This chapter covers how the drilling scope is set from the desktop study and reconnaissance: boring layout, depths, sampling and in situ testing, groundwater observations, laboratory quantities, and the railroad constraints on drilling near track. It ends with the request for proposal (RFP) sent to contract drillers and the contingencies that keep the estimate honest.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Railroad investigation requirements and variability values for setting boring spacing and depth. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Boring spacing along track alignment | Subgrade strength zone: Very high to high | New track or rehabilitation | 500 | ft | LI16 T8.1, p.358 | |||
| Boring spacing along track alignment | Subgrade strength zone: Medium | New track or rehabilitation | 200 | ft | LI16 T8.1, p.358 | |||
| Boring spacing along track alignment | Subgrade strength zone: Low to very low | New track or rehabilitation | 100 | ft | LI16 T8.1, p.358 | |||
| Casing diameter requiring test borings under track | Class I railroad pipeline crossings | Borings each side of track on the crossing centerline | 48 | in | RRPIPE1 T3.1.1, p.11 | |||
| Class I railroad public project investigation | Boring series spacing along line | 1,320 | ft | RRGEO text, p.1 | ||||
| Class I railroad public project investigation | Borings per series | 3 | each | RRGEO text, p.1 | ||||
| Class I railroad public project investigation | Cut-section boring depth below proposed ditch flowline | 5 | ft | RRGEO text, p.1 | ||||
| Bridge boring depth | Below spread footing | 2 | × footing width | RRBRG text, p.1 | ||||
| Bridge boring depth | Below estimated pile tip | From preliminary static analysis | 10 | ft | RRBRG text, p.1 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Vertical scale of fluctuation | Clay – su | Lab testing | 2.6 | 15.4 | 28.2 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Clay – su | Vane shear | 6.6 | 13.4 | 20.3 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Clay – su | Vane shear | 150.9 | 173.9 | 196.9 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Sand, clay – qc | CPT | 0.3 | 5.05 | 9.8 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Sand, clay – qc | CPT | 9.8 | 136.2 | 262.5 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Offshore soils – qc | CPT | 1 | 1.15 | 1.3 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Offshore soils – qc | CPT | 45.9 | 85.3 | 124.7 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Clay – qt | CPTu | 0.7 | 1.15 | 1.6 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Clay – qt | CPTu | 75.5 | 146 | 216.5 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Cohesive-behavior soils – qc1N | CPT | 0.3 | 1.15 | 2 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Intermediate-behavior soils – qc1N | CPT | 1 | 2.15 | 3.3 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Cohesionless-behavior soils – qc1N | CPT | 1.3 | 2.45 | 3.6 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Sand – fs | CPT | 4.3 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Cohesive-behavior soils – Ic | CPT | 0.7 | 1.15 | 1.6 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Intermediate-behavior soils – Ic | CPT | 2 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Cohesionless-behavior soils – Ic | CPT | 1 | 2.45 | 3.9 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Sand – N | SPT | 7.9 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Clay, loam – w | Lab testing | 5.2 | 23.5 | 41.7 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Clay, loam – w | Lab testing | 557.8 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Clay, loam – wL | Lab testing | 5.2 | 16.9 | 28.5 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Clay, loam – γ | Lab testing | 7.9 | 16.9 | 25.9 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Organic silty clay – e | Lab testing | 9.8 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Organic silty clay – σ′p | Lab testing | 2 | ft | FGE T31.6, p.484 | |||
| Horizontal scale of fluctuation | Organic silty clay – σ′p | Lab testing | 590.6 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Sand – ln(Dr) | SPT | 12.1 | ft | FGE T31.6, p.484 | |||
| Horizontal scale of fluctuation | Sand – ln(Dr) | SPT | 219.8 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Sand – n | – | 21.3 | ft | FGE T31.6, p.484 | |||
| Horizontal scale of fluctuation | Sand – n | – | 10.8 | ft | FGE T31.6, p.484 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Minimum pipeline depth | Cased pipe under track – base of rail to top of pipe | 5.5 | ft | RRPIPE1 text, p.6 | ||||
| Minimum pipeline depth | Uncased natural gas under track – base of rail to top of pipe | 10 | ft | RRPIPE1 text, p.6 | ||||
| Minimum pipeline depth | Longitudinal, non-flammable, ≤ 50 ft from track centerline – cover | 4 | ft | RRPIPE1 text, p.6 | ||||
| Minimum pipeline depth | Longitudinal, flammable, ≤ 50 ft from track centerline – cover | 6 | ft | RRPIPE1 text, p.6 | ||||
| Minimum pipeline depth | Flammable pipe not under track – cover below ground or ditch bottom | 3 | ft | RRPIPE1 text, p.6 | ||||
| Minimum pipeline depth | Longitudinal pipeline ≤ 50 ft from track centerline – cover | 4.5 | ft | RRPIPE2 text, p.1 | ||||
| Minimum pipeline depth | Uncased steel natural gas pipe, other locations – cover | 6 | ft | RRPIPE2 text, p.2 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
Every boring needs a stated purpose. If the purpose cannot be written in one line, the boring is either in the wrong place or not needed. Typical purposes on railroad work are: the foundation soils and depth to rock under the toe of a fill that is being steepened; the bearing stratum for a light-tower or signal foundation; the subgrade for heavy-duty pavement; the soft-soil depth for undercut limits; and conditions below a proposed ditch grade.
