3.2.11 Terrain Analysis and Aerial Photograph Interpretation

Building a preliminary site model from the office before anyone goes to the field: maps, records, history and hazards.
Author: Daniel P. Colwell
3.2.11 Terrain Analysis and Aerial Photograph Interpretation

Terrain analysis is the interpretation of landforms, drainage, tone and vegetation on topographic maps and remotely sensed images to map the geologic conditions of a site before it is drilled. Hunt (2007) calls it often the most important part of a geotechnical investigation: landform reflects how resistant the materials are to erosion, so ridges, valleys, slope shapes and drainage reveal rock type, structure, soil origin, groundwater and hazards such as landslides and sinkholes.

3.2.11.1 Imagery and scales

Table 3.2-14. Imagery for corridor terrain analysis (after Hunt 2007, Table 1.3)
PurposeImageryScale or resolution
Regional geology and major structures (faults, folds)Satellite images; radar where cloud cover is persistentModerate resolution, whole region
General mapping of large areasStereo pairs of aerial photographs1:60,000 to 1:40,000
Detailed mapping of rock, soil, drainage, slides, sinkholesStereo pairs, black and white, true color or color infrared1:20,000 to 1:8,000
Ground moisture, seepage, wet ground at sinkholes and fault tracesColor infrared (CIR) stereo pairs; thermal infraredLarge to local areas
Ground surface under treesLiDAR bare-earth DEM and hillshade (Section 3.2.12)1 to 3 ft grid typical

Hunt recommends interpreting photographs at two scale ranges for any large study: the small scale for the overview and the large scale for detail. Historical photographs are especially valuable on railroads because they show the ground before fills, cuts and vegetation changed it.

3.2.11.2 Elements of interpretation

  • Landform and slope. Hard rocks form ridges and steep slopes; shales, soluble rocks and weathered zones form valleys and gentle slopes. Slides, sinkholes and gullies have characteristic shapes: scarps, hummocky ground, closed depressions.
  • Drainage pattern and stream form. See Table 3.2-15. Streams, lakes and swamps mark the water table.
  • Gullies. Sharp V gullies form in sand and gravel, broad U gullies in silt and loess, gentle saucer shapes in clay.
  • Tone (black and white photographs). White to light gray: free-draining soil above the water table or acid rocks; dull gray: slow-draining soils or basic rocks; dark gray to black: poorly drained or organic soil, water near the surface.
  • Vegetation. Tree lines often follow floodplain limits and fault traces; water-loving plants mark seepage.
  • Land use. Fills, cuts, borrow pits, quarries and mines are the main man-made features to map.
  • Color infrared. Healthy vegetation appears red, stressed vegetation pink to light, wet ground and water dark; useful for seepage lines and wet sinkholes.
Table 3.2-15. Drainage patterns and what they indicate (dendritic, trellis, rectangular and radial after the Physical Geology text and Hunt 2007; parallel, deranged and karst added from general practice)
PatternAppearanceIndicatesRailroad significance
DendriticTree-like, branching in all directionsUniform material: flat-lying sedimentary rock, massive crystalline rock, thick uniform soilFew structural controls; slope problems follow soil and weathering
TrellisLong parallel main streams with short tributaries at right anglesTilted or folded interbedded rocks, parallel faultsCuts across the strike meet alternating hard and soft beds and dip-slope sliding
RectangularStreams turn at right angles; segments of similar lengthJointed or faulted rock with two joint sets at right anglesJoint-controlled wedge and toppling failures in cuts
RadialStreams flow outward from a high pointDomes, volcanic cones, isolated peaksVariable dip around the feature
ParallelClosely spaced parallel streamsSteep uniform slopes, young surfaces, loessErodible ground; gullying of side slopes
DerangedIrregular, with lakes, swamps and unconnected streamsYoung glacial terrainPeat, soft lake deposits, variable till (Chapter 2.6)
Karst (internal)Few surface streams; closed depressions and sinking streamsSoluble rock: limestone, dolomite, gypsumSinkholes under track and structures (Chapter 2.11)

For railroad work: Build a strip map along the line from the topographic map, the hillshade and two scales of stereo photographs, earliest and latest. Mark landforms, drainage patterns, wet ground, old slides, filled ravines, borrow pits and culvert outfalls, and carry the map into the reconnaissance (Chapter 3.5) to check each feature on the ground. A change in drainage pattern along the line usually marks a change in geology, and is a good place for a boring.

