The desktop study usually starts from the track chart or aerial imagery, and curve data come with it. Curvature matters to the geotechnical work in several ways: superelevation thickens the ballast under the high rail, sharp curves (over 3°) add centrifugal force to shoring design next to track (Chapter 7.1), and the speeds the curve can carry decide whether critical-speed checks (Chapter 6.5) or passenger ride limits apply. A Class I railroad's recommended method, based on the standard balance equation, is summarized here.
Equation 3.2-1. Balance, spiral length and maximum speed
E = superelevation (in.), D = degree of curve (chord definition, R = 50/sin(D/2)), V = speed (mph), Eu = underbalance (in.). The 62E term keeps the runoff no steeper than 1 in. in 62 ft (freight car torsion); 1.63 EuVp is for passenger comfort.
| Limit | Value |
|---|---|
| Maximum | Lesser of balanced elevation and 5 in. (more only with the chief engineer's authority) |
| Minimum | Greatest of 1/2 in., balanced freight − 2 in., balanced passenger − 3 in. |
| Choice within the range | As low as practical, since most tonnage is slow heavy freight that damages the low rail |
| Reverse curves | At least 100 ft of tangent between spirals |
| Grade compensation (industry track standard) | 0.04% per degree of curve |
| Result | Value |
|---|---|
| Balanced elevation, freight / passenger | 5" / 7 7/8" |
| Allowed range | 4 7/8" to 5" |
| Superelevation applied | 4 7/8" |
| Minimum spiral (passenger comfort governs over freight torsion, 302 ft) | 367 ft |
| Maximum passenger speed at Eu = 3 in. | 75 mph |
Open the curve superelevation calculator →
Degree of curve and radius, balanced and allowable superelevation, spiral length, maximum speeds and grade compensation.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.