves) |
| USGS 3DEP lidar (1-m, about 3-ft, DEM) and hillshade | Ground elevations, slopes, scarps, hummocky fill, drainage paths | Note the collection date; recent fill, stockpiles and ruts will not show. Phone GPS altitudes can differ from lidar by 3 to 8 ft and should not be used |
| Aerial and satellite imagery (current and historical) | Land cover, wet areas, ponding, erosion, clearing, construction history | State the positional accuracy of the base imagery; boring symbols may appear offset |
| USDA-NRCS soil survey (SSURGO) | Map units, USCS by depth, drainage class, depth to water and rock | Shallow (to about 5 ft) and generalized; urban land units have no data |
Assemble everything in one map file (KMZ) with a layer for each source. The same file becomes the base for the boring plan, the reconnaissance and, later, the report figures. Name layers so they can be traced into the report (for example "Previous borings and well logs" and "Drill-rig access routes (conceptual)").
Groundwater and drainage control most railroad ground hazards, so the desktop study collects every clue to them:
| Indicator | What it suggests | Follow-up |
|---|---|---|
| Ground only a few feet above a nearby lake or river | Groundwater within a few feet of the surface | Rule out infiltration testing; plan casing or mud rotary for deeper borings |
| Deep, variable water levels in nearby wells (100 to 200 ft) | Karst carbonate aquifer; perched water possible over rock | Record water at drilling, completion and 24 hours |
| Hydric soil units and wetland mapping along an old spur or ditch | Wettest ground on site; soft access | Schedule those borings after a dry period or on frozen ground |
| Ponding, dark standing water or odor reported in ditches | Organic muck, sulfur-bearing fill or a sewer source | Historical review; four-gas monitoring while drilling |
The history of a site often explains its ground better than the geology map. Build a short timeline from the oldest map forward, and say what each period means for the borings.
| Period | What happened | What it means for the exploration |
|---|---|---|
| Late glacial | Lake plain of a glacial lake; shallow postglacial lake within wetlands; dolomite bedrock at depth | Lacustrine sand and silt over glacial till; bedrock well below boring depths |
| 1830s to 1880s | Marsh used for hunting and fishing; first railroad on the marsh edge | Original surface at or near lake level |
| 1880s to 1990s | Near-continuous filling with steel slag, cinders, municipal waste, dredge spoil and debris | Variable, unengineered fill; cemented slag may cause auger refusal; screen cuttings |
| 1960s | Engineering borings drilled in the area for a planned development | Legacy data to collect |
| 2010s | Facility expansions with borings and reports | Profile already known; target the gaps |
| Present | Ground 5 to 13 ft above the lake; hummocky fill; a 50- to 60-ft mound in one corner | Expect 0.5 to 6 ft of fill; check imagery before scoping the mound |
| Period | What happened | What it means for the exploration |
|---|---|---|
| Paleozoic | Carbonates and shales thrust along a regional fault system; tectonic breccia in the shear zone | Irregular rock surface; rapid changes from residual clay to breccia |
| Quaternary | Creek downcutting; karst dissolution (sinkholes, pinnacled rock, clay-filled voids); old landslide masses | Core where refusal is shallow; consider geophysics if the rock surface is erratic |
| 1850s | Railroad graded by hand and cart; embankment fill probably undocumented, with cinders | Treat the existing embankment as uncontrolled fill |
| 1960s | Interstate built through the corridor; chronic cut-slope problems in the breccia | Expect weak, sheared rock in cuts |
| 2020s | Siding design borings; avoidance redesign with steeper slopes | New borings needed only where the redesign moves onto unexplored ground |
Railroad records add what public sources cannot: track charts, slow-order and geometry-defect history, past repairs, valuation maps with utilities and property lines, and earlier reports. Ask for them in the first week; they often take longest to arrive.

