7.4.5 Remedial Options
Treating the cuts and embankments of a railroad as an asset portfolio: inventory, condition, deterioration, prioritization and the choice of remedial works.
Railroads favor driven or drilled soldier pile walls for stabilization (Chapter 7.1)
Reinforcement
Soil nails, rock bolts, reinforced slopes
Check corrosion where ground chemistry is aggressive (Chapter 2.12)
Ground improvement
Grouting, deep mixing, lime injection, aggregate columns
See Chapter 7.2
Rock slope
Scaling, trim blasting, mesh and drapes, rockfall barriers, catch ditches, slide fences
Detectors provide warning, not prevention
Erosion and scour
Riprap, gabions, articulated mats, vegetation, channel training
Size for design flood; protect toe below scour depth
Operational
Monitoring, speed restrictions, slide detection, inspection after storms
The observational approach (Chapter 5.5)
Photo 7.4.5-1. Trench excavation (left) and placement of Electro-Kinetic Geosynthetic (EKG) electrode strips (right) during installation. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-2. Cutaway illustration showing the installation of electrodes in a slope stabilization project. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-3. Illustration of the electrode pattern, wired for electrokinetic activation. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-4. Slope during electrode installation, with tree preservation noted; cathode and anode locations labeled. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-5. Anode (left) and cathode (right) connections during active electrokinetic treatment; nearby plant growth indicates the low impact of the treatment on the surrounding environment. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-6. Plan view diagrams of the vertical-anode and horizontal-anode/cathode electrode layouts used at the Interstate 40 test section, Holbrook, AZ. (From O'Bannon, Morris, and Mancini, 1976; reproduced with permission of the Transportation Research Board.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-7. Wiring diagram of the current and voltage instrumentation used at the Interstate 40 test section. (From O'Bannon, Morris, and Mancini, 1976; reproduced with permission of the Transportation Research Board.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-8. Plan of the electrode and chemical-injection-point arrangement used at the Seattle-Tacoma Airport runway test section. (Dearstyne and Newman, 1963; with permission of ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.4.5-9. Cross section of the saturated runway subgrade, showing mud and void zones beneath the pavement and the electrode/drain arrangement used to treat them. (Dearstyne and Newman, 1963; with permission of ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Photo 7.4.5-10. Textured, perforated Geoweb strip material. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-11. GEOWEB sections expanded and installed over a graded slope. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-12. Variable Expansion of the Geoweb Cell. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-13. Geoweb Expansion. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-14. ATRA® Stake Clip. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-15. ATRA® Anchor. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-16. ATRA® Anchor Connected Over the Cell Wall. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-17. ATRA® Anchor over Tendon. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-18. ATRA® Tendon Clip. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-19. ATRA® Tendon Clips with Tendons through the Geoweb Cell Wall. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).Photo 7.4.5-20. ATRA® Key Geoweb Panel Connection — inserting the key. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Remedial design should address the cause identified in the investigation, not only the symptom; a wall built across a slide that is driven by a blocked culvert will be loaded by the same water that caused the slide. Retaining structures and ground improvement are covered in Chapter 7.1 and Chapter 7.2, and slope stability analysis in Chapter 6.3.
More options: recycled plastic pins for shallow slides are in Section 7.4.9, and a method for comparing the carbon footprint of options is in Section 7.4.10.