This chapter explains the two levels of geotechnical work, what each one delivers, how to choose between them, and how to make sure the scope, the fee and the report all say the same thing. It builds on the two report types described in Section 8.4.1: the geotechnical data report and the geotechnical design report.
An exploration collects and presents subsurface data. An investigation collects the data and then interprets it, analyzes it and makes recommendations. The field work can be identical; the difference is in what the engineer does with the results and what the client may rely on. Confusing the two is a common source of disputes: a client who paid for borings expects design answers, or a contractor treats a data report as if it carried recommendations.
Exploration covers the first box. Investigation covers all four.
| Item | Subsurface exploration | Geotechnical investigation |
|---|---|---|
| Purpose | Collect and present factual data | Answer the design question |
| Field and laboratory work | Borings, sampling, field tests, laboratory tests | Same, plus targeted tests chosen for the analyses |
| Interpretation | None, or limited to classification | Geologic interpretation, design parameters, groundwater regime |
| Analysis | None | Bearing capacity, settlement, slope stability, seepage, pavement, seismic as needed |
| Recommendations | None | Foundation and earthwork recommendations; construction considerations; special provisions |
| Deliverable | Geotechnical data report (Section 8.4.1.1) | Geotechnical design or final report (Section 8.4.1.2); or a memorandum for a limited question |
| Who relies on it | Designers and bidders who will do their own interpretation | The designer and owner for the stated project |
| Seal | Often not sealed as design | Sealed by the responsible engineer where required |
A data-only scope is the right choice when someone else will do the design, when the design is not yet defined, or when the data are needed to compare sites or alternatives before any one is chosen.
An investigation adds the engineering: interpretation of the data, the analyses the project needs, and specific recommendations. For railroad work typical analyses are track subgrade support and settlement, slope stability of fills and cuts (with and without the trigger condition), culvert bearing and settlement, foundations for bridges, signals and light towers, pavement subgrade parameters for yards, and the ground hazard risk rating with alternatives (Chapter 3.8).
| Project | Outputs |
|---|---|
| Siding or new main | Subgrade parameters; undercut and stabilization; cut and fill slope recommendations; culvert recommendations |
| Steepened or widened fill | Global stability (factor of safety 1.5 long-term); toe key, buttress or reinforcement alternatives; quantities by reach |
| Yard or intermodal pavement | Subgrade CBR, k and resilient modulus; undercut; geosynthetics or reclamation; light-tower shaft design |
| Bridge or culvert | Foundation type, capacity and settlement; lateral pile design; scour considerations |
| Ground hazard site | Current risk rating; alternatives with risk reduction ratings and costs (Sections 3.8.21 to 3.8.39) |
| Content | Data report | Design report | Memorandum |
|---|---|---|---|
| Project description and scope | Yes | Yes | Brief |
| Boring location plan and logs | Yes | Yes | Attached |
| Laboratory data | Yes | Yes | Attached |
| Groundwater observations | Yes | Yes | Yes |
| Site conditions and geology | Factual | Interpreted | As needed |
| Design parameters | No | Yes | For the question asked |
| Analyses | No | Yes, with calculation appendix | For the question asked |
| Recommendations | No | Yes | Yes, limited |
| Limitations | Yes | Yes | Yes |

Name the deliverable in the proposal (Chapter 3.1), in the cost estimate task list (Chapter 3.7, Task F) and in the report title. When a client asks for "borings" on a design-sensitive problem, explain in one paragraph what a data report will and will not give them, and offer the investigation as an option. When a project grows from data into design, change the scope in writing (Chapter 8.2) rather than letting recommendations creep into a data report.
Interpretation and recommendations carry professional responsibility that data do not. Be clear about who may rely on the work and for what; state the limitations (the borings show conditions at their locations and times only; conditions between borings may differ); and keep data and interpretation visibly separate in every report, so that a later reader looking for the basis of a claim can tell which is which (Section 8.4.1).
| Topic | Refer to |
|---|---|
| Report types and report preparation | Chapter 8.4 |
| Memorandums | Chapter 8.3 |
| Change orders | Chapter 8.2 |
| Scope and deliverables in the proposal | Chapter 3.1 |
| Investigation planning | Chapter 3.9 |
A test pit is the cheapest way to see the ground, and every pit is an excavation under OSHA 29 CFR 1926 Subpart P; one 5 ft or deeper needs a protective system unless it is in stable rock. Reese and Eidson's Handbook of OSHA Construction Safety and Health reprints the standard. Its Appendix A classifies soil as stable rock or Type A, B or C from strength and condition, and Appendix B gives the maximum slope for each type. A trench box, shoring or sloping is required at 5 ft or more unless the cut is in stable rock. Anyone entering a pit to log or sample it is covered, and that is the usual reason an exploration pit is sloped or boxed. Next to track the railroad's own clearances apply as well.
| Type | Definition (summary) | Maximum slope (H:V), excavations under 20 ft |
|---|---|---|
| Stable rock | Natural solid mineral matter that stays intact when exposed | Vertical |
| A | Cohesive soil with qu of 1.5 tsf or more; not fissured, not subject to vibration, not previously disturbed, no layers dipping into the cut, no seepage | 3/4:1 (1/2:1 if open 24 hours or less and 12 ft or less deep) |
| B | Cohesive soil with qu over 0.5 and under 1.5 tsf; angular gravel, silt, silt loam, sandy loam; Type A soil that is fissured or subject to vibration; previously disturbed soil | 1:1 |
| C | Cohesive soil with qu of 0.5 tsf or less; gravel, sand, loamy sand; submerged soil or soil with water freely seeping; layers dipping into the cut at 4H:1V or steeper | 1½:1 |
| Requirement | Limit | Source |
|---|---|---|
| Protective system | Required at 5 ft or more except in stable rock | Subpart P |
| Engineer-designed protection | Deeper than 20 ft | Subpart P |
| Means of egress | Ladder, stair or ramp within 25 ft of lateral travel at 4 ft or more | Subpart P |
| Spoil and equipment | At least 2 ft back from the edge | Subpart P |
| Inspection | Daily and after rain or other changes, by a competent person | Subpart P |
| Track clearance for excavations | No closer than 12 ft to centerline; flagman within 25 ft; clear the 25 ft zone when trains pass | Railroad temporary shoring guidelines |
| Utility excavations and bores | 20 ft minimum from centerline | AREMA Chapter 1, Part 5 |
An 8 ft deep, 4 ft by 10 ft pit in stiff clay (pocket penetrometer 1.8 tsf), 30 ft from track. By strength alone the clay is Type A, but train vibration drops it to Type B, so the sides must be laid back at 1:1 and the top opening grows to 20.0 x 26.0 ft for 70.3 cu yd of excavation. Away from track the same clay would be Type A at 0.5H:1V (open less than a day and no deeper than 12 ft). A 6 ft pit 15 ft from centerline would need a flagman, and its sloped opening would reach within 12 ft of centerline. That pit has to be shored or boxed, not sloped.
Open the test pit safety calculator →
OSHA soil type from strength and conditions, the need for a protective system, maximum allowable slope, top opening and volume, egress, and railroad clearance warnings.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads, clients and projects are not named.