| Hazard | Sources | Notes |
|---|---|---|
| Flooding and scour | FEMA flood maps, stream gauges and flood categories, historical high-water marks | Pair water-sensitive sites with a gauge for the live rating |
| Landslides | State and USGS landslide inventories, lidar hillshade, previous reports | Look for scarps, hummocky ground and bowed fences |
| Karst and subsidence | State karst maps, sinkhole inventories, mine maps, InSAR where available | Pinnacled rock and voids call for coring and possibly geophysics |
| Seismic | USGS hazard maps and site class correlations | Liquefaction screening for loose saturated sands (Chapter 6.5) |
| Contamination | State and federal remediation, landfill, underground tank and RCRA databases; a radius report | Slag fill aquifers can have pH above 12; plan screening and cuttings handling |
| Protected resources | Wetlands inventory, threatened and endangered species (IPaC), migratory bird windows | Affects clearing dates and access (Chapter 3.6) |
For network-scale screening, the Federal Railroad Administration's Composite Hazard Index ranks segments, while gauge-based monitoring and public databases rank individual sites. Chapter 3.8 compares the two and shows how the desktop study feeds the preliminary risk rating.
For a water-sensitive site (a fill across a creek, a culvert, a slope above a river), the desktop study also sets the numbers the site will be watched against: the culvert capacity storm, the river stage at which water reaches the toe, and the antecedent rainfall that has preceded past failures. These become the thresholds of the live risk rating (Section 3.8.26) and the trigger rating of Section 3.8.18.
Finish with an expected profile, stated as a simple table with depth ranges, and a list of what the borings must answer. The profile below, assembled from 43 legacy borings for a parking expansion, set the depths of both the light-tower and the pavement borings.
| Depth (typical) | Stratum | Notes |
|---|---|---|
| 0 to 1 ft | Topsoil, gravel or asphalt | Topsoil often mixed with cinders |
| 0.5 to 3 to 6 ft | Slag, cinder and urban fill | Very dense, cemented slag; auger refusal in several borings; chemical odor in one |
| 3 to 6 ft (local) | Organic clay and peat | Water content over 100 percent; drives settlement |
| 4 to 8 to 13.5 ft | Lacustrine sand and silt | Very loose to medium dense, saturated; N typically 2 to 8 |
| 8 to 13.5 to 30+ ft | Glacial till | Stiff to very stiff lean to fat clay; Qu about 1.0 to 3.7 tsf; no legacy boring below 30 ft |
| 1 to 6 ft | Groundwater | Close to the lake level |
The same model drives design implications: light-tower shafts will need casing or slurry through the loose saturated sand and will take their capacity in the till; pavement subgrade will need undercut and geosynthetics or full-depth reclamation; organic pockets control settlement; slag and odors call for screening and a cuttings plan.
The desktop study is delivered as a map file and a short summary. Keep it to what the next step needs.
| Item | Content |
|---|---|
| Map file (KMZ) | Study area, legacy borings and wells with logs, soil units, geology, flood and wetland layers, utilities from valuation maps, conceptual access routes, proposed borings |
| Site background summary | Location and references; legacy work; expected profile; site history; hazards; data gaps; implications for design |
| Questions for reconnaissance | Access, utilities, wet ground, obstructions, property lines, odors |
| Inputs to the risk rating | Situational attributes, trigger and thresholds (Chapter 3.8) |
Interactive map tools, such as the hazard-monitoring map and the earth viewer on this site, can build and export the map file directly, so the same layers carry through to the field form and the full assessment.
| Topic | Refer to |
|---|---|
| Desktop study sections of the risk assessment | Section 3.8.23 |
| Trigger rating and geospatial frequency | Sections 3.8.18 and 3.8.19 |
| Reconnaissance | Chapter 3.4 |
| Site conditions write-up | Chapter 3.5 |
| Drilling scope | Chapter 3.3 |
| Groundwater characterization | Chapter 2.8 |
| Problem soils (silts, clays, peats, rock and sand) | Chapters 2.4 to 2.7 |
The desktop study usually starts from the track chart or aerial imagery, and curve data come with it. Curvature matters to the geotechnical work in several ways: superelevation thickens the ballast under the high rail, sharp curves (over 3°) add centrifugal force to shoring design next to track (Chapter 7.1), and the speeds the curve can carry decide whether critical-speed checks (Chapter 6.5) or passenger ride limits apply. A Class I railroad's recommended method, based on the standard balance equation, is summarized here.
