This chapter sets out how a ground hazard or geotechnical assignment is scoped and proposed. It follows the proposal from the first request through the desktop look, the boring layout, the subconsultant quotes and the cost estimate to the assumptions that go out with the fee. The examples are drawn from recent railroad proposals (an intermodal parking expansion on filled marshland and a siding re-grade on steep embankment slopes), with client details removed.
A proposal does several jobs at once. To the client it is an offer: a scope, a deliverable, a schedule and a fee. To the firm it is a decision about whether that fee can deliver those services to the standard of care. To the project team it is the plan of the work, and the first engineering product on the job, because it fixes what will be explored, tested and analyzed and therefore what the final report can and cannot say. Once signed, it is the contract baseline: its assumptions define what the fee covers and what counts as a change. Table 3.1-1 lists these purposes.
| Purpose | Audience | What it has to do |
|---|---|---|
| Offer of services | Client | State the scope, deliverable, schedule and fee clearly enough to be accepted and priced competitively |
| Internal risk assessment | The firm | Decide whether the fee and schedule can deliver the requested services to the standard of care, given what is not known about the site |
| Plan of the work | Project team | Fix what will be explored, tested and analyzed, and therefore what the final report can and cannot say |
| Contract baseline | Both parties | Record the assumptions and exclusions the fee rests on, so that a change in conditions is recognized as a change (Chapter 8.2) |
| Statement of known risk | Client | Tell the client, before work starts, which ground and site questions will remain open after the proposed work |
Two pressures meet in every proposal. The first is uncertainty: the ground has not been explored, the records may be thin, and access, track time and the client’s real question may not be clear from the request. The second is price: most work is won on a competitive fee, or negotiated against a budget the client already has in mind. A thin scope saves money at the proposal stage and costs it back later in change orders, return trips and hedged recommendations. A padded scope loses the work. Under a fixed fee, whatever the proposal fails to anticipate is paid for by the firm.
For that reason an internal risk assessment is made on every proposal, including a sole-sourced estimate requested by email. It is not shown to the client. It compares two things: what the client expects (the decision to be supported, the deliverable, the schedule, the budget and how firm an answer is wanted) and the level of effort needed to deliver it. Where the two do not line up, the gap is the proposal’s risk. Table 3.1-2 lists the usual places a mismatch appears.
| Item | Client expectation | Level of effort it requires | Sign of a mismatch |
|---|---|---|---|
| Decision to be supported | Replace, repair or monitor; design-level or screening | Exploration depth and analysis matched to that decision | A design-level answer requested on a screening budget |
| Deliverable | Letter, data report, full recommendations report, design input | Engineering and review hours (Chapter 3.7) | “Brief letter” that must carry design parameters |
| Schedule | Report date, often tied to a work window | Track time, drilling availability, lab turnaround | Report due before lab results can exist |
| Budget | Stated or implied ceiling | Sum of tasks at realistic production rates | Fee forced down by removing borings rather than tasks |
| Site access | Assumed easy | Hi-rail or track-mounted rig, flagging, right-of-entry, clearing (Chapter 3.6) | No access route visible in imagery |
| Certainty of the answer | A firm recommendation | Enough data to support it without hedging | Variable ground with one boring proposed |
The risk rating theory of Chapter 3.8 applies directly. Each uncertainty is rated on the same 1-to-5 scales and scored with the same equation, R = F × S. Here F is the likelihood that the conditions or the effort will differ materially from what the fee assumes, and S is the consequence to the firm and the client if they do (Table 3.1-3). The scores fall into the five levels of Table 3.8-72, and each level calls for a particular proposal response (Table 3.1-4). As in the risk ratings, the worst item governs.
