Finish with an expected profile, stated as a simple table with depth ranges, and a list of what the borings must answer. The profile below, assembled from 43 legacy borings for a parking expansion, set the depths of both the light-tower and the pavement borings.
| Depth (typical) | Stratum | Notes |
|---|---|---|
| 0 to 1 ft | Topsoil, gravel or asphalt | Topsoil often mixed with cinders |
| 0.5 to 3 to 6 ft | Slag, cinder and urban fill | Very dense, cemented slag; auger refusal in several borings; chemical odor in one |
| 3 to 6 ft (local) | Organic clay and peat | Water content over 100 percent; drives settlement |
| 4 to 8 to 13.5 ft | Lacustrine sand and silt | Very loose to medium dense, saturated; N typically 2 to 8 |
| 8 to 13.5 to 30+ ft | Glacial till | Stiff to very stiff lean to fat clay; Qu about 1.0 to 3.7 tsf; no legacy boring below 30 ft |
| 1 to 6 ft | Groundwater | Close to the lake level |
The same model drives design implications: light-tower shafts will need casing or slurry through the loose saturated sand and will take their capacity in the till; pavement subgrade will need undercut and geosynthetics or full-depth reclamation; organic pockets control settlement; slag and odors call for screening and a cuttings plan.