Equation 3.2-1. Balance, spiral length and maximum speed
E = superelevation (in.), D = degree of curve (chord definition, R = 50/sin(D/2)), V = speed (mph), Eu = underbalance (in.). The 62E term keeps the runoff no steeper than 1 in. in 62 ft (freight car torsion); 1.63 EuVp is for passenger comfort.
| Limit | Value |
|---|---|
| Maximum | Lesser of balanced elevation and 5 in. (more only with the chief engineer's authority) |
| Minimum | Greatest of 1/2 in., balanced freight − 2 in., balanced passenger − 3 in. |
| Choice within the range | As low as practical, since most tonnage is slow heavy freight that damages the low rail |
| Reverse curves | At least 100 ft of tangent between spirals |
| Grade compensation (industry track standard) | 0.04% per degree of curve |
| Result | Value |
|---|---|
| Balanced elevation, freight / passenger | 5" / 7 7/8" |
| Allowed range | 4 7/8" to 5" |
| Superelevation applied | 4 7/8" |
| Minimum spiral (passenger comfort governs over freight torsion, 302 ft) | 367 ft |
| Maximum passenger speed at Eu = 3 in. | 75 mph |
Open the curve superelevation calculator →
Degree of curve and radius, balanced and allowable superelevation, spiral length, maximum speeds and grade compensation.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.
The NRCS soil survey covers almost all of the United States and is usually the first soil information available for a railroad site. It is an agricultural (pedological) classification of the upper 5 to 6.5 ft of the ground, mapped at about 1:12,000 to 1:24,000, and its engineering tables are estimates for typical soils, not test results. Used with that in mind, it is very good at flagging problem soils along a corridor before any borings are drilled (Arnold and Eswaran 2003; García-Gaines and Frankenstein 2015).
| Order | How it forms | Engineering flags for railroad work |
|---|---|---|
| Gelisols | Permafrost; freeze–thaw churning | Thaw settlement and frost heave; ice-rich ground |
| Histosols | Organic matter accumulates in waterlogged ground | Peat and muck: very compressible, weak, long-term settlement (Chapter 2.6) |
| Spodosols | Acid leaching of iron and aluminum from sandy soil into a cemented subsoil | Cemented layers that perch water; acidic and often wet: corrosion |
| Andisols | Weathering of volcanic ash | Low density, high water content; strength and plasticity change irreversibly on drying and remolding |
| Oxisols | Extreme tropical weathering to iron and aluminum oxides | Deep residual soils; aggregated clays that classify oddly (Chapter 2.13); mainly Hawaii and Puerto Rico |
| Vertisols | Smectite clay shrinks and swells, forming cracks and slickensides | Expansive clay: track geometry loss, shallow slope failures, structure heave (Chapter 2.5) |
| Aridisols | Dry climate; carbonate, gypsum and salt accumulate | Collapsible soils (Chapter 2.9), caliche and arid soils (Chapter 2.13), gypsum dissolution (Chapter 2.11), corrosive salts |
| Ultisols | Acid leaching; clay moves into the subsoil | Residual soils of the humid Southeast (Chapter 2.13); erodible surface, acidic and corrosive |
| Mollisols | Dark, humus-rich topsoil under grassland | Often on loess: collapsible when dry, frost-susceptible silt |
| Alfisols | Clay moves into a base-rich subsoil | Clayey subsoil under silty topsoil; frost-susceptible silt |
| Inceptisols | Weak development | Variable; often young soils on slopes and floodplains |
| Entisols | Little or no development: recent deposits or eroding slopes | Fresh alluvium, dune sand, colluvium: loose, soft, liquefiable or erodible |
The USDA texture class uses particle size only: sand is 2 to 0.05 mm, silt 0.05 to 0.002 mm and clay finer than 0.002 mm, with gravel added as a modifier. USCS sets the sand–fines boundary at 0.075 mm (No. 200 sieve) and splits fines by plasticity, not size. So a texture class does not fix a USCS group; it only makes some groups more likely. A consensus mapping from several data sets, thousands of samples in all, is given in Table 3.2-13.