| Rating | F: likelihood that conditions or effort differ materially from what the fee assumes | S: consequence if they do |
|---|---|---|
| 1 | Rare: recent borings at the site; simple, documented geology; access confirmed | Negligible: absorbed in normal margin (less than about 2% of fee) |
| 2 | Unlikely: good nearby data and simple geology; access route visible | Minor: 2–5% of fee or a few days of schedule |
| 3 | Possible: regional data only; moderate variability expected | Moderate: 5–15% of fee; schedule slip; a change order needed |
| 4 | Likely: little or no data; variable or problem geology; access unknown | Major: 15–30% of fee; remobilization; recommendations must be qualified |
| 5 | Almost certain: no data and known difficult conditions | Severe: more than 30% of fee; standard of care cannot be met as scoped; safety, liability or relationship at stake |
| Level | R = F × S | Proposal response |
|---|---|---|
| 1 Low | 1–2 | Price as scoped; standard assumptions |
| 2 Guarded | 3–5 | Price as scoped; name the item in the assumptions |
| 3 Elevated | 6–10 | Scope it, or carry it with a stated assumption, an optional task or a contingency allowance |
| 4 High | 12–16 | Do more desktop work before pricing; then scope it directly, phase the work, or price it on unit rates |
| 5 Severe | 20–25 | Do not price as a fixed fee. Propose a Phase 1 study only, time and materials, or decline |
The first rating is made from the request alone, and it is usually High, because almost nothing is known. Pricing at that point means either padding every task or gambling on the ground. The next step is a desktop study (Chapter 3.2) sized to the proposal: geology and soil maps, legacy borings, as-built plans, imagery and lidar, hazard databases and the railroad’s own history of the site. It costs hours, not days, and it settles what public and railroad records can settle.
The items are then rated again. Whatever the desktop study could not settle is the residual uncertainty, and the residual uncertainty is the scope of work. Each boring, sample, test and analysis in the proposal should answer one of the residual items, and each residual item should be answered by something in the scope or carried by a stated assumption, optional task or contingency. Fieldwork is not proposed for what the desk work already answered. Figure 3.1-1 shows the sequence.
Most railroad requests arrive as a short email from the client’s project manager rather than a formal request for proposal. Many are sole-sourced and ask for a cost estimate with a bullet list of assumptions, not a full proposal document. The process is the same for both; only the amount written out for the client differs. The internal ratings are kept in the project file either way.
| Stage | Output | Typical lead | Where |
|---|---|---|---|
| Read the request | One-paragraph statement of the problem, the decision the work supports and the client’s expectations | Project manager | Section 3.1.1 |
| First risk rating | List of uncertainty items, each rated F and S | Project manager with geotechnical lead | This section; Section 3.8.22 |
| Desktop study | Site map (KMZ), legacy boring and well logs, soil and geology summary, imagery, access, site history | Project or design engineer | Chapter 3.2 |
| Re-rate | Residual uncertainty list with revised F and S | Geotechnical lead | Section 3.2.6 |
| Scope the residual | Boring plan, depths and sampling, lab program, analyses, deliverable | Project manager with geotechnical lead | Section 3.1.2; Chapter 3.3 |
| Quotes and estimate | Drilling and laboratory quotes; task-by-task hours, track time, travel | Project manager | Section 3.1.5; Chapter 3.7 |
| Decide and send | Assumptions and exclusions, contingency, go or no-go; estimate or proposal to the client | Project manager | Section 3.1.3, 3.1.6, 3.1.7 |
A Class I railroad located in Middle Tennessee asks, by email, for a fixed-fee proposal for a geotechnical exploration and recommendations to replace a 60-inch corrugated metal pipe culvert under a 25-ft main-line embankment. The report is wanted in four weeks; no budget is stated. Before any research, the proposal team lists six things it does not know and rates each with the scales in Table 3.1-3. It rates them again after the desktop study and again after drafting the scope.
