Chapter 3.1 — Scoping Proposals

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell

This chapter sets out how a ground hazard or geotechnical assignment is scoped and proposed. It follows the proposal from the first request through the desktop look, the boring layout, the subconsultant quotes and the cost estimate to the assumptions that go out with the fee. The examples are drawn from recent railroad proposals (an intermodal parking expansion on filled marshland and a siding re-grade on steep embankment slopes), with client details removed.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
3.1.0 Purpose and Overview

A proposal does several jobs at once. To the client it is an offer: a scope, a deliverable, a schedule and a fee. To the firm it is a decision about whether that fee can deliver those services to the standard of care. To the project team it is the plan of the work, and the first engineering product on the job, because it fixes what will be explored, tested and analyzed and therefore what the final report can and cannot say. Once signed, it is the contract baseline: its assumptions define what the fee covers and what counts as a change. Table 3.1-1 lists these purposes.

Table 3.1-1. The purposes a proposal serves
PurposeAudienceWhat it has to do
Offer of servicesClientState the scope, deliverable, schedule and fee clearly enough to be accepted and priced competitively
Internal risk assessmentThe firmDecide whether the fee and schedule can deliver the requested services to the standard of care, given what is not known about the site
Plan of the workProject teamFix what will be explored, tested and analyzed, and therefore what the final report can and cannot say
Contract baselineBoth partiesRecord the assumptions and exclusions the fee rests on, so that a change in conditions is recognized as a change (Chapter 8.2)
Statement of known riskClientTell the client, before work starts, which ground and site questions will remain open after the proposed work

Why an internal risk assessment is always done

Two pressures meet in every proposal. The first is uncertainty: the ground has not been explored, the records may be thin, and access, track time and the client’s real question may not be clear from the request. The second is price: most work is won on a competitive fee, or negotiated against a budget the client already has in mind. A thin scope saves money at the proposal stage and costs it back later in change orders, return trips and hedged recommendations. A padded scope loses the work. Under a fixed fee, whatever the proposal fails to anticipate is paid for by the firm.

For that reason an internal risk assessment is made on every proposal, including a sole-sourced estimate requested by email. It is not shown to the client. It compares two things: what the client expects (the decision to be supported, the deliverable, the schedule, the budget and how firm an answer is wanted) and the level of effort needed to deliver it. Where the two do not line up, the gap is the proposal’s risk. Table 3.1-2 lists the usual places a mismatch appears.

Table 3.1-2. Client expectations set against the level of effort they require
ItemClient expectationLevel of effort it requiresSign of a mismatch
Decision to be supportedReplace, repair or monitor; design-level or screeningExploration depth and analysis matched to that decisionA design-level answer requested on a screening budget
DeliverableLetter, data report, full recommendations report, design inputEngineering and review hours (Chapter 3.7)“Brief letter” that must carry design parameters
ScheduleReport date, often tied to a work windowTrack time, drilling availability, lab turnaroundReport due before lab results can exist
BudgetStated or implied ceilingSum of tasks at realistic production ratesFee forced down by removing borings rather than tasks
Site accessAssumed easyHi-rail or track-mounted rig, flagging, right-of-entry, clearing (Chapter 3.6)No access route visible in imagery
Certainty of the answerA firm recommendationEnough data to support it without hedgingVariable ground with one boring proposed

Applying the risk rating to the proposal

The risk rating theory of Chapter 3.8 applies directly. Each uncertainty is rated on the same 1-to-5 scales and scored with the same equation, R = F × S. Here F is the likelihood that the conditions or the effort will differ materially from what the fee assumes, and S is the consequence to the firm and the client if they do (Table 3.1-3). The scores fall into the five levels of Table 3.8-72, and each level calls for a particular proposal response (Table 3.1-4). As in the risk ratings, the worst item governs.

