3.2.10 Using NRCS Soil Survey Data in the Desktop Study

Building a preliminary site model from the office before anyone goes to the field: maps, records, history and hazards.
Author: Daniel P. Colwell
3.2.10 Using NRCS Soil Survey Data in the Desktop Study

The NRCS soil survey covers almost all of the United States and is usually the first soil information available for a railroad site. It is an agricultural (pedological) classification of the upper 5 to 6.5 ft of the ground, mapped at about 1:12,000 to 1:24,000, and its engineering tables are estimates for typical soils, not test results. Used with that in mind, it is very good at flagging problem soils along a corridor before any borings are drilled (Arnold and Eswaran 2003; García-Gaines and Frankenstein 2015).

3.2.10.1 How the survey is organized

  • Map units are the areas outlined on the map. Each is named for one or more soil components (usually soil series) and contains inclusions of other soils too small to map separately.
  • Soil Taxonomy classifies soils in six categories: order, suborder, great group, subgroup, family and series. The series is the most detailed. The family name gives particle-size class, mineralogy and soil temperature, all useful to an engineer.
  • Horizons are layers formed by weathering: O (organic), A (topsoil), E (leached), B (subsoil enriched in clay, iron or carbonate), C (little-altered parent material) and R (bedrock). Suffixes add detail: t for clay accumulation, ss for slickensides, g for gleying (wet), k for carbonate, y for gypsum, z for salts, x for fragipan.
  • Engineering data (from SSURGO through Web Soil Survey): USCS and AASHTO classes, liquid limit and plasticity index ranges, linear extensibility (shrink–swell), depth to water table and bedrock, flooding and ponding frequency, frost action, risk of corrosion of steel and concrete, and ratings for uses such as local roads and shallow excavations.

3.2.10.2 Soil orders and what they flag

Table 3.2-11. The 12 Soil Taxonomy orders, their formation and engineering flags (formation after Arnold and Eswaran 2003; engineering flags are screening judgment)
OrderHow it formsEngineering flags for railroad work
GelisolsPermafrost; freeze–thaw churningThaw settlement and frost heave; ice-rich ground
HistosolsOrganic matter accumulates in waterlogged groundPeat and muck: very compressible, weak, long-term settlement (Chapter 2.6)
SpodosolsAcid leaching of iron and aluminum from sandy soil into a cemented subsoilCemented layers that perch water; acidic and often wet: corrosion
AndisolsWeathering of volcanic ashLow density, high water content; strength and plasticity change irreversibly on drying and remolding
OxisolsExtreme tropical weathering to iron and aluminum oxidesDeep residual soils; aggregated clays that classify oddly (Chapter 2.13); mainly Hawaii and Puerto Rico
VertisolsSmectite clay shrinks and swells, forming cracks and slickensidesExpansive clay: track geometry loss, shallow slope failures, structure heave (Chapter 2.5)
AridisolsDry climate; carbonate, gypsum and salt accumulateCollapsible soils (Chapter 2.9), caliche and arid soils (Chapter 2.13), gypsum dissolution (Chapter 2.11), corrosive salts
UltisolsAcid leaching; clay moves into the subsoilResidual soils of the humid Southeast (Chapter 2.13); erodible surface, acidic and corrosive
MollisolsDark, humus-rich topsoil under grasslandOften on loess: collapsible when dry, frost-susceptible silt
AlfisolsClay moves into a base-rich subsoilClayey subsoil under silty topsoil; frost-susceptible silt
InceptisolsWeak developmentVariable; often young soils on slopes and floodplains
EntisolsLittle or no development: recent deposits or eroding slopesFresh alluvium, dune sand, colluvium: loose, soft, liquefiable or erodible

3.2.10.3 USDA texture and USCS are not the same

The USDA texture class uses particle size only: sand is 2 to 0.05 mm, silt 0.05 to 0.002 mm and clay finer than 0.002 mm, with gravel added as a modifier. USCS sets the sand–fines boundary at 0.075 mm (No. 200 sieve) and splits fines by plasticity, not size. So a texture class does not fix a USCS group; it only makes some groups more likely. A consensus mapping from several data sets, thousands of samples in all, is given in Table 3.2-13.

