7.4.6 Worked Example

Treating the cuts and embankments of a railroad as an asset portfolio: inventory, condition, deterioration, prioritization and the choice of remedial works.
Author: Daniel P. Colwell
7.4.6 Worked Example
The example uses generic sites and costs and is not taken from any client project. It follows the five-part format.
Example 7.4-1: Ranking Three Earthwork Repairs by Risk Reduction per Dollar

A district has budget for about $2 million of earthwork repairs this year. Three candidate sites have been rated on the GHRM 5 × 5 matrix, with the expected rating after the proposed repair and its estimated cost.

Given

VariableValueDescription
Site AF = 4, S = 4; after: F = 2, S = 4; C = $1.2MEmbankment slide; soldier pile wall
Site BF = 3, S = 5; after: F = 1, S = 5; C = $2.5MRock cut over a bridge approach; full slope stabilization
Site CF = 5, S = 3; after: F = 2, S = 3; C = $0.6MCulvert-driven settlement; culvert replacement and drainage
BudgetAbout $2.0MAvailable this year

Required

  • Risk scores before and after for each site
  • Risk reduction per $1M
  • Ranked program within the budget

Equations

  1. Eq. 7.4-1: R = F × S — risk score
  2. Eq. 7.4-2: E = (Rbefore − Rafter)/C — risk reduction per $1M

Steps

Step 1 · Site A
R: 4 × 4 = 16 → 2 × 4 = 8; reduction 8; E = 8 / 1.2
E ≈ 6.7 per $1M
↓
Step 2 · Site B
R: 3 × 5 = 15 → 1 × 5 = 5; reduction 10; E = 10 / 2.5
E = 4.0 per $1M
Spot check: Largest reduction, but the most expensive.
↓
Step 3 · Site C
R: 5 × 3 = 15 → 2 × 3 = 6; reduction 9; E = 9 / 0.6
E = 15 per $1M
Spot check: Cheapest site gives the most risk reduction per dollar.
↓
Step 4 · Rank and fit to budget
C ($0.6M) + A ($1.2M) = $1.8M ≤ $2.0M; B would exceed budget
Program: C, then A; B next year
Spot check: Total reduction 9 + 8 = 17 points for $1.8M, against 10 points for $2.5M at B alone.
↓
Solution
Rank by efficiency: Site C (15 per $1M), Site A (6.7), Site B (4.0). Fund C and A this year ($1.8M, 17 points of risk reduction) and program B for next year.

Solution

Rank by efficiency: Site C (15 per $1M), Site A (6.7), Site B (4.0). Fund C and A this year ($1.8M, 17 points of risk reduction) and program B for next year.

Ranking by the before score alone would put A first (16) and treat B and C as equal (15). Ranking by efficiency shows that the culvert repair at C removes almost as much risk as the expensive rock stabilization at B for a quarter of the cost.

Judgment still applies: Site B has a severity of 5 (a rock cut over a bridge approach). If its frequency rating is rising, or if it is on a passenger route, it may justify interim measures this year, such as scaling, a slide fence or monitoring under a TARP (Chapter 5.5), while the full stabilization is designed and funded. The remaining $0.2M could fund those interim measures.

Example 7.4-2: Carbon Footprint of Two Facings for a Nailed Cut Slope

Problem Statement

A cut slope beside the main track of a Class I railroad located in Pennsylvania keeps raveling onto the ditch and needs a nailed facing over a 300-ft length (about 9,000 ft² of face). Two facings meet the stability and design-life requirements: reinforced shotcrete, or galvanized high-tensile steel wire mesh with an erosion mat. The owner reports emissions and wants the carbon footprint of each option alongside the cost estimate (Section 7.4.10).

Track Nails (both options) Facing:A shotcrete, orB steel wire mesh Given (300-ft cut, 9,000 ft² face) A: shotcrete 545,000 lb nail grout cement 113,000 lb steel (nails, rebar) 32,700 lb B: mesh steel 5,400 lb; zinc 160 lb nail steel 19,200 lb nail grout cement 113,000 lb erosion mat 450 lb Haul 40 miles by truck Required: footprint of A and B(lb CO₂e) and largest item
Figure 7.4-1. Example 7.4-2: nailed cut slope with two facing options.

Given

VariableValueDescription
Option A materialsShotcrete 545,000 lb (including 25% rebound); nail grout cement 113,000 lb; steel nails and reinforcement 32,700 lbShotcrete facing
Option B materialsMesh steel 5,400 lb; zinc 160 lb; nail steel 19,200 lb; nail grout cement 113,000 lb; polypropylene mat 450 lbWire mesh facing
Factors (Table 7.4-10)Concrete 0.135; cement 0.83; reinforcing steel 1.25; primary steel 1.7; zinc 2.46; polypropylene 2.0 lb CO2e/lbGWP per lb of material
Transport40 miles by truck at 0.72 lb CO2e per ton-mileAll materials

Required

  • (a) Footprint of Option A
  • (b) Footprint of Option B
  • (c) Which item dominates, and the saving

