Elastic settlement, one-dimensional consolidation and its rate, secondary compression, and acceleration with surcharge and vertical drains.
Variables. q = net contact pressure (psf); B = footing width (ft); ν = Poisson's ratio (0.5 undrained clay; 0.3–0.35 sand); Es = soil modulus (psf); Iw = shape and rigidity factor
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| q | net contact pressure (psf) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| B | footing width (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| ν | Poisson's ratio (0.5 undrained clay | Assumed (published values) | Rarely measured; choose from published ranges. Use 0.5 for undrained clay. | 0.25–0.40; 0.5 undrained · by USCS group |
| Es | soil modulus (psf) | Field test, lab test or correlation | Pressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc. | loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group |
| Iw | shape and rigidity factor | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
Use. Sands (most of the settlement) and undrained distortion of clays.
Limitations. Es is the controlling uncertainty; choose it for the stress and strain level of the problem. Homogeneous half-space; for layered or increasing stiffness use the strain-influence approach.
Source. Timoshenko & Goodier 1951; Bowles 1996 [61] [11] · In the manual: Ch 6.2 Eq. 6.2-4
Variables. Cc = compression index; e0 = initial void ratio (ST-01); H = layer thickness (ft); σ'v0 = initial effective stress at mid-layer (psf); Δσ = stress increase at mid-layer (psf, from ST-04 to ST-09)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | compression index | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
| e0 | initial void ratio (ST-01) | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| H | layer thickness (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| σ'v0 | initial effective stress at mid-layer (psf) | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
| Δσ | intermediate value computed on this page | Another equation | Computed: Δσ = stress increase at mid-layer (psf, from ST-04 to ST-09) | project-specific |
Use. Clay where σ'v0 = σ'p (OCR = 1).
Limitations. One-dimensional compression; use sublayers no thicker than about 5–10 ft so that the log term is not averaged across a large stress change. Measure Cc and σ'p on undisturbed samples (ASTM D2435).
Source. Terzaghi 1925 [56] [27] · In the manual: Ch 6.2 Eq. 6.2-5, Ch 6.2 Eq. 6.2-10
Variables. Cr = recompression (swell) index, roughly Cc/5 to Cc/10; σ'p = preconsolidation stress (psf)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cr | recompression (swell) index, roughly C_c/5 to C_c/10 | Lab test | Unload–reload slope of the e–log σ' curve (ASTM D2435). Screening: Cr ≈ Cc/5 to Cc/10. | 0.01–0.08 (inorganic clays) · by USCS group |
| σ'p | preconsolidation stress (psf) | Lab test (or correlation) | Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0. | OCR 1 (NC) to > 4 (heavily OC) · by USCS group |
| Cc | compression index | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
| e0 | void ratio | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| σ'v | vertical stress / pore pressure | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
Use. Overconsolidated or desiccated-crust clays, and reloading of old embankment foundations.
Limitations. The result depends strongly on σ'p; sample disturbance lowers measured σ'p and raises computed settlement.
Source. Terzaghi 1925; Holtz et al. 2011 [56] [27] · In the manual: Ch 6.2 Eq. 6.2-7
Variables. Δe = change in void ratio from the e–log σ' curve; mv = coefficient of volume compressibility (1/psf) over the actual stress range
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Δe | change in void ratio from the e–log σ' curve | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| mv | coefficient of volume compressibility (1/psf) over the actual stress range | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
Use. Reading settlement directly from a consolidation test curve over the design stress range.
Limitations. mv is not constant; take it over the same stress interval as the design load.
Source. Terzaghi 1943; Holtz et al. 2011 [57] [27] · In the manual: Ch 6.2 §6.2.4
Variables. cv = coefficient of consolidation (ft2/day); t = time (days); Hdr = drainage path (ft; H/2 for two-way drainage, H for one-way); k = permeability (ft/day); γw = 62.4 pcf
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| cv | coefficient of consolidation (ft^2/day) | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
| t | time (days) | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| Hdr | drainage path (ft | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| k | permeability (ft/day) | Field or lab test | Field: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only. | clean sand 1–100, clay < 0.001 ft/day · by USCS group |
| γw | 62.4 pcf | Constant | Physical constant or standard value. | project-specific |
Use. Rate of primary consolidation under one-dimensional vertical drainage.
Limitations. Laboratory cv often under-predicts field rates where sand seams shorten Hdr; identify drainage boundaries from CPTu dissipation or continuous sampling.
Source. Terzaghi 1925 [56] · In the manual: Ch 6.2 Eq. 6.2-11, Ch 6.2 Eq. 6.2-13
Variables. U = average degree of consolidation (decimal in the series and first approximation; percent in the second)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| U | average degree of consolidation (decimal in the series and first approximation | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
Use. Uniform initial excess pore pressure with depth (wide loads relative to layer thickness).
Limitations. For narrow loads or triangular pore pressure distributions the U–Tv relationship differs. Construction time spreads loading; treat the load as applied at mid-construction.