Table 3.2-12. Particle-size limits compared
FractionUSDAUSCS (ASTM D2487)
Gravel> 2 mm (modifier)75 to 4.75 mm
Sand2 to 0.05 mm4.75 to 0.075 mm
Silt0.05 to 0.002 mmFines < 0.075 mm, split into silt and clay by plasticity (A-line)
Clay< 0.002 mm
Table 3.2-13. Most likely USCS group for each USDA texture class (after García-Gaines and Frankenstein 2015), with the spread seen in one 1,196-sample data set
USDA textureMost likely USCSSpread in the 1961 data set
SandSPSM and SP-SM about equally common
Loamy sandSMAlmost all SM
Sandy loamSMSM 40%, ML 20%, SC 13%, SM-SC 9%, CL 8%
Sandy clay loamSCMostly CL (19 of 31), then SC
Sandy claySC or CLToo few samples
LoamCLCL 53%, ML 22%, CL-ML 11%
Silt loamMLCL 45%, ML 36%, CL-ML 10%
SiltMLAll ML
Clay loamCLCL 78%
Silty clay loamCLCL 65%, CH 28%
ClayCH or CLCH 66%
Silty clayCH or CLCH 78%, CL 22%

The spread shows why the mapping is only a starting point: a silt loam is about as likely to be CL as ML, and the report itself recommends laboratory classification for anything that matters.

3.2.10.4 Using the survey along a railroad

  • Screen the corridor for Vertisols and soils with high linear extensibility, Histosols and organic surface horizons, hydric and frequently ponded soils, gypsic and salic horizons, shallow bedrock and fragipans, and soils rated for high frost action.
  • Use the corrosion ratings for buried steel and concrete as a first screen for culverts, piles and signal and communication cable routes, then test (Section 5.2.30). Soil-map-based ratings of shrink–swell and salt corrosion have been used to route buried telecommunication cables away from damaging soils, and the same approach suits railroad cable routes.
  • Know the limits. Data stop at about 5 to 6.5 ft. The existing roadbed and yards are usually mapped as urban land, made land or pits with no data. Values are typical ranges, not site measurements.
  • Record the map unit, component and series in the desktop study so later boring results can be compared and the map can be judged for the rest of the line.

For railroad work: Use the soil survey to decide where to drill and what to test, not to design. A corridor-length table of map units with their order, texture, listed USCS, linear extensibility, depth to water and corrosion ratings takes little time to build from Web Soil Survey and often shows where the problem soils are before the first boring. Flag any length of track where the survey and the track maintenance record agree, for example high shrink–swell soils where surfacing is frequent.

3.2.10.5 Sources

  1. Arnold, R. W. and Eswaran, H. (2003). “Conceptual Basis for Soil Classification: Lessons from the Past.” In Eswaran, H., Rice, T., Ahrens, R. and Stewart, B. A. (eds.), Soil Classification: A Global Desk Reference. Boca Raton, FL: CRC Press, Chapter 4.Find source ↗
  2. Fitzpatrick, R. W., Powell, B., McKenzie, N. J., Maschmedt, D. J., Schoknecht, N. and Jacquier, D. W. (2003). “Demands on Soil Classification in Australia.” In Eswaran, H. et al. (eds.), Soil Classification: A Global Desk Reference. Boca Raton, FL: CRC Press, Chapter 9.Find source ↗
  3. García-Gaines, R. A. and Frankenstein, S. (2015). USCS and the USDA Soil Classification System: Development of a Mapping Scheme. ERDC/CRREL TR-15-4. Hanover, NH: U.S. Army Engineer Research and Development Center, Cold Regions Research and Engineering Laboratory.Find source ↗

Percentages in Table 3.2-13 are calculated from the 1961 Waterways Experiment Station data set reproduced in the report.