| Question | Exploration that answers it |
|---|---|
| Will a steepened 1.5H:1V fill be stable? | Borings at the toe of the new slope to rock or below the critical slip surface; Shelby tubes in soft clay for strength; rock core where refusal is shallow |
| What will carry a high-mast light tower? | One boring per tower to below the expected shaft tip (35 ft in one recent program); SPT at 5-ft intervals |
| What subgrade will heavy pavement sit on? | Shallow borings on a grid (10 ft) with dynamic cone penetrometer (DCP) testing to 5 ft; bulk samples for Proctor and CBR |
| How deep is the soft soil to be undercut? | Hand-auger probes between borings |
| What is below a new ditch grade? | Short borings or hand augers to below the proposed invert (6 ft in one recent program) |
| What is the groundwater regime? | Water at drilling, completion and 24 hours; observation wells or piezometers where seepage controls the design |
Lay borings out on the map file from the desktop study (Chapter 3.2), on the features that control design, and away from utilities and property lines. Name them by purpose and number them in one direction along the line (for example west to east) so that field staff, the driller and the report use the same order. Use new prefixes that cannot be confused with legacy borings at the same site.
| Feature | Typical layout | Source |
|---|---|---|
| Embankment or cut slope | Borings at the shoulder or crest and at the toe; 80 to 165 ft apart at critical areas, wider in uniform ground; a railroad's minimum is a three-boring series about every quarter mile | Look, Table 1.8; a Class I railroad's public projects requirements |
| Track subgrade (siding, new main) | One boring every 500 ft in strong soil, 200 ft in medium and 100 ft in weak soil, plus at cuts, fills and culverts; hand-auger or DCP probes between | Li and others (2016) |
| Light towers, signals, bridges | One boring per foundation; at each bridge support | Look, Table 1.8 |
| Pavement and yards | Grid, commonly 300 to 500 ft; denser in heavy-load zones; check grid points against soil map units | Practice |
| Culverts | Under 66 ft: one boring; 66 to 130 ft: one at each end; longer: each end and every 66 ft | Look, Table 1.8 |
Section 3.9.5.3 gives the full criteria, the sources and the planner calculator.
A grid laid on a large wet parcel should be checked against the soil map units before it is priced. On one 123-acre marsh parcel a 500 x 500 ft grid gave 28 borings, 17 in a loamy fill unit and 11 in an undrained clayey unit along the edges; the soft clay unit became the critical case for settlement, and the earlier option of one boring per 50,000 sq ft was dropped as too dense for the question being asked.