| Item | F / S on receipt | Desktop finding | F / S after desk | F / S after scope |
|---|---|---|---|---|
| A Depth to rock under the culvert | 4 / 4 | Bridge plans 400 ft away show limestone at 18–22 ft | 2 / 4 | 1 / 4 |
| B Groundwater and seepage through the fill | 3 / 3 | Imagery shows ponding upstream in wet seasons; no records | 3 / 3 | 2 / 2 |
| C Fill type and strength | 4 / 3 | No construction records; fill origin unknown | 4 / 3 | 2 / 3 |
| D Rig access and track time | 4 / 4 | Lidar and imagery show a farm road to the downstream toe; crest by hi-rail only | 2 / 3 | 2 / 2 |
| E Karst: voids or pinnacled rock | 3 / 5 | State geologic map: limestone; sinkhole inventory: three within 0.5 mile | 3 / 5 | 2 / 4 |
| F Report date versus lab turnaround | 4 / 3 | Not a desktop item; settled by a call with the client (Section 3.1.1) | 2 / 3 | 1 / 3 |
| Fee | Base fee estimate for the scoped work: $48,000 | |||
| pC, CC | Item C: probability 0.25 that the fill needs added consolidation testing and analysis costing $6,000 | |||
| pE, CE | Item E: probability 0.20 that a void or pinnacle needs two added borings and the resistivity survey, costing $18,000 | |||
Submit a fixed fee of $48,000 with a $5,100 (about 11%) contingency allowance or an optional karst task, and stated assumptions for access, track time and the report date. As received, the request rated High on five of six items, which calls for more research, not a price. The desktop study, costing a few hours, settled rock depth, access and schedule. It could not settle groundwater, fill strength or karst, and those three items are exactly what the borings, piezometer, rock core and lab program are aimed at. What remains after that scope is Elevated, which a fixed fee can carry when the assumptions are written down.
The ratings also tell the client something. Item E stays Elevated even after the scope: two borings through a karst embankment can miss a void. Saying so in the proposal, with the resistivity survey offered as an option, sets the client’s expectation before the work starts rather than in a change order afterwards.
Start by writing down, in one paragraph, what the client is trying to decide. Requests rarely say this directly. "Schedule the additional borings needed for the steeper side slopes" really means "tell us whether steepening the fill is cheaper than buying the neighbor's land." "Survey, geotech and environmental for a parking expansion" really means "tell us what it will take to build heavy-duty pavement and light towers on this ground." The scope follows from that sentence, not from the list of tasks in the email.
| Question | Why it matters | Where the answer usually comes from |
|---|---|---|
| What is being built or protected, and what loads does it carry? | Sets boring depths, tests and analyses (track, pavement for container handlers, light towers, walls, culverts) | Request email, concept plans, client project manager |
| What decision will the report support? | Keeps the scope aimed at the question, such as slope steepening versus property purchase | Conversation with the client project manager |
| What has already been done at or near the site? | Legacy borings can reduce the program or show where the gaps are | Previous reports, project files, public well and boring databases |
| Are there ground rules? | Some clients fix the number of light towers, ban infiltration tests in high groundwater or cap the budget | Request email |
| What is the budget limit and the schedule? | Determines whether locations are priced together or separately and when field work can happen | Client project manager |
| Is the work sole-sourced or competitive? | Sole-sourced work should carry conservative assumptions rather than a cut scope | Request email |
| Who else is on the team? | Survey, environmental, drainage and structures scopes must not overlap or leave gaps | Internal project manager |
Record the request, the date and who sent it at the top of the proposal file. When the scope changes during development (borings added, depths cut, a location dropped), date each change and say who agreed to it. That history is what lets the team explain the final number and later defend it.
The scope is written by task, in the order the work will be done, so that the cost estimate (Chapter 3.7) can follow it line for line. A typical railroad geotechnical scope has the tasks below; ground hazard assignments add the risk assessment task.
| Task | Content | Notes |
|---|---|---|
| A. Project management | Setup, coordination, client meetings, invoicing, quality control | Usually 8 to 12% of labor hours |
| B. Ground hazard risk management | Desktop study, field assessment, risk rating, alternatives (Chapters 3.2, 3.8 and 3.8) | Only on ground hazard work |
| C. Engineer reconnaissance | Site visit to confirm access, utilities and boring locations (Chapter 3.4) | Travel and on-site time; one trip is normal |
| D. Subsurface field exploration | Utility clearance, mobilization, drilling oversight, logging, demobilization | Driller is a subconsultant; the field engineer is with the rig every day |
| E. Laboratory testing | Index, strength, consolidation, compaction, corrosion tests | In-house or by the drilling subconsultant's laboratory |
| F. Geotechnical engineering | Typed logs, analysis, report or memorandum | Deliverable is set by the client's question (Chapter 8.1) |
| G to M. Other disciplines | Pavement design, survey, hydrology, structures, permitting, bid package, construction quality assurance | Only if requested; coordinate with those teams |
The field program is described in enough detail that a reviewer could price it: number of borings, depth of each, sampling interval, special sampling (Shelby tubes, rock core, bulk samples), field tests (dynamic cone penetrometer, pocket penetrometer, vane), groundwater readings, screening (photo-ionization detector where fill or odors are expected), backfill method and the number of drilling days. Name the borings in the proposal (for example HML-1 to HML-8 and PB-1 to PB-11) so they can be traced into the field and the report.