Table 3.1-3. Likelihood and severity scales for proposal risk (same 1-to-5 scales as Section 3.8.22)
RatingF: likelihood that conditions or effort differ materially from what the fee assumesS: consequence if they do
1Rare: recent borings at the site; simple, documented geology; access confirmedNegligible: absorbed in normal margin (less than about 2% of fee)
2Unlikely: good nearby data and simple geology; access route visibleMinor: 2–5% of fee or a few days of schedule
3Possible: regional data only; moderate variability expectedModerate: 5–15% of fee; schedule slip; a change order needed
4Likely: little or no data; variable or problem geology; access unknownMajor: 15–30% of fee; remobilization; recommendations must be qualified
5Almost certain: no data and known difficult conditionsSevere: more than 30% of fee; standard of care cannot be met as scoped; safety, liability or relationship at stake
Table 3.1-4. Proposal response by risk level (levels and score ranges from Table 3.8-72)
LevelR = F × SProposal response
1 Low1–2Price as scoped; standard assumptions
2 Guarded3–5Price as scoped; name the item in the assumptions
3 Elevated6–10Scope it, or carry it with a stated assumption, an optional task or a contingency allowance
4 High12–16Do more desktop work before pricing; then scope it directly, phase the work, or price it on unit rates
5 Severe20–25Do not price as a fixed fee. Propose a Phase 1 study only, time and materials, or decline

Desktop study first, then scope the residual uncertainty

The first rating is made from the request alone, and it is usually High, because almost nothing is known. Pricing at that point means either padding every task or gambling on the ground. The next step is a desktop study (Chapter 3.2) sized to the proposal: geology and soil maps, legacy borings, as-built plans, imagery and lidar, hazard databases and the railroad’s own history of the site. It costs hours, not days, and it settles what public and railroad records can settle.

The items are then rated again. Whatever the desktop study could not settle is the residual uncertainty, and the residual uncertainty is the scope of work. Each boring, sample, test and analysis in the proposal should answer one of the residual items, and each residual item should be answered by something in the scope or carried by a stated assumption, optional task or contingency. Fieldwork is not proposed for what the desk work already answered. Figure 3.1-1 shows the sequence.

Uncertainty in the requestGround, groundwater, access, history and client expectations all unknownAfter the desktop studyResidual uncertainty: what public and railroad records cannot settleSettled at desk cost:not proposed as fieldwork= Proposed scope of workBorings, sampling, lab and analyses aimed only at the residualLeft after the scopeCarried in writing, not in the fee:Exclusions, optional tasks, contingency and the change-order clause(Sections 3.1.3 and 3.1.6, Chapter 8.2)Rule:research what can be known; drill what cannot; write down what is left.Bar length is schematic. Each bar is the same list of uncertainties, re-rated with R = F × S (Section 3.8.22).
Figure 3.1-1. How the proposal narrows uncertainty. The desktop study removes what can already be known, the scope of work is built from what remains, and the proposal’s assumptions carry the rest.

How the proposal is put together

1. Read the request
Client expectations: the decision, deliverable, schedule, budget (Section 3.1.1)
▬▸
2. First risk rating
Rate each uncertainty F × S before any research
▬▸
3. Desktop study
Geology, soils, legacy borings, imagery, access, history (Chapter 3.2)
▬▸
4. Re-rate
What the desktop study settled; list the residual uncertainty
▬▸
5. Scope the residual
Borings, sampling, lab and analyses aimed at what is still unknown (Sections 3.1.2, Chapter 3.3)
▬▸
6. Quotes and estimate
Subconsultants, labor, track time (Section 3.1.5, Chapter 3.7)
▬▸
7. Decide and send
Assumptions, exclusions, contingency, go or no-go (Sections 3.1.3, 3.1.6, 3.1.7)

Most railroad requests arrive as a short email from the client’s project manager rather than a formal request for proposal. Many are sole-sourced and ask for a cost estimate with a bullet list of assumptions, not a full proposal document. The process is the same for both; only the amount written out for the client differs. The internal ratings are kept in the project file either way.

Table 3.1-5. Proposal stages, outputs and who does the work
StageOutputTypical leadWhere
Read the requestOne-paragraph statement of the problem, the decision the work supports and the client’s expectationsProject managerSection 3.1.1
First risk ratingList of uncertainty items, each rated F and SProject manager with geotechnical leadThis section; Section 3.8.22
Desktop studySite map (KMZ), legacy boring and well logs, soil and geology summary, imagery, access, site historyProject or design engineerChapter 3.2
Re-rateResidual uncertainty list with revised F and SGeotechnical leadSection 3.2.6
Scope the residualBoring plan, depths and sampling, lab program, analyses, deliverableProject manager with geotechnical leadSection 3.1.2; Chapter 3.3
Quotes and estimateDrilling and laboratory quotes; task-by-task hours, track time, travelProject managerSection 3.1.5; Chapter 3.7
Decide and sendAssumptions and exclusions, contingency, go or no-go; estimate or proposal to the clientProject managerSection 3.1.3, 3.1.6, 3.1.7

