Shallow, surface-parallel slides 3 to 6 ft deep are the most common earthwork failure on side slopes built of or cut into high-plasticity clay. They follow prolonged rain: the near-surface soil wets, seasonal shrink–swell cycles open cracks and loosen it, and its strength falls toward the fully softened value. Each slide is small, but the slides recur, and they undermine shoulders, fill ditches and threaten the ballast section at the crest. Driven recycled plastic pins (RPPs) are a low-cost repair that reinforces the slope across the slip surface without excavation (Khan et al. 2018).
RPPs are square plastic members, typically 4 in. × 4 in. and 8 to 10 ft long, made mostly of recycled high-density polyethylene with other plastics and minor fillers; fiber-reinforced versions are stiffer. They are driven perpendicular to the slope face on a grid. Each pin crossing the slip surface adds bending and shear resistance, so the factor of safety becomes FS = (MR + ΔMR) / MD (Eq. 7.4-3), where MR and MD are the resisting and driving moments about the slip circle and ΔMR is the added resistance from the pins. Plastic does not rot or corrode, but it creeps under sustained load, so the design resistance per pin should allow for creep over the design life.
| Item | Value |
|---|---|
| Soil | CH clay fill from a weathered shale formation; LL 48–79, PI 25–51; back-analyzed FS = 1.05 with fully softened strength |
| Pins | 4 in. × 4 in., 8 and 10 ft long, at 3, 4, 5 and 6 ft centers (4 ft in most sections) |
| Computed FS after pinning | 1.43 to 1.54 (finite element analysis) |
| Installation | Crawler rig with a mast-mounted vibratory percussion hammer working on the slope; about 4 minutes per 10-ft pin; 100 to 120 pins per day |
| Crest settlement after 5 years | Pinned sections 2.75 to 6.25 in. (least where pins were 3 ft apart); unpinned control sections 9.5 to 15 in. |
| Movement after pinning | Less than 1.5 in. of additional settlement in the pinned sections; inclinometers showed movement largest at the surface and decreasing with depth |
| Untreated slopes nearby | Six shallow failures on the opposite, unpinned slope during the monitoring period |
| Effect of spacing (analysis) | Crest displacement rose from about 1 in. at 2-ft spacing to 4.7 in. at 8-ft spacing |
For railroad work: Pins suit sloughing cut and fill side slopes in high-plasticity clay where the failures keep reaching the ditch line or the ballast shoulder. The rig works on the slope face, so most of the work can stay outside the track foul zone, but check rig access, the stability of the slope under the rig, and buried signal and communication cables near the crest before driving. Monitor pinned and unpinned lengths with survey points at the crest and an inclinometer, and compare them, as the case history did, before using pins across a whole subdivision. This guidance on use is engineering judgment drawn from the case history, not a design method.
A worked pin layout is Example 7.4-3 (Section 7.4.6).
Values are as reported in English units.