| Item | Parking and light towers on filled marshland | Steepened siding fill on a hillside |
|---|---|---|
| Borings | 8 light-tower borings to 35 ft; 11 pavement borings to 10 ft (390 ft) | 8 toe borings to 15 ft; 2 ditch borings to 6 ft (132 ft) |
| Sampling | SPT; DCP to 5 ft in pavement borings; 3 bulk samples for Proctor and CBR | Continuous SPT; Shelby tubes in soft clay; NQ core where refusal is shallow (15 ft contingency) |
| Screening and water | PID on every boring; groundwater at drilling and completion | Water at drilling, completion and 24 hours |
| Rig and days | One truck rig; about 7 drilling days | Track or ATV rig with mats; about 2.5 drilling days plus a separate setup |
| Laboratory | Moisture, Atterberg, -200 and hydrometer, organics, UC, consolidation on peat, Proctor and CBR, corrosion suite on slag | Moisture, Atterberg, -200, organics, UC, consolidation, CU triaxial or direct shear, rock UCS |
| Engineering | Drilled-shaft axial and lateral design; pavement subgrade parameters; undercut; settlement over organics | Global stability of 1.5H:1V slopes; shot-rock toe key versus geogrid; quantities by reach |
| Deliverable | Geotechnical report | Memorandum addendum to the earlier report |
Say what will be delivered, in what form and when: a data report (exploration), a geotechnical report with recommendations (investigation), or a memorandum (Chapters 8.1 and 8.3). State whether typed logs, laboratory sheets, analysis output and quantity tables are included. On ground hazard work, say whether the deliverable includes risk ratings and stabilization alternatives with costs.
The assumption list is the part of the proposal the client reads most carefully and the part that protects the scope later. Every item that could change the cost belongs on it. Write each assumption as a plain statement the client can agree or disagree with.
| Topic | Typical assumption | Why it is stated |
|---|---|---|
| Access | Borings are accessible to a truck-mounted rig from public roads or the railroad right-of-way; clearing, matting or a track rig is priced separately where noted | Clearing and mats can exceed the drilling cost on wooded or wet sites (Chapter 3.6) |
| Right-of-entry | The railroad will provide right-of-entry on its property; entry onto other property, if needed, will be arranged by the railroad or priced as additional work | Boring locations often plot outside the property line once surveyed |
| Track protection | Flagging and track protection will be provided by the railroad at no cost to the consultant | Flagging availability drives the schedule |
| Train standby | Standby time for trains is budgeted at an assumed number of hours per day (for example 3.5 hours, from past work on the line) | Standby is often the largest variable cost |
| Utilities | Public utilities will be located through the one-call system; railroad signal and communication lines will be located by the railroad | Borings must be kept a set distance from utilities |
| Boring locations | Locations may be adjusted in the field for access and utilities; ground elevations will be surveyed or taken from lidar | Avoids disputes when borings move |
| Groundwater and cuttings | Cuttings will be spread on site unless screening indicates impacted material, in which case drumming and disposal are additional work | Fill sites with odor or slag may need drummed cuttings |
| Laboratory | Quantities are estimates; the tests performed will be selected after the borings are logged | Lets the engineer target the tests |
| Schedule | Field work can begin within a stated time after notice to proceed, weather and flagging permitting | Sets expectations |
| Exclusions | Environmental sampling, wetland delineation, survey, infiltration testing or design by others are excluded unless listed | Prevents scope creep |
Phase the work so that each phase answers a question before the next is committed. On a site with two parcels the client may authorize one or both, so each is estimated separately. On a ground hazard program the desktop study and risk rating (Chapters 3.2 and 3.8) decide which sites go to field assessment and which go to borings.