Example 3.2-1: Reading a Soil Survey Map Unit for a Siding Extension

Problem Statement

A Class I railroad located in Texas plans to extend a siding across farmland beside the main track. Before borings are scheduled, the desktop study pulls the soil survey map unit that covers most of the new alignment. The engineer must check whether the USCS classes listed in the survey agree with the USDA textures, estimate the shrink–swell potential of the upper 5 ft, and decide what the investigation must look for (Section 3.2.10).

Ap Bt Btss 08 in.36 in.60 in. Given (map unit component, typical horizons) Ap 0–8 in.: silt loam; listed USCS CL-ML; LEP 1.5% Bt 8–36 in.: silty clay loam; listed USCS CL; LEP 4.5% Btss 36–60 in.: clay with slickensides; listed USCS CH; LEP 7.5% (LEP = linear extensibility percent) Required:LE over 60 in.,USCS check,hazard flags
Figure 3.2-3. Example 3.2-1: typical soil profile of the map unit.

Given

VariableValueDescription
Ap, 0–8 in.Silt loam; listed CL-ML; LEP 1.5%Plowed surface horizon
Bt, 8–36 in.Silty clay loam; listed CL; LEP 4.5%Clay-enriched subsoil
Btss, 36–60 in.Clay; listed CH; LEP 7.5%Clay-enriched subsoil with slickensides (“ss”)
ClassesLEP: low < 3%, moderate 3–6%, high 6–9%, very high ≥ 9%NRCS shrink–swell classes

Required

  • (a) Expected USCS class for each horizon from Table 3.2-13, compared with the listed class
  • (b) Linear extensibility LE of the upper 60 in. and the class of each horizon
  • (c) What the borings and laboratory program must check

Equations

  1. Eq. 3.2-1: LE = Σ (LEPi / 100) × ti — sum over horizons of thickness ti (in.)

Steps

Step 1 · (a) USCS check
Silt loam → ML; silty clay loam → CL; clay → CH (Table 3.2-13)
Listed CL-ML, CL, CH: consistent
Spot check: Silt loam spreads between ML and CL (Table 3.2-13); the listed CL-ML sits between them.
↓
Step 2 · (b) LE by horizon
0.015 × 8 = 0.12; 0.045 × 28 = 1.26; 0.075 × 24 = 1.80
LE = 3.18 in. (8.1 cm)
↓
Step 3 · (b) Classes
Ap 1.5% low; Bt 4.5% moderate; Btss 7.5% high
High shrink–swell below 3 ft
Spot check: An LE of 6 cm (2.4 in.) or more within 100 cm (39 in.) is the threshold Soil Taxonomy uses for vertic (shrink–swell) soils; 8.1 cm exceeds it, and the slickensides confirm it.
↓
Step 4 · (c) Investigation
Borings through the Btss into the C horizon; Atterberg limits, swell tests and suction on the clay; sulfate for any lime treatment
Plan for expansive clay under the new subgrade and slopes
↓
Solution
USCS classes consistent; LE ≈ 3.2 in. (8.1 cm), high below 3 ft; treat as expansive clay until tests show otherwise.

Solution

(a) ML, CL and CH expected; the listed CL-ML, CL and CH agree. (b) LE ≈ 3.2 in. (8.1 cm); low, moderate and high by horizon. (c) Investigate and design for expansive clay.

LE is an index of potential volume change between moist and oven-dry, not a prediction of track movement: field moisture changes are smaller and depend on cover, drainage and climate. It is enough to say that the siding subgrade, cut slopes and any shallow culvert or signal foundations are in shrink–swell clay, so the investigation should include swell tests and suction measurements (Chapter 2.5), and the design should consider moisture control, lime treatment after sulfate screening (Section 7.2.7) and the shallow-slide risk on side slopes (Section 7.4.9). The map unit also has inclusions of other soils, so borings, not the map, set the design.