3.2.3 Historic Imagery and Railroad Records

Building a preliminary site model from the office before anyone goes to the field: maps, records, history and hazards.
Author: Daniel P. Colwell
3.2.3 Historic Imagery and Railroad Records

The history of a site often explains its ground better than the geology map. Build a short timeline from the oldest map forward, and say what each period means for the borings.

Table 3.2-3. Example site timeline: an intermodal facility on former marshland
PeriodWhat happenedWhat it means for the exploration
Late glacialLake plain of a glacial lake; shallow postglacial lake within wetlands; dolomite bedrock at depthLacustrine sand and silt over glacial till; bedrock well below boring depths
1830s to 1880sMarsh used for hunting and fishing; first railroad on the marsh edgeOriginal surface at or near lake level
1880s to 1990sNear-continuous filling with steel slag, cinders, municipal waste, dredge spoil and debrisVariable, unengineered fill; cemented slag may cause auger refusal; screen cuttings
1960sEngineering borings drilled in the area for a planned developmentLegacy data to collect
2010sFacility expansions with borings and reportsProfile already known; target the gaps
PresentGround 5 to 13 ft above the lake; hummocky fill; a 50- to 60-ft mound in one cornerExpect 0.5 to 6 ft of fill; check imagery before scoping the mound
Table 3.2-4. Example site timeline: a siding through folded carbonate terrain
PeriodWhat happenedWhat it means for the exploration
PaleozoicCarbonates and shales thrust along a regional fault system; tectonic breccia in the shear zoneIrregular rock surface; rapid changes from residual clay to breccia
QuaternaryCreek downcutting; karst dissolution (sinkholes, pinnacled rock, clay-filled voids); old landslide massesCore where refusal is shallow; consider geophysics if the rock surface is erratic
1850sRailroad graded by hand and cart; embankment fill probably undocumented, with cindersTreat the existing embankment as uncontrolled fill
1960sInterstate built through the corridor; chronic cut-slope problems in the brecciaExpect weak, sheared rock in cuts
2020sSiding design borings; avoidance redesign with steeper slopesNew borings needed only where the redesign moves onto unexplored ground

Railroad records add what public sources cannot: track charts, slow-order and geometry-defect history, past repairs, valuation maps with utilities and property lines, and earlier reports. Ask for them in the first week; they often take longest to arrive.

Thin soil over weathered rock in a cut beside the track. Historical maps and the geology map told the team to expect shallow rock here, and the boring plan carried rock-coring contingency for it.
Figure 3.2-1. Thin soil over weathered rock in a cut beside the track. Historical maps and the geology map told the team to expect shallow rock here, and the boring plan carried rock-coring contingency for it.