Chapter 3.3 — Drilling Scope

Deciding where, how deep and how many borings and tests a site needs, and writing it so a driller can price it.
Author: Daniel P. Colwell

This chapter covers how the drilling scope is set from the desktop study and reconnaissance: boring layout, depths, sampling and in situ testing, groundwater observations, laboratory quantities, and the railroad constraints on drilling near track. It ends with the request for proposal (RFP) sent to contract drillers and the contingencies that keep the estimate honest.

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Railroad investigation requirements and variability values for setting boring spacing and depth. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Railroad investigation requirements (Class I railroads, track spacing) (9 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Boring spacing along track alignmentSubgrade strength zone: Very high to highNew track or rehabilitation500ftLI16 T8.1, p.358
Boring spacing along track alignmentSubgrade strength zone: MediumNew track or rehabilitation200ftLI16 T8.1, p.358
Boring spacing along track alignmentSubgrade strength zone: Low to very lowNew track or rehabilitation100ftLI16 T8.1, p.358
Casing diameter requiring test borings under trackClass I railroad pipeline crossingsBorings each side of track on the crossing centerline48inRRPIPE1 T3.1.1, p.11
Class I railroad public project investigationBoring series spacing along line1,320ftRRGEO text, p.1
Class I railroad public project investigationBorings per series3eachRRGEO text, p.1
Class I railroad public project investigationCut-section boring depth below proposed ditch flowline5ftRRGEO text, p.1
Bridge boring depthBelow spread footing2× footing widthRRBRG text, p.1
Bridge boring depthBelow estimated pile tipFrom preliminary static analysis10ftRRBRG text, p.1
Open this set in the database ↗
Scale of fluctuation (sets boring and test spacing) (28 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Vertical scale of fluctuationClay – suLab testing2.615.428.2ftFGE T31.6, p.484
Vertical scale of fluctuationClay – suVane shear6.613.420.3ftFGE T31.6, p.484
Horizontal scale of fluctuationClay – suVane shear150.9173.9196.9ftFGE T31.6, p.484
Vertical scale of fluctuationSand, clay – qcCPT0.35.059.8ftFGE T31.6, p.484
Horizontal scale of fluctuationSand, clay – qcCPT9.8136.2262.5ftFGE T31.6, p.484
Vertical scale of fluctuationOffshore soils – qcCPT11.151.3ftFGE T31.6, p.484
Horizontal scale of fluctuationOffshore soils – qcCPT45.985.3124.7ftFGE T31.6, p.484
Vertical scale of fluctuationClay – qtCPTu0.71.151.6ftFGE T31.6, p.484
Horizontal scale of fluctuationClay – qtCPTu75.5146216.5ftFGE T31.6, p.484
Vertical scale of fluctuationCohesive-behavior soils – qc1NCPT0.31.152ftFGE T31.6, p.484
Vertical scale of fluctuationIntermediate-behavior soils – qc1NCPT12.153.3ftFGE T31.6, p.484
Vertical scale of fluctuationCohesionless-behavior soils – qc1NCPT1.32.453.6ftFGE T31.6, p.484
Vertical scale of fluctuationSand – fsCPT4.3ftFGE T31.6, p.484
Vertical scale of fluctuationCohesive-behavior soils – IcCPT0.71.151.6ftFGE T31.6, p.484
Vertical scale of fluctuationIntermediate-behavior soils – IcCPT2ftFGE T31.6, p.484
Vertical scale of fluctuationCohesionless-behavior soils – IcCPT12.453.9ftFGE T31.6, p.484
Vertical scale of fluctuationSand – NSPT7.9ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – wLab testing5.223.541.7ftFGE T31.6, p.484
Horizontal scale of fluctuationClay, loam – wLab testing557.8ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – wLLab testing5.216.928.5ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – γLab testing7.916.925.9ftFGE T31.6, p.484
Vertical scale of fluctuationOrganic silty clay – eLab testing9.8ftFGE T31.6, p.484
Vertical scale of fluctuationOrganic silty clay – σ′pLab testing2ftFGE T31.6, p.484
Horizontal scale of fluctuationOrganic silty clay – σ′pLab testing590.6ftFGE T31.6, p.484
Vertical scale of fluctuationSand – ln(Dr)SPT12.1ftFGE T31.6, p.484
Horizontal scale of fluctuationSand – ln(Dr)SPT219.8ftFGE T31.6, p.484
Vertical scale of fluctuationSand – n–21.3ftFGE T31.6, p.484
Horizontal scale of fluctuationSand – n–10.8ftFGE T31.6, p.484
Open this set in the database ↗
Pipeline crossings: minimum depths (7 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Minimum pipeline depthCased pipe under track – base of rail to top of pipe5.5ftRRPIPE1 text, p.6
Minimum pipeline depthUncased natural gas under track – base of rail to top of pipe10ftRRPIPE1 text, p.6
Minimum pipeline depthLongitudinal, non-flammable, ≤ 50 ft from track centerline – cover4ftRRPIPE1 text, p.6
Minimum pipeline depthLongitudinal, flammable, ≤ 50 ft from track centerline – cover6ftRRPIPE1 text, p.6
Minimum pipeline depthFlammable pipe not under track – cover below ground or ditch bottom3ftRRPIPE1 text, p.6
Minimum pipeline depthLongitudinal pipeline ≤ 50 ft from track centerline – cover4.5ftRRPIPE2 text, p.1
Minimum pipeline depthUncased steel natural gas pipe, other locations – cover6ftRRPIPE2 text, p.2
Open this set in the database ↗
References (6)
  1. RRBRG – Ruel, M. (2003). General Requirements for Geotechnical Investigations for Bridge Construction Projects (a Class I railroad).
  2. RRPIPE2 – A Class I railroad. Pipeline Crossing and Longitudinal Occupancy Specifications (form US-0510).
  3. RRPIPE1 – A Class I railroad (2018). Specifications for the Design and Construction of Pipeline Occupancies (revised June 5, 2018).
  4. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
  5. LI16 – Li, D., Hyslip, J., Sussmann, T. & Chrismer, S. (2016). Railway Geotechnics. CRC Press / Taylor & Francis.
  6. RRGEO – A Class I railroad. Public Projects – Geotechnical Requirements.

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
3.3.0 Objectives of the Exploration

Every boring needs a stated purpose. If the purpose cannot be written in one line, the boring is either in the wrong place or not needed. Typical purposes on railroad work are: the foundation soils