How the rest of this chapter does it

  • Section 3.1.1: reading the request and pinning down the client’s expectations, the first half of the comparison.
  • Section 3.1.2: building the scope from the residual uncertainty, with Chapter 3.3 for boring layout, depth and sampling.
  • Section 3.1.3: writing down what the scope does not cover, so that it is carried by the contract rather than the fee.
  • Section 3.1.4: phasing, which is the usual answer to a High rating that the desktop study cannot bring down.
  • Section 3.1.5: choosing fixed fee, unit rates or time and materials to suit the residual risk, with Chapter 3.7 for the estimate itself.
  • Section 3.1.6: how contract terms share the risk that remains, with Chapter 8.2 for change orders.
  • Section 3.1.7: the review before sending, including the go or no-go decision.
Rate before you research, research before you scope, and scope only what the research could not answer. Whatever is left goes in the assumptions, in writing.

Worked example

The example shows the ratings at the three points where they change: as the request arrives, after the desktop study and after the scope is drafted. It is laid out in five parts: what is known (Given), what is wanted (Required), the equations, a flow chart of the steps with a spot check at each step, and the solution with what it means for the proposal.
Example 3.1-1: Rating a Culvert Replacement Request Before and After the Desktop Study

A Class I railroad located in Middle Tennessee asks, by email, for a fixed-fee proposal for a geotechnical exploration and recommendations to replace a 60-inch corrugated metal pipe culvert under a 25-ft main-line embankment. The report is wanted in four weeks; no budget is stated. Before any research, the proposal team lists six things it does not know and rates each with the scales in Table 3.1-3. It rates them again after the desktop study and again after drafting the scope.

Mapped limestone (karst region): depth and soundness unknownMain track60-in. CMP?? fill strength25 ftponding upstreamGivenFixed fee; report in 4 weeksItems A–F, each with F and Son receipt, after desk, after scopeBase fee estimate $48,000p and C for residual items C and ERequiredR and level of each item, 3 stagesGoverning proposal levelScope or assumption for each itemContingency K; go or no-goBlack = given; red = required
Given and required for Example 3.1-1.

Given

ItemF / S on receiptDesktop findingF / S after deskF / S after scope
A Depth to rock under the culvert4 / 4Bridge plans 400 ft away show limestone at 18–22 ft2 / 41 / 4
B Groundwater and seepage through the fill3 / 3Imagery shows ponding upstream in wet seasons; no records3 / 32 / 2
C Fill type and strength4 / 3No construction records; fill origin unknown4 / 32 / 3
D Rig access and track time4 / 4Lidar and imagery show a farm road to the downstream toe; crest by hi-rail only2 / 32 / 2
E Karst: voids or pinnacled rock3 / 5State geologic map: limestone; sinkhole inventory: three within 0.5 mile3 / 52 / 4
F Report date versus lab turnaround4 / 3Not a desktop item; settled by a call with the client (Section 3.1.1)2 / 31 / 3
FeeBase fee estimate for the scoped work: $48,000
pC, CCItem C: probability 0.25 that the fill needs added consolidation testing and analysis costing $6,000
pE, CEItem E: probability 0.20 that a void or pinnacle needs two added borings and the resistivity survey, costing $18,000

Required

  • The risk score R and level of each item on receipt, after the desktop study and after the scope
  • The governing proposal level at each stage and the response it calls for (Table 3.1-4)
  • Which items become scope and which become stated assumptions
  • A contingency allowance for the residual cost exposure, and whether to submit a fixed fee

Equations

  1. Eq. 1: R = F × S — risk score, 1 to 25 (Section 3.8.22)
  2. Eq. 2: Level = 1 Low (1–2), 2 Guarded (3–5), 3 Elevated (6–10), 4 High (12–16), 5 Severe (20–25) — Table 3.8-72
  3. Eq. 3: Proposal level = max(LevelA … LevelF) — the worst item governs, as in the risk ratings
  4. Eq. 4: K = Σ pi Ci — expected cost of the residual items carried as contingency (Section 8.2.8)