| Fraction | USDA | USCS (ASTM D2487) |
|---|---|---|
| Gravel | > 2 mm (modifier) | 75 to 4.75 mm |
| Sand | 2 to 0.05 mm | 4.75 to 0.075 mm |
| Silt | 0.05 to 0.002 mm | Fines < 0.075 mm, split into silt and clay by plasticity (A-line) |
| Clay | < 0.002 mm |
| USDA texture | Most likely USCS | Spread in the 1961 data set |
|---|---|---|
| Sand | SP | SM and SP-SM about equally common |
| Loamy sand | SM | Almost all SM |
| Sandy loam | SM | SM 40%, ML 20%, SC 13%, SM-SC 9%, CL 8% |
| Sandy clay loam | SC | Mostly CL (19 of 31), then SC |
| Sandy clay | SC or CL | Too few samples |
| Loam | CL | CL 53%, ML 22%, CL-ML 11% |
| Silt loam | ML | CL 45%, ML 36%, CL-ML 10% |
| Silt | ML | All ML |
| Clay loam | CL | CL 78% |
| Silty clay loam | CL | CL 65%, CH 28% |
| Clay | CH or CL | CH 66% |
| Silty clay | CH or CL | CH 78%, CL 22% |
The spread shows why the mapping is only a starting point: a silt loam is about as likely to be CL as ML, and the report itself recommends laboratory classification for anything that matters.
For railroad work: Use the soil survey to decide where to drill and what to test, not to design. A corridor-length table of map units with their order, texture, listed USCS, linear extensibility, depth to water and corrosion ratings takes little time to build from Web Soil Survey and often shows where the problem soils are before the first boring. Flag any length of track where the survey and the track maintenance record agree, for example high shrink–swell soils where surfacing is frequent.
Percentages in Table 3.2-13 are calculated from the 1961 Waterways Experiment Station data set reproduced in the report.
A Class I railroad located in Texas plans to extend a siding across farmland beside the main track. Before borings are scheduled, the desktop study pulls the soil survey map unit that covers most of the new alignment. The engineer must check whether the USCS classes listed in the survey agree with the USDA textures, estimate the shrink–swell potential of the upper 5 ft, and decide what the investigation must look for (Section 3.2.10).
| Variable | Value | Description |
|---|---|---|
| Ap, 0–8 in. | Silt loam; listed CL-ML; LEP 1.5% | Plowed surface horizon |
| Bt, 8–36 in. | Silty clay loam; listed CL; LEP 4.5% | Clay-enriched subsoil |
| Btss, 36–60 in. | Clay; listed CH; LEP 7.5% | Clay-enriched subsoil with slickensides (“ss”) |
| Classes | LEP: low < 3%, moderate 3–6%, high 6–9%, very high ≥ 9% | NRCS shrink–swell classes |
(a) ML, CL and CH expected; the listed CL-ML, CL and CH agree. (b) LE ≈ 3.2 in. (8.1 cm); low, moderate and high by horizon. (c) Investigate and design for expansive clay.
LE is an index of potential volume change between moist and oven-dry, not a prediction of track movement: field moisture changes are smaller and depend on cover, drainage and climate. It is enough to say that the siding subgrade, cut slopes and any shallow culvert or signal foundations are in shrink–swell clay, so the investigation should include swell tests and suction measurements (Chapter 2.5), and the design should consider moisture control, lime treatment after sulfate screening (Section 7.2.7) and the shallow-slide risk on side slopes (Section 7.4.9). The map unit also has inclusions of other soils, so borings, not the map, set the design.