Equations

  1. Eq. 7.4-4: Footprint = Σ(mass × GWP) + Σ(ton-miles × 0.72)

Steps

Step 1 · (a) Option A materials
545,000 × 0.135 + 113,000 × 0.83 + 32,700 × 1.25 = 73,600 + 93,800 + 40,900
208,300 lb CO2e
↓
Step 2 · (a) Option A transport
690,700 lb = 345 tons; 345 × 40 × 0.72
9,900 lb; total A ≈ 218,000 lb CO2e
↓
Step 3 · (b) Option B materials
5,400 × 1.7 + 160 × 2.46 + 19,200 × 1.25 + 113,000 × 0.83 + 450 × 2.0 = 9,200 + 400 + 24,000 + 93,800 + 900
128,300 lb CO2e
↓
Step 4 · (b) Option B transport
138,200 lb = 69 tons; 69 × 40 × 0.72
2,000 lb; total B ≈ 130,000 lb CO2e
Spot check: B uses one-fifth of the mass of A, and its haul footprint is about one-fifth of A’s: 2,000/9,900 = 0.20.
↓
Step 5 · (c) Compare
93,800 / 130,000 for the nail grout in B; (218,000 − 130,000) / 218,000
Nail grout cement is about 72% of B; B saves about 40%
↓
Solution
A ≈ 218,000 lb CO2e (109 tons); B ≈ 130,000 lb CO2e (65 tons); B is about 40% lower.

Solution

(a) About 218,000 lb CO2e. (b) About 130,000 lb CO2e. (c) The nail grout cement dominates both options, so B saves about 40%, less than the four to five times reported in Section 7.4.10.

The saving here is smaller than in the published comparison because the same nails are used in both options and their grout dominates. The next places to cut carbon are the nails themselves: fewer or shorter nails where the design allows, or a grout with supplementary cementitious material. Check the factors against current supplier declarations before reporting the numbers, and note that delivery by work train instead of truck would cut the small transport share further.

Example 7.4-3: Laying Out Recycled Plastic Pins for a Shallow Slide

Problem Statement

A 20-ft high-plasticity clay fill below the main track of a Class I railroad located in Texas has a shallow slide 100 ft long that has pushed the toe into the ditch after every wet season. Inclinometers show the slip surface is 4 to 6 ft deep. The railroad wants a repair that can be installed from the slope face in short work windows, and recycled plastic pins are proposed (Section 7.4.9). The engineer must choose the pin spacing that raises the factor of safety to 1.40 and estimate the number of pins and working days.

Track Slip surface, R = 40 ft 6 rows of 10-ft pins, 4 ft apart Required: spacing salong the slope, pin count Given (per ft of slope)MD = 300,000 lb-ftMR = 315,000 lb-ft (FS 1.05)Target FS = 1.40Pin resistance 1,200 lbRepair length 100 ft100–120 pins per day
Figure 7.4-2. Example 7.4-3: slip surface crossed by rows of plastic pins.

Given

VariableValueDescription
MD, MR300,000 and 315,000 lb-ft per ft of slope lengthDriving and resisting moments from back-analysis (FS = 1.05)
FStarget1.40Required factor of safety after repair
P1,200 lb per pinDesign lateral resistance per pin at the slip surface, reduced for creep (from limit-resistance curves or load tests)
R40 ftSlip circle radius; pin force taken as acting at R
Rows6 rows of 10-ft pins, 4 ft apart down the slopeRows that cross the slip surface
L; rate100 ft; 100 to 120 pins per dayRepair length and installation rate

Required

  • (a) Added resisting moment needed per ft of slope
  • (b) Pins needed per ft of slope length and the spacing along the slope
  • (c) Total pins and working days

Equations

  1. Eq. 7.4-3: FS = (MR + ΔMR) / MD
  2. Eq. 1: ΔMR = (nrows / s) P R per ft of slope length, with s the pin spacing along the slope

Steps

Step 1 · (a) Moment needed
1.40 × 300,000 − 315,000
ΔMR = 105,000 lb-ft per ft
↓
Step 2 · (b) Pins per ft
Each pin gives 1,200 × 40 = 48,000 lb-ft; 105,000 / 48,000
2.19 pins per ft of slope length
↓
Step 3 · (b) Spacing
s = 6 rows / 2.19 = 2.74 ft; round down
s = 2.5 ft along the slope (grid 2.5 ft × 4 ft)
Spot check: With s = 2.5 ft: ΔMR = (6/2.5) × 48,000 = 115,200; FS = (315,000 + 115,200)/300,000 = 1.43. A 3-ft spacing gives only 1.37.
↓
Step 4 · (c) Pins and days
100/2.5 = 40 per row; 40 × 6 rows; 240 / 100 to 240 / 120
240 pins; about 2 to 2.5 working days
↓
Solution
2.5 ft × 4 ft grid; FS ≈ 1.43; 240 pins; 2 to 3 days of installation.

Solution

(a) 105,000 lb-ft per ft of slope. (b) 2.19 pins per ft, so pins at 2.5 ft along the slope in rows 4 ft apart (FS ≈ 1.43). (c) 240 pins, about 2 to 3 working days.

This is a simplified moment check that treats every pin as mobilizing its full design resistance at the slip surface; pins near the crest and toe, where the slip surface is shallow, may mobilize less, so check the layout with a slope stability program that models pins as reinforcement. Close the spacing near the crest where movement threatens the shoulder, extend the rows 10 ft beyond each end of the slide, restore drainage at the toe, and set survey points to compare pinned and unpinned lengths (Section 7.4.9).