Steps

Step 1 · Rate the request as received (Eq. 1, Eq. 2)
Uses: F and S on receipt
A 4×4, B 3×3, C 4×3, D 4×4, E 3×5, F 4×3
A = 16 (High); B = 9 (Elevated); C = 12 (High); D = 16 (High); E = 15 (High); F = 12 (High)
Spot check: 15 lies in the 12–16 band (3×5 is listed as High in Table 3.8-72), and 9 lies in 6–10, Elevated.
↓
Step 2 · Governing level on receipt (Eq. 3)
Uses: levels from Step 1
Five of six items are High; none is Severe
Proposal level = 4 High → do the desktop study before pricing (Table 3.1-4)
Spot check: No item reaches 20, so a fixed fee is not ruled out; it is only premature.
↓
Step 3 · Re-rate after the desktop study (Eq. 1, Eq. 2)
Uses: F and S after desk
A 2×4, B 3×3, C 4×3, D 2×3, E 3×5, F 2×3
A = 8 (Elevated); B = 9 (Elevated); C = 12 (High); D = 6 (Elevated); E = 15 (High); F = 6 (Elevated)
Spot check: The desk work lowered F for A, D and F only. B, C and E are unchanged, because records cannot show groundwater, fill strength or voids. Those three are the residual uncertainty.
↓
Step 4 · Turn the residual into scope or assumptions
Uses: Step 3 levels; Table 3.1-4
Every item still Elevated or higher gets a line in the proposal: scope (A, B, C, E) or a stated assumption (D, F)
Scope: 2 borings to rock with 10 ft of core each, continuous SPT in fill, 1 piezometer, lab program; optional resistivity survey
Spot check: Nothing is proposed for what the desk work already settled: no boring is added to find rock depth beyond confirming it at the culvert.
↓
Step 5 · Re-rate what is left after the scope (Eq. 1, Eq. 2, Eq. 3)
Uses: F and S after scope
A 1×4, B 2×2, C 2×3, D 2×2, E 2×4, F 1×3
A = 4 (Guarded); B = 4 (Guarded); C = 6 (Elevated); D = 4 (Guarded); E = 8 (Elevated); F = 3 (Guarded); governing level = 3 Elevated
Spot check: The highest score is 8, inside 6–10, so the proposal is Elevated, not High: a fixed fee with stated assumptions and a contingency is appropriate.
↓
Step 6 · Contingency for the Elevated residual (Eq. 4)
Uses: pC, CC, pE, CE, base fee
K = 0.25 × $6,000 + 0.20 × $18,000 = $1,500 + $3,600
K = $5,100, or 10.6% of the $48,000 base fee
Spot check: 5,100 / 48,000 = 0.106. Item E alone is $3,600, 71% of K, which agrees with E being the highest residual score.
↓
Solution
High on receipt → desktop study → residual items B, C and E scoped, D and F assumed → Elevated after scope; go with a $48,000 fixed fee, a $5,100 contingency (or an optional task) and stated assumptions.

Solution

Submit a fixed fee of $48,000 with a $5,100 (about 11%) contingency allowance or an optional karst task, and stated assumptions for access, track time and the report date. As received, the request rated High on five of six items, which calls for more research, not a price. The desktop study, costing a few hours, settled rock depth, access and schedule. It could not settle groundwater, fill strength or karst, and those three items are exactly what the borings, piezometer, rock core and lab program are aimed at. What remains after that scope is Elevated, which a fixed fee can carry when the assumptions are written down.

The ratings also tell the client something. Item E stays Elevated even after the scope: two borings through a karst embankment can miss a void. Saying so in the proposal, with the resistivity survey offered as an option, sets the client’s expectation before the work starts rather than in a change order afterwards.

3.1.1 Understanding the Request

Start by writing down, in one paragraph, what the client is trying to decide. Requests rarely say this directly. "Schedule the additional borings needed for the steeper side slopes" really means "tell us whether steepening the fill is cheaper than buying the neighbor's land." "Survey, geotech and environmental for a parking expansion" really means "tell us what it will take to build heavy-duty pavement and light towers on this ground." The scope follows from that sentence, not from the list of tasks in the email.

