3.2.4 Hazard Databases

Building a preliminary site model from the office before anyone goes to the field: maps, records, history and hazards.
Author: Daniel P. Colwell
3.2.4 Hazard Databases
Table 3.2-5. Hazard screening sources
HazardSourcesNotes
Flooding and scourFEMA flood maps, stream gauges and flood categories, historical high-water marksPair water-sensitive sites with a gauge for the live rating
LandslidesState and USGS landslide inventories, lidar hillshade, previous reportsLook for scarps, hummocky ground and bowed fences
Karst and subsidenceState karst maps, sinkhole inventories, mine maps, InSAR where availablePinnacled rock and voids call for coring and possibly geophysics
SeismicUSGS hazard maps and site class correlationsLiquefaction screening for loose saturated sands (Chapter 6.5)
ContaminationState and federal remediation, landfill, underground tank and RCRA databases; a radius reportSlag fill aquifers can have pH above 12; plan screening and cuttings handling
Protected resourcesWetlands inventory, threatened and endangered species (IPaC), migratory bird windowsAffects clearing dates and access (Chapter 3.6)

For network-scale screening, the Federal Railroad Administration's Composite Hazard Index ranks segments, while gauge-based monitoring and public databases rank individual sites. Chapter 3.8 compares the two and shows how the desktop study feeds the preliminary risk rating.