7.4.4 Prioritizing Interventions

Treating the cuts and embankments of a railroad as an asset portfolio: inventory, condition, deterioration, prioritization and the choice of remedial works.
Author: Daniel P. Colwell
7.4.4 Prioritizing Interventions

With limited funds, interventions should be ranked by how much risk they remove per dollar, not simply by which assets score highest. A high-risk site that is very expensive to fix may rank below two moderate-risk sites that are cheap to fix.

R = F × S(Eq. 7.4-1)
Risk score on the GHRM 5 × 5 matrix: F = frequency rating, S = severity rating (each 1 to 5).
E = (Rbefore − Rafter) / C(Eq. 7.4-2)
Risk reduction efficiency: reduction in risk score per unit cost C (for example, per $1 million).

Efficiency ranking should be combined with judgment: any site with a severity of 5 and an increasing frequency needs action regardless of efficiency, and low-cost actions such as clearing drainage are usually worth doing everywhere.