3.2.11.3 Worked example

Example 3.2-2: Ordering Stereo Aerial Photographs for a Corridor Study

Problem Statement

A Class I railroad located in Kentucky has had repeated slides along a 12-mile line through shale hills. Before any borings are planned, the engineer wants historical stereo aerial photographs at two scales to map old slide scars, fills and drainage along the line (Section 3.2.11). The engineer must find the ground covered by each frame, the spacing between exposures and the number of photographs to order along a single flight line.

12-mile corridor (63,360 ft)G = frame on ground = ?air base B = ?9 in. × 9 in. frames at 1:20,000, 60% forward overlapNumber of photos N = ? (and at 1:40,000)GivenL = 12 mi = 63,360 ftFormat 9 × 9 in.Scale 1:20,000 (detail)Scale 1:40,000 (overview)Forward overlap 60%Single flight lineRequiredGround coverage G per frameAir base BPhotos N for each scaleBlack = given; red = required
Given and required for Example 3.2-2.

Given

VariableValueDescription
L12 mi = 63,360 ftCorridor length, one flight line
Format9 in. × 9 in.Standard aerial camera frame
S1:20,000 and 1:40,000Detail and overview scales (Hunt: use two scale ranges)
p60%Forward overlap needed for stereo viewing

Required

  • (a) Ground coverage G of one frame at each scale
  • (b) Air base B (distance between exposure centers)
  • (c) Number of photographs N for full stereo coverage

Equations

  1. Eq. 3.2-2: G = d × S — frame side d times the scale denominator
  2. Eq. 3.2-3: B = (1 − p) G
  3. Eq. 3.2-4: N = ⌈L/B⌉ + 1, plus one frame at each end so both ends are seen in stereo

Steps

Step 1 · (a) Coverage at 1:20,000
9 in. × 20,000 = 180,000 in. ÷ 12
G = 15,000 ft (2.8 mi) square
Spot check: 1:20,000 is 1,667 ft per inch; 9 in. × 1,667 = 15,000 ft.
↓
Step 2 · (b) Air base
(1 − 0.60) × 15,000
B = 6,000 ft
↓
Step 3 · (c) Photos at 1:20,000
63,360 / 6,000 = 10.6 → 11 intervals; 11 + 1 = 12; + 2 end frames
N = 14 photographs
↓
Step 4 · Overview at 1:40,000
G = 30,000 ft; B = 12,000 ft; 63,360/12,000 = 5.3 → 6; 6 + 1 + 2
N = 9 photographs
Spot check: Half the scale, twice the coverage and about half as many frames.
↓
Solution
1:20,000: G = 15,000 ft, B = 6,000 ft, 14 photos; 1:40,000: G = 30,000 ft, B = 12,000 ft, 9 photos.

Solution

(a) 15,000 ft at 1:20,000; 30,000 ft at 1:40,000. (b) 6,000 ft and 12,000 ft. (c) About 14 and 9 photographs.

A single flight line at 1:20,000 covers 7,500 ft each side of the track, far more than the corridor, so one line is enough unless the alignment curves sharply. Order the earliest available year as well as a recent one: old slide scars, filled ravines, borrow pits and abandoned alignments are often clearer before vegetation and later work hide them. Check the photos against the LiDAR hillshade (Section 3.2.12) and the slide inventory, then mark the features to visit during reconnaissance.

3.2.11.4 Sources

  1. Hunt, R. E. (2007). Geotechnical Investigation Methods: A Field Guide for Geotechnical Engineers. Boca Raton, FL: CRC Press.
  2. Introduction to Physical Geology (college textbook; Chapter 9, Geologic Time, and Chapter 14, Streams and Lakes; author and edition not shown in the copy reviewed).