| Step | Typical duration | Controlling factor |
|---|---|---|
| Proposal preparation | 1 to 2 weeks (a two-week turnaround is common) | Subconsultant quotes |
| Client approval and notice to proceed | 1 to 4 weeks | Client budget approval |
| One-call locate, flagging request, right-of-entry | 1 to 3 weeks | Flagging availability; property owners |
| Reconnaissance and clearing | 1 to 5 days | Vegetation, wetlands, nesting season |
| Drilling | 1 to 10 days | Number of borings, train traffic, access |
| Laboratory testing | 2 to 4 weeks | Consolidation and triaxial tests |
| Analysis and report | 2 to 4 weeks after laboratory data | Review cycle |
Two calendar constraints come up often on railroad work: flagging crews tend to start their work week on a Tuesday, and clearing near trees should be done outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them) or after a nest check.
Most railroad geotechnical work is estimated as time and materials against the client's rate schedule, with subconsultant costs passed through. The estimate itself is built task by task (Chapter 3.7). When a client sets a budget limit, test the scope against it early: in one recent case the first location fit under the limit and the two locations together did not, so they were priced as separate lines and the client was told which one fit.
Lab testing should be carried once. Where the drilling subconsultant's quote includes laboratory testing, zero the consultant's own laboratory lines so the client is not billed twice.
The proposal also allocates risk. Railroad master service agreements usually govern insurance, safety training and payment, but three items should be checked on every job:
Before the estimate goes out, walk the checklist below. It follows the order of the proposal checklist and the railroad project checklist used in practice.
| Step | Check |
|---|---|
| Read the request | Overview, location and scope written down; ground rules listed |
| Site location and extent | Latitude and longitude, city, county and state; study-area polygon in a KMZ |
| Desktop review | Imagery, soil survey, quadrangle maps (current and historical), geology, well logs, legacy reports (Chapter 3.2) |
| Special conditions | Seismic, expansive or collapsible soils, karst, fill, organics, contamination |
| Boring location plan | Borings named and located; depths, sampling and purpose stated for each |
| Laboratory program | Tests and quantities tied to the analyses |
| Rig and access | Rig type, drilling method, clearing and mats, water source (Chapter 3.6) |
| Contract driller | RFP sent; quote received and checked against the RFP quantities |
| Questions | Open items listed for the client |
| Draft estimate and scope | Labor, subconsultants, travel; assumptions list |
| Final | Totals checked; within any budget limit; quote and estimate agree; files saved to the proposal folder |
| Topic | Refer to |
|---|---|
| Desktop study | Chapter 3.2 |
| Drilling scope and subconsultant RFP | Chapter 3.3 |
| Reconnaissance | Chapter 3.4 |
| Access and clearing | Chapter 3.6 |
| Cost estimate | Chapter 3.7 |
| Risk ratings and risk assessment | Chapter 3.8 |
| Investigation planning | Chapter 3.9 |
| Exploration versus investigation; change orders; memorandums | Chapters 8.1, 8.2 and 8.3 |
The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this chapter, gathered here from across the manual in the November 2026 restructure: 5 tools (0 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).
| Project Management & Checklists | |||
|---|---|---|---|
| PM | Cookbook ChecklistUsed in Chapter 3.9, 3.9.4 Boring Location Planning — Criteria by Project Type | guide only | Guide |
| PM | Project Book Data SheetUsed in Chapter 3.9, 3.9.4 Boring Location Planning — Criteria by Project Type | guide only | Guide |
| PM | Proposal ChecklistUsed in Chapter 3.9, 3.9.1 Background — Why Planning is a Billable Deliverable | guide only | Guide |
| PM | RR Project ChecklistUsed in Chapter 1.1, 1.1.10 Grade & Slope Stabilization Program — Roles and Process | guide only | Guide |
| Pavements, Subgrade & Frost | |||
| PV | Cookbook RailroadUsed in Chapter 2.3, 2.3.1 Background: The Railroad Track Structure | guide only | Guide |