Source. Terzaghi 1925; Casagrande, as given by Taylor 1948 [56] [55] · In the manual: Ch 6.2 §6.2.5, Ch 6.2 Eq. 6.2-19
Variables. Cα = secondary compression index; ep = void ratio at the end of primary consolidation; t1 = time to end of primary (days); t2 = end of design life (days)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cα | secondary compression index | Lab test | Slope of e vs log time after primary consolidation in the consolidation test (ASTM D2435). | Cα/Cc 0.03–0.08 · by USCS group |
| ep | void ratio at the end of primary consolidation | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| t1 | time to end of primary (days) | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| t2 | end of design life (days) | Design criterion | Set by the client railroad standards, AREMA, AASHTO, USACE or the project specification. | project-specific |
Use. Organic clays, peats and soft clays over a long service life.
Limitations. Cα drops after overconsolidation by surcharge; use the post-surcharge value where a surcharge is removed.
Source. Mesri 1973 [36] · In the manual: Ch 6.2 Eq. 6.2-14
Variables. Sc,f = final primary settlement under the permanent load; Ss,f = secondary settlement to be removed; Sc,(f+s) = primary settlement under permanent load plus surcharge; ts = time the surcharge must stay in place
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Sc,f | final primary settlement under the permanent load | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| Ss,f | secondary settlement to be removed | Field or lab measurement | Recorded during the test or monitoring (readings, times, dimensions of the test setup). | project-specific |
| Sc,(f+s) | primary settlement under permanent load plus surcharge | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| ts | time the surcharge must stay in place | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| cv | coefficient of consolidation | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
Use. Choosing surcharge height and duration for approach fills and embankments over soft clay.
Limitations. Ureq is an average; the mid-depth of a thick layer lags behind it. Use the U at the least consolidated point (mid-layer) where rebound after removal must be avoided, and confirm with settlement plates and piezometers.
Source. Johnson 1970 [31] · In the manual: Ch 6.2 §6.2.8
Variables. ch = horizontal coefficient of consolidation (ft2/day); de = drain influence diameter (ft); S = drain spacing (ft); dw, ds = drain and smear-zone diameters (ft); kh/ks = smear permeability ratio; L = drain length for one-way discharge (ft); z = depth (ft); qw = drain discharge capacity (ft3/day); a, b = PVD band dimensions (ft)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| ch | horizontal coefficient of consolidation (ft^2/day) | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
| de | drain influence diameter (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| S | drain spacing (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| kh/ks | smear permeability ratio | Field or lab test | Field: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only. | clean sand 1–100, clay < 0.001 ft/day · by USCS group |
| L | drain length for one-way discharge (ft) | Hydraulic study | From the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design. | project-specific |
| z | depth (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| qw | drain discharge capacity (ft^3/day) | Product data | Manufacturer's data sheet for the specified product, confirmed by project QA testing. | project-specific |
Use. PVD and sand drain design. With no smear and no well resistance, μ ≈ ln(n) − 0.75.
Limitations. Smear parameters are uncertain and govern at close spacing; calibrate with a test section where possible.
Source. Barron 1948; Hansbo 1981 [6] [22] · In the manual: Ch 7.2 §7.2.3
Variables. Uv from SE-06; Ur from SE-09
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Uv | intermediate value computed on this page | Another equation | Computed: U_v = from SE-06 | project-specific |
| Ur | intermediate value computed on this page | Another equation | Computed: U_r = from SE-09 | project-specific |
Use. Total degree of consolidation with PVDs in a layer that also drains vertically.
Limitations. Uv is usually small in thick clay with drains, so U ≈ Ur.
Source. Carillo 1942 [13] · In the manual: Ch 7.2 §7.2.3
Variables. SA, SB = settlement at two points (in. or ft); LAB = distance between them (same units)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| LAB | distance between them (same units) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
Use. Bridge-approach transitions, track profile and structure tolerance checks.
Limitations. Compare with the railroad's own limits (the manual cites 1/500 at Class 4 bridge approaches). Use predicted settlements at the same time after construction.
Source. Skempton & MacDonald 1956 [53] · In the manual: Ch 6.2 Eq. 6.2-16
Variables. α = creep compression rate (% per log cycle; Table in §6.2.6.1); H = fill thickness; t1, t2 = times after placement
Use. Long-term settlement of new or old fills under track.
Limitations. Rates are from a small number of case histories; for the engineered rows α depends on σ′v in MPa.
Source. Skinner 2012 (Eq. 58.2), from Charles and Watts 2001 [69] · In the manual: Ch 6.2 §6.2.6.1
Variables. γ = fill unit weight; H = embankment height; D* = equivalent constrained modulus of the fill
Use. Settlement of the fill itself during and after construction.
Limitations. Vol. II omits the unit of the D* values it quotes (50 for compacted sandy gravel, 6 for low-plasticity clay; apparently MPa). Confirm against Charles (1993).
Source. Nowak 2012 (Eq. 70.7), after Trenter 2001 [70] · In the manual: Ch 6.2 §6.2.6.1
Variables. e0,i = as-placed void ratio; esat,i = void ratio on the saturated compression curve at the layer stress
Use. Settlement of fill placed dry of optimum when it is first flooded.
Limitations. Away from slopes only; not for high-plasticity clay; depends on the height the fill becomes saturated.
Source. Thorel et al. 2011 [68] · In the manual: Ch 2.4 §2.4.20