Owners increasingly ask for the carbon footprint of a repair alongside its cost. A simple footprint can be estimated from the materials and transport each option needs: list the mass of each material, multiply by an emission factor, and add the transport. Emission factors are expressed as global warming potential (GWP): the mass of CO2-equivalent per unit mass of material, which counts all greenhouse gases, weighted by their effect, and not only CO2 from burning fuel (Gross et al. 2018).
Footprint (lb CO2e) = Σ (mass of material × GWP factor) + Σ (ton-miles hauled × transport factor) (Eq. 7.4-4)
| Material or process | GWP (lb CO2e per lb) |
|---|---|
| Reinforcing steel (mixed converter and electric-arc steel) | 1.25 |
| Primary (converter) steel | 1.7 |
| Portland cement | 0.83 |
| Concrete or shotcrete (about 630 lb cement per yd³) | 0.135 |
| Zinc for galvanizing | 2.46 |
| Aluminum | 11.7 |
| PVC pipe | 2.16 |
| Polypropylene erosion mat | 2.0 |
| Truck transport | 0.72 lb CO2e per ton-mile |
For a 330-ft length of nailed slope, a facing of high-tensile steel wire mesh with nails used about 37 tons of materials, most of it the cement grout for the nails. An equivalent reinforced shotcrete facing with nails used about 680 tons, mostly shotcrete (including about 25% rebound loss). The GWP of the mesh option was four to five times lower, because concrete has a high footprint per job and because the lighter option needed less hauling. The open mesh also lets the slope be vegetated and does not trap water behind the facing.
For railroad work: Add a footprint line to the option comparison in Section 7.4.5 when the owner reports emissions. Materials delivered by work train rather than truck have a lower transport footprint per ton-mile, so record how material will reach the site. Do not let the footprint override safety, track outage limits or design life; use it to choose between options that meet those.
A worked comparison of two facings is Example 7.4-2 (Section 7.4.6).