3.1.1.1 Questions to Answer Before Writing Scope

Table 3.1-6. Questions to answer before scoping
QuestionWhy it mattersWhere the answer usually comes from
What is being built or protected, and what loads does it carry?Sets boring depths, tests and analyses (track, pavement for container handlers, light towers, walls, culverts)Request email, concept plans, client project manager
What decision will the report support?Keeps the scope aimed at the question, such as slope steepening versus property purchaseConversation with the client project manager
What has already been done at or near the site?Legacy borings can reduce the program or show where the gaps arePrevious reports, project files, public well and boring databases
Are there ground rules?Some clients fix the number of light towers, ban infiltration tests in high groundwater or cap the budgetRequest email
What is the budget limit and the schedule?Determines whether locations are priced together or separately and when field work can happenClient project manager
Is the work sole-sourced or competitive?Sole-sourced work should carry conservative assumptions rather than a cut scopeRequest email
Who else is on the team?Survey, environmental, drainage and structures scopes must not overlap or leave gapsInternal project manager

Record the request, the date and who sent it at the top of the proposal file. When the scope changes during development (borings added, depths cut, a location dropped), date each change and say who agreed to it. That history is what lets the team explain the final number and later defend it.

Example. On an intermodal parking expansion the request gave three ground rules: assume eight high-mast light towers at about 500 ft spacing, perform no infiltration tests because groundwater is very high, and keep assumptions conservative because the work was sole-sourced. Each rule changed the boring layout and the lab program before a single quote was requested.
3.1.2 Scope of Services and Deliverables

The scope is written by task, in the order the work will be done, so that the cost estimate (Chapter 3.7) can follow it line for line. A typical railroad geotechnical scope has the tasks below; ground hazard assignments add the risk assessment task.

Table 3.1-7. Standard task structure for geotechnical and ground hazard scopes
TaskContentNotes
A. Project managementSetup, coordination, client meetings, invoicing, quality controlUsually 8 to 12% of labor hours
B. Ground hazard risk managementDesktop study, field assessment, risk rating, alternatives (Chapters 3.2, 3.8 and 3.8)Only on ground hazard work
C. Engineer reconnaissanceSite visit to confirm access, utilities and boring locations (Chapter 3.4)Travel and on-site time; one trip is normal
D. Subsurface field explorationUtility clearance, mobilization, drilling oversight, logging, demobilizationDriller is a subconsultant; the field engineer is with the rig every day
E. Laboratory testingIndex, strength, consolidation, compaction, corrosion testsIn-house or by the drilling subconsultant's laboratory
F. Geotechnical engineeringTyped logs, analysis, report or memorandumDeliverable is set by the client's question (Chapter 8.1)
G to M. Other disciplinesPavement design, survey, hydrology, structures, permitting, bid package, construction quality assuranceOnly if requested; coordinate with those teams

3.1.2.1 Describing the Field Program

The field program is described in enough detail that a reviewer could price it: number of borings, depth of each, sampling interval, special sampling (Shelby tubes, rock core, bulk samples), field tests (dynamic cone penetrometer, pocket penetrometer, vane), groundwater readings, screening (photo-ionization detector where fill or odors are expected), backfill method and the number of drilling days. Name the borings in the proposal (for example HML-1 to HML-8 and PB-1 to PB-11) so they can be traced into the field and the report.

Table 3.1-8. Example field programs from two recent railroad proposals
ItemParking and light towers on filled marshlandSteepened siding fill on a hillside
Borings8 light-tower borings to 35 ft; 11 pavement borings to 10 ft (390 ft)8 toe borings to 15 ft; 2 ditch borings to 6 ft (132 ft)
SamplingSPT; DCP to 5 ft in pavement borings; 3 bulk samples for Proctor and CBRContinuous SPT; Shelby tubes in soft clay; NQ core where refusal is shallow (15 ft contingency)
Screening and waterPID on every boring; groundwater at drilling and completionWater at drilling, completion and 24 hours
Rig and daysOne truck rig; about 7 drilling daysTrack or ATV rig with mats; about 2.5 drilling days plus a separate setup
LaboratoryMoisture, Atterberg, -200 and hydrometer, organics, UC, consolidation on peat, Proctor and CBR, corrosion suite on slagMoisture, Atterberg, -200, organics, UC, consolidation, CU triaxial or direct shear, rock UCS
EngineeringDrilled-shaft axial and lateral design; pavement subgrade parameters; undercut; settlement over organicsGlobal stability of 1.5H:1V slopes; shot-rock toe key versus geogrid; quantities by reach
DeliverableGeotechnical reportMemorandum addendum to the earlier report