Terrain analysis is the interpretation of landforms, drainage, tone and vegetation on topographic maps and remotely sensed images to map the geologic conditions of a site before it is drilled. Hunt (2007) calls it often the most important part of a geotechnical investigation: landform reflects how resistant the materials are to erosion, so ridges, valleys, slope shapes and drainage reveal rock type, structure, soil origin, groundwater and hazards such as landslides and sinkholes.
| Purpose | Imagery | Scale or resolution |
|---|---|---|
| Regional geology and major structures (faults, folds) | Satellite images; radar where cloud cover is persistent | Moderate resolution, whole region |
| General mapping of large areas | Stereo pairs of aerial photographs | 1:60,000 to 1:40,000 |
| Detailed mapping of rock, soil, drainage, slides, sinkholes | Stereo pairs, black and white, true color or color infrared | 1:20,000 to 1:8,000 |
| Ground moisture, seepage, wet ground at sinkholes and fault traces | Color infrared (CIR) stereo pairs; thermal infrared | Large to local areas |
| Ground surface under trees | LiDAR bare-earth DEM and hillshade (Section 3.2.12) | 1 to 3 ft grid typical |
Hunt recommends interpreting photographs at two scale ranges for any large study: the small scale for the overview and the large scale for detail. Historical photographs are especially valuable on railroads because they show the ground before fills, cuts and vegetation changed it.
| Pattern | Appearance | Indicates | Railroad significance |
|---|---|---|---|
| Dendritic | Tree-like, branching in all directions | Uniform material: flat-lying sedimentary rock, massive crystalline rock, thick uniform soil | Few structural controls; slope problems follow soil and weathering |
| Trellis | Long parallel main streams with short tributaries at right angles | Tilted or folded interbedded rocks, parallel faults | Cuts across the strike meet alternating hard and soft beds and dip-slope sliding |
| Rectangular | Streams turn at right angles; segments of similar length | Jointed or faulted rock with two joint sets at right angles | Joint-controlled wedge and toppling failures in cuts |
| Radial | Streams flow outward from a high point | Domes, volcanic cones, isolated peaks | Variable dip around the feature |
| Parallel | Closely spaced parallel streams | Steep uniform slopes, young surfaces, loess | Erodible ground; gullying of side slopes |
| Deranged | Irregular, with lakes, swamps and unconnected streams | Young glacial terrain | Peat, soft lake deposits, variable till (Chapter 2.6) |
| Karst (internal) | Few surface streams; closed depressions and sinking streams | Soluble rock: limestone, dolomite, gypsum | Sinkholes under track and structures (Chapter 2.11) |
For railroad work: Build a strip map along the line from the topographic map, the hillshade and two scales of stereo photographs, earliest and latest. Mark landforms, drainage patterns, wet ground, old slides, filled ravines, borrow pits and culvert outfalls, and carry the map into the reconnaissance (Chapter 3.5) to check each feature on the ground. A change in drainage pattern along the line usually marks a change in geology, and is a good place for a boring.
A Class I railroad located in Kentucky has had repeated slides along a 12-mile line through shale hills. Before any borings are planned, the engineer wants historical stereo aerial photographs at two scales to map old slide scars, fills and drainage along the line (Section 3.2.11). The engineer must find the ground covered by each frame, the spacing between exposures and the number of photographs to order along a single flight line.
| Variable | Value | Description |
|---|---|---|
| L | 12 mi = 63,360 ft | Corridor length, one flight line |
| Format | 9 in. × 9 in. | Standard aerial camera frame |
| S | 1:20,000 and 1:40,000 | Detail and overview scales (Hunt: use two scale ranges) |
| p | 60% | Forward overlap needed for stereo viewing |
(a) 15,000 ft at 1:20,000; 30,000 ft at 1:40,000. (b) 6,000 ft and 12,000 ft. (c) About 14 and 9 photographs.
A single flight line at 1:20,000 covers 7,500 ft each side of the track, far more than the corridor, so one line is enough unless the alignment curves sharply. Order the earliest available year as well as a recent one: old slide scars, filled ravines, borrow pits and abandoned alignments are often clearer before vegetation and later work hide them. Check the photos against the LiDAR hillshade (Section 3.2.12) and the slide inventory, then mark the features to visit during reconnaissance.
A project GIS keeps every layer of the desktop study on one map in one coordinate system, so the data can be overlaid, queried and handed on. The workflow below follows the standard steps in desktop GIS software (Law and Collins 2016) applied to a railroad corridor.
For railroad work: Use the railroad's own milepost and valuation station system as an attribute on every feature, because that is how track forces locate problems. Keep raw and derived data separate in the geodatabase, note the source and date of every layer, and save the project with the report so the next study starts from it rather than from scratch.