A district has budget for about $2 million of earthwork repairs this year. Three candidate sites have been rated on the GHRM 5 × 5 matrix, with the expected rating after the proposed repair and its estimated cost.
| Variable | Value | Description |
|---|---|---|
| Site A | F = 4, S = 4; after: F = 2, S = 4; C = $1.2M | Embankment slide; soldier pile wall |
| Site B | F = 3, S = 5; after: F = 1, S = 5; C = $2.5M | Rock cut over a bridge approach; full slope stabilization |
| Site C | F = 5, S = 3; after: F = 2, S = 3; C = $0.6M | Culvert-driven settlement; culvert replacement and drainage |
| Budget | About $2.0M | Available this year |
Rank by efficiency: Site C (15 per $1M), Site A (6.7), Site B (4.0). Fund C and A this year ($1.8M, 17 points of risk reduction) and program B for next year.
Ranking by the before score alone would put A first (16) and treat B and C as equal (15). Ranking by efficiency shows that the culvert repair at C removes almost as much risk as the expensive rock stabilization at B for a quarter of the cost.
Judgment still applies: Site B has a severity of 5 (a rock cut over a bridge approach). If its frequency rating is rising, or if it is on a passenger route, it may justify interim measures this year, such as scaling, a slide fence or monitoring under a TARP (Chapter 5.5), while the full stabilization is designed and funded. The remaining $0.2M could fund those interim measures.
A cut slope beside the main track of a Class I railroad located in Pennsylvania keeps raveling onto the ditch and needs a nailed facing over a 300-ft length (about 9,000 ft² of face). Two facings meet the stability and design-life requirements: reinforced shotcrete, or galvanized high-tensile steel wire mesh with an erosion mat. The owner reports emissions and wants the carbon footprint of each option alongside the cost estimate (Section 7.4.10).
| Variable | Value | Description |
|---|---|---|
| Option A materials | Shotcrete 545,000 lb (including 25% rebound); nail grout cement 113,000 lb; steel nails and reinforcement 32,700 lb | Shotcrete facing |
| Option B materials | Mesh steel 5,400 lb; zinc 160 lb; nail steel 19,200 lb; nail grout cement 113,000 lb; polypropylene mat 450 lb | Wire mesh facing |
| Factors (Table 7.4-10) | Concrete 0.135; cement 0.83; reinforcing steel 1.25; primary steel 1.7; zinc 2.46; polypropylene 2.0 lb CO2e/lb | GWP per lb of material |
| Transport | 40 miles by truck at 0.72 lb CO2e per ton-mile | All materials |
(a) About 218,000 lb CO2e. (b) About 130,000 lb CO2e. (c) The nail grout cement dominates both options, so B saves about 40%, less than the four to five times reported in Section 7.4.10.
The saving here is smaller than in the published comparison because the same nails are used in both options and their grout dominates. The next places to cut carbon are the nails themselves: fewer or shorter nails where the design allows, or a grout with supplementary cementitious material. Check the factors against current supplier declarations before reporting the numbers, and note that delivery by work train instead of truck would cut the small transport share further.
A 20-ft high-plasticity clay fill below the main track of a Class I railroad located in Texas has a shallow slide 100 ft long that has pushed the toe into the ditch after every wet season. Inclinometers show the slip surface is 4 to 6 ft deep. The railroad wants a repair that can be installed from the slope face in short work windows, and recycled plastic pins are proposed (Section 7.4.9). The engineer must choose the pin spacing that raises the factor of safety to 1.40 and estimate the number of pins and working days.
| Variable | Value | Description |
|---|---|---|
| MD, MR | 300,000 and 315,000 lb-ft per ft of slope length | Driving and resisting moments from back-analysis (FS = 1.05) |
| FStarget | 1.40 | Required factor of safety after repair |
| P | 1,200 lb per pin | Design lateral resistance per pin at the slip surface, reduced for creep (from limit-resistance curves or load tests) |
| R | 40 ft | Slip circle radius; pin force taken as acting at R |
| Rows | 6 rows of 10-ft pins, 4 ft apart down the slope | Rows that cross the slip surface |
| L; rate | 100 ft; 100 to 120 pins per day | Repair length and installation rate |
(a) 105,000 lb-ft per ft of slope. (b) 2.19 pins per ft, so pins at 2.5 ft along the slope in rows 4 ft apart (FS ≈ 1.43). (c) 240 pins, about 2 to 3 working days.
This is a simplified moment check that treats every pin as mobilizing its full design resistance at the slip surface; pins near the crest and toe, where the slip surface is shallow, may mobilize less, so check the layout with a slope stability program that models pins as reinforcement. Close the spacing near the crest where movement threatens the shoulder, extend the rows 10 ft beyond each end of the slide, restore drainage at the toe, and set survey points to compare pinned and unpinned lengths (Section 7.4.9).