3.1.2.2 Deliverables

Say what will be delivered, in what form and when: a data report (exploration), a geotechnical report with recommendations (investigation), or a memorandum (Chapters 8.1 and 8.3). State whether typed logs, laboratory sheets, analysis output and quantity tables are included. On ground hazard work, say whether the deliverable includes risk ratings and stabilization alternatives with costs.

A site investigation checklist of the kind used to make sure no part of the program is left out of the scope.
Figure 3.1-2. A site investigation checklist of the kind used to make sure no part of the program is left out of the scope.
3.1.3 Assumptions, Exclusions and Limitations

The assumption list is the part of the proposal the client reads most carefully and the part that protects the scope later. Every item that could change the cost belongs on it. Write each assumption as a plain statement the client can agree or disagree with.

Table 3.1-9. Standard assumptions for railroad geotechnical proposals
TopicTypical assumptionWhy it is stated
AccessBorings are accessible to a truck-mounted rig from public roads or the railroad right-of-way; clearing, matting or a track rig is priced separately where notedClearing and mats can exceed the drilling cost on wooded or wet sites (Chapter 3.6)
Right-of-entryThe railroad will provide right-of-entry on its property; entry onto other property, if needed, will be arranged by the railroad or priced as additional workBoring locations often plot outside the property line once surveyed
Track protectionFlagging and track protection will be provided by the railroad at no cost to the consultantFlagging availability drives the schedule
Train standbyStandby time for trains is budgeted at an assumed number of hours per day (for example 3.5 hours, from past work on the line)Standby is often the largest variable cost
UtilitiesPublic utilities will be located through the one-call system; railroad signal and communication lines will be located by the railroadBorings must be kept a set distance from utilities
Boring locationsLocations may be adjusted in the field for access and utilities; ground elevations will be surveyed or taken from lidarAvoids disputes when borings move
Groundwater and cuttingsCuttings will be spread on site unless screening indicates impacted material, in which case drumming and disposal are additional workFill sites with odor or slag may need drummed cuttings
LaboratoryQuantities are estimates; the tests performed will be selected after the borings are loggedLets the engineer target the tests
ScheduleField work can begin within a stated time after notice to proceed, weather and flagging permittingSets expectations
ExclusionsEnvironmental sampling, wetland delineation, survey, infiltration testing or design by others are excluded unless listedPrevents scope creep
Be conservative where the work is sole-sourced. A client that has chosen the consultant does not need the lowest number; it needs a number that will hold. Carry realistic standby, a mobilization for each separate setup, and a coring contingency where rock may be shallow.
3.1.4 Schedule and Phasing

Phase the work so that each phase answers a question before the next is committed. On a site with two parcels the client may authorize one or both, so each is estimated separately. On a ground hazard program the desktop study and risk rating (Chapters 3.2 and 3.8) decide which sites go to field assessment and which go to borings.

Table 3.1-10. Typical durations for a small railroad geotechnical program
StepTypical durationControlling factor
Proposal preparation1 to 2 weeks (a two-week turnaround is common)Subconsultant quotes
Client approval and notice to proceed1 to 4 weeksClient budget approval
One-call locate, flagging request, right-of-entry1 to 3 weeksFlagging availability; property owners
Reconnaissance and clearing1 to 5 daysVegetation, wetlands, nesting season
Drilling1 to 10 daysNumber of borings, train traffic, access
Laboratory testing2 to 4 weeksConsolidation and triaxial tests
Analysis and report2 to 4 weeks after laboratory dataReview cycle

Two calendar constraints come up often on railroad work: flagging crews tend to start their work week on a Tuesday, and clearing near trees should be done outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them) or after a nest check.