| Feature | Minimum depth | Extend if | Source |
|---|---|---|---|
| Embankment toe or slope | Below the deepest credible slip surface; 0.5 to 2 times the slope height below the toe (1.5 H is a common choice), or to rock | Soft or organic soils continue | Das; Look |
| Track subgrade | 10 to 15 ft below proposed grade; to rock in shallow-rock cuts | Soft soils, fat clays or groundwater near the surface | Li and others |
| Pavement | 10 ft below finished grade (DCP to 5 ft) | Organics or soft fill continue below 10 ft | EM 1110-1-1804 |
| Drilled shafts and light towers | Expected tip depth plus at least 10 ft, or 3 shaft diameters, whichever is deeper; poles by height in Look | Weak stratum below the bearing layer | A Class I railroad's bridge requirements; Look |
| Spread footings | About 2 times the footing width below the base, checked by the ASCE stress rule | Compressible layers within the stress zone | A Class I railroad; Das |
| Culverts | 2 to 4 times the span below the invert, and through compressible soils | High fill over soft ground | Look |
| Rock | Core about 10 ft into rock to confirm it is not a boulder | Voids or clay seams in karst | Look |
| Method | Use | Specification notes |
|---|---|---|
| Standard Penetration Test (SPT) | All soils; strength and density correlations | 5-ft intervals as a default; continuous in the upper 10 ft or where conditions change; record hammer type and efficiency |
| Shelby (thin-wall) tubes | Soft to stiff clay and silt; consolidation and strength tests | 3-in. diameter; two per boring where soft clay is found; from an offset boring if needed; sealed and kept upright |
| Rock coring | Rock quality, strength, joints, voids | NQ (about 2 in.) core; RQD and recovery; coring contingency where refusal depth is uncertain |
| Dynamic cone penetrometer (DCP) | Pavement subgrade strength; CBR correlation | To 5 ft beside pavement borings; usually covered by the driller's day rate |
| Pocket penetrometer and torvane | Field strength of cohesive samples | Every cohesive SPT and tube end |
| Bulk samples | Proctor, CBR, resilient modulus | About 50 lb per sample from the subgrade zone |
| Photo-ionization detector (PID) | Screening in fill, slag and odor areas | Every sample in fill; drum cuttings if readings or odors indicate impacted material |
| Hand-auger probes | Soft-soil depth, ditch conditions | Between borings; cheap and fast where access is poor |
Record groundwater at first encounter, at completion and, where it matters, after 24 hours. On soft-ground and slope projects a 24-hour reading is worth the short return trip. Where seepage or pore pressure controls design (slopes, levee-like fills, culverts), add observation wells or vibrating-wire piezometers and leave them in place; on unstable slopes add an inclinometer at the critical section (Chapter 5.3).
| Constraint | What to plan |
|---|---|
| Track protection and flagging | Request flagging through the railroad early; flagging crews often start their week on Tuesday; budget train standby (3.5 hours per day was the average on one line) |
| Fouling zone | No drilling within the fouling distance of track without protection; plan locations off the ballast shoulder where possible |
| Safety training and badging | Railroad contractor safety training and badges for every person on site, including the driller |
| Utilities | Public one-call ticket (by the driller); railroad signal and communication lines located by the railroad; 25-ft clearance from valuation-map utilities |
| Insurance | Driller's insurance to meet the railroad agreement, naming the railroad and the consultant; a rider if the policy excludes work within 50 ft of track |
| Access | Drive on the right-of-way, never on ballast; separate setups for distant reaches (Chapter 3.6) |
| Property | Confirm the right-of-way width at each boring; right-of-entry from neighbors if a boring plots outside it |
| Method | Best for | Limits |
|---|---|---|
| Solid or continuous flight auger (CFA) | Shallow borings above groundwater | Samples disturbed; holes collapse below water |
| Hollow-stem auger (HS) | Most soil borings; SPT and tubes through the stem | Heave in loose saturated sand; refusal on cobbles and cemented slag |
| Mud rotary (RW) | Deep borings below water; loose sands | Water source needed; mud handling |
| Air rotary (RA) | Fractured or honeycombed rock where water is lost | Dust; sample quality |
| Rock coring (NQ) | Rock quality and strength | Water source unless cored with air |
| Dual-wall percussion, ODEX, sonic | Cobbles, boulders, rubble fill | Higher cost; limited availability |
| Rig | Use |
|---|---|
| Truck-mounted | Paved yards, roads, gravel lots, firm shoulders |
| Track-mounted (rubber tracks) | Soft ground, slopes, brush; most railroad toe borings |
| ATV with balloon tires | Wet fields and marsh, light footprint |
| Hi-rail | On-track work inside a track window |
| Portable or tripod | Steep or confined sites; hand-carried |

The RFP turns the scope into something a driller can price. A standard RFP covers the items below; leaving any of them out invites a quote that cannot be compared with the others or a change order later.
| Section | Content |
|---|---|
| Project overview and location | Purpose, site, railroad, map file with proposed borings and access routes |
| Access | Truck or ATV rig; clearing by whom; water tank access; overhead and underground utilities |
| Driller's scope | One-call locate; site reconnaissance with a flagman before drilling, with a call to the engineer before leaving site |
| Drilling and sampling | Boring table (ID, location, depth, method, sampling); SPT interval; tubes; core size; water source or air coring; ability to drill cobbles and boulders |
| Site cleanup and backfill | Grout or cuttings per railroad, local, state and federal requirements; disposal of excess cuttings |
| Samples and laboratory | Packaging and shipping; tests the driller may be asked to run (with standards) and how results are reported |
| Consultant's scope | Utility coordination with the railroad; flagging; field engineer to log and handle samples; landowner coordination |
| Cost tabulation | Locate, reconnaissance, clearing, mobilization, drilling and coring per foot, tubes, backfill, standby per hour (assumed hours), per diem, shipping, laboratory tests, office time |
| Documentation | Insurance certificates; railroad safety training and badges; start date after notice to proceed |
| Terms | Payment terms; insurance minimums and additional insured; rider for work near track |
Estimate the laboratory program from the analyses: index tests on most samples, strength and consolidation where the analyses need them, compaction and CBR for pavement, and corrosion tests on slag and cinder fill or where structures are buried. Lab quantities are estimates; the tests run are chosen after the logs are reviewed.