3.1.5 Fee Basis

Most railroad geotechnical work is estimated as time and materials against the client's rate schedule, with subconsultant costs passed through. The estimate itself is built task by task (Chapter 3.7). When a client sets a budget limit, test the scope against it early: in one recent case the first location fit under the limit and the two locations together did not, so they were priced as separate lines and the client was told which one fit.

35%43%18%TotalConsultant laborDrilling subconsultantLaboratory subconsultantTravel and expensesShare of total fee, 19-boring field investigation with report (rounded)
Figure 3.1-3. Typical split of a field-investigation fee where drilling and laboratory testing are subcontracted. Drilling is usually the largest single item, which is why the drilling quote is requested before the estimate is finished.

Lab testing should be carried once. Where the drilling subconsultant's quote includes laboratory testing, zero the consultant's own laboratory lines so the client is not billed twice.

3.1.6 Risk Allocation and Contract Terms

The proposal also allocates risk. Railroad master service agreements usually govern insurance, safety training and payment, but three items should be checked on every job:

  • Differing site conditions. State that the scope is based on the conditions expected from the desktop study, and that refusal, obstructions, impacted material or conditions materially different from those expected will be handled as a change (Chapter 8.2).
  • Subconsultant terms. Subconsultants need insurance that meets the railroad agreement, with both the railroad and the consultant named as additional insured, and a rider if their policy excludes work within 50 ft of track. Payment terms that hold payment until the client pays should be disclosed in the request for quotes.
  • Standard of care and reliance. Make clear what the deliverable is (exploration data or investigation recommendations) and who may rely on it (Chapter 8.1).
Change order triggers belong in the proposal. If standby is assumed at 3.5 hours a day, say so; then extra standby is plainly a change rather than a dispute.
3.1.7 Proposal Review Checklist

Before the estimate goes out, walk the checklist below. It follows the order of the proposal checklist and the railroad project checklist used in practice.

Table 3.1-11. Proposal review checklist
StepCheck
Read the requestOverview, location and scope written down; ground rules listed
Site location and extentLatitude and longitude, city, county and state; study-area polygon in a KMZ
Desktop reviewImagery, soil survey, quadrangle maps (current and historical), geology, well logs, legacy reports (Chapter 3.2)
Special conditionsSeismic, expansive or collapsible soils, karst, fill, organics, contamination
Boring location planBorings named and located; depths, sampling and purpose stated for each
Laboratory programTests and quantities tied to the analyses
Rig and accessRig type, drilling method, clearing and mats, water source (Chapter 3.6)
Contract drillerRFP sent; quote received and checked against the RFP quantities
QuestionsOpen items listed for the client
Draft estimate and scopeLabor, subconsultants, travel; assumptions list
FinalTotals checked; within any budget limit; quote and estimate agree; files saved to the proposal folder
3.1.8 Cross-References
Table 3.1-12. Related chapters
TopicRefer to
Desktop studyChapter 3.2
Drilling scope and subconsultant RFPChapter 3.3
ReconnaissanceChapter 3.4
Access and clearingChapter 3.6
Cost estimateChapter 3.7
Risk ratings and risk assessmentChapter 3.8
Investigation planningChapter 3.9
Exploration versus investigation; change orders; memorandumsChapters 8.1, 8.2 and 8.3
3.1.9 Apps and Tools5

The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this chapter, gathered here from across the manual in the November 2026 restructure: 5 tools (0 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).

Tools

Project Management & Checklists
PMCookbook ChecklistUsed in Chapter 3.9, 3.9.4 Boring Location Planning — Criteria by Project Typeguide onlyGuide
PMProject Book Data SheetUsed in Chapter 3.9, 3.9.4 Boring Location Planning — Criteria by Project Typeguide onlyGuide
PMProposal ChecklistUsed in Chapter 3.9, 3.9.1 Background — Why Planning is a Billable Deliverableguide onlyGuide
PMRR Project ChecklistUsed in Chapter 1.1, 1.1.10 Grade & Slope Stabilization Program — Roles and Processguide onlyGuide
Pavements, Subgrade & Frost
PVCookbook RailroadUsed in Chapter 2.3, 2.3.1 Background: The Railroad Track Structureguide onlyGuide
← Previous · 2.0 The Underworld Chapter 2.13 — Residual, Tropical and Arid Soils
Next · 3.0 Risk Management → Chapter 3.2 — Desktop Study