| Test | Quantity | Purpose |
|---|---|---|
| Moisture content | 55 | All samples |
| Atterberg limits | 7 | Classification, strength correlations |
| Percent finer than No. 200 | 7 | Classification |
| Organic content | 2 | Where organics are found |
| Shelby tube extrusion | 16 | Logging and specimen selection |
| Unconfined compression | 4 | Undrained strength |
| Consolidation | 1 to 2 | Settlement of soft fat clay |
| CU triaxial or direct shear | 2 | Drained strength for slope stability |
| Rock unconfined compression | As cored | Rock strength |
| Item | Typical allowance | Why |
|---|---|---|
| Train standby | Hours per day from past work on the line | Largest variable cost on busy lines |
| Refusal and offsets | Half a day where cemented slag, cobbles or shallow rock are expected | Moves and re-drills |
| Rock coring | 5 ft at selected borings, plus a total contingency | Rock depth uncertain |
| Separate setups | One mobilization per distant reach | Reaches miles apart need a new setup |
| Mats and clearing | From the reconnaissance (Chapter 3.6) | Wet or wooded access |
| Topic | Refer to |
|---|---|
| Desktop study | Chapter 3.2 |
| Reconnaissance | Chapter 3.4 |
| Access and clearing | Chapter 3.6 |
| Cost estimate | Chapter 3.7 |
| Investigation planning and scope | Chapter 3.9 |
| Borings and sampling | Chapter 4.1 |
| In situ testing | Chapter 5.1 |
| Laboratory testing | Chapter 5.2 |
| Construction monitoring and instrumentation | Chapter 5.3 |
Utility crossings are one of the most common reasons for borings on railroad right-of-way, and one of the most common causes of track settlement when the bore is poorly controlled. AREMA Chapter 1, Part 5, sets the depth, casing and length requirements, and railroad pipeline specifications add the boring program: borings on each side of the track on the crossing centerline, sampled continuously to 5 ft below the proposed invert (rock cored), and grouted full depth. A 2020 conference paper on trenchless risks stresses settlement monitoring of the ground, not just the rails, since loaded rails can bridge a void until it collapses.
| Item | Requirement |
|---|---|
| Casing depth | 5 1/2 ft base of rail to top of casing (4 1/2 ft under secondary or industry track); 3 ft below ground or ditch elsewhere |
| Uncased steel carrier (secondary or industry track) | 10 ft below base of rail; 6 ft below ground or ditch elsewhere |
| Casing length, each side, measured from the centerline of the outside track | Greatest of 2 ft beyond toe of slope, 3 ft beyond ditch, 25 ft (sealed ends) or 45 ft (open ends) |
| Steel casing inside diameter | Carrier OD (joints, couplings) + 2 in. under 6 in.; + 4 in. for 6 in. and over |
| Steel casing material | Minimum yield 35,000 psi; wall per Table 1-5-1 (thicker if uncoated and unprotected) |
| Bored hole | About the pipe OD; more than about 1 in. oversize calls for remedial measures (grouting) |
| Cover from base of tie (ft) | 2 | 5 | 8 | 10 | 12 | 15 | 20 | 30 |
|---|---|---|---|---|---|---|---|---|
| Live load (psf) | 3,800 | 2,400 | 1,600 | 1,100 | 800 | 600 | 300 | 100 |
Over 30 ft of cover, use dead load only.
| Item | Result |
|---|---|
| Depth, base of rail to top of casing | 6.50 ft |
| E80 live load at 5.85 ft of cover | 2,173 psf |
| Total vertical pressure (with 120 pcf soil) | 2,953 psf |
| Casing wall, coated | 0.406 in. |
| Casing inside diameter for a 24 in. carrier | 29.19 in. |
| Casing length (sealed, tracks 14 ft apart) | 64 ft |
| Bore overcut on diameter | 1.00 in. |
| Boring depth (invert + 5 ft) | 14.0 ft |
The 31 in. bore is at the limit of the AREMA overcut; the annulus should be grouted as the casing advances, and settlement points should be set on the ground at the track before boring starts.
Open the pipeline crossing calculator →
Depth checks, E80 live load at the pipe, minimum casing wall, casing size and length, bore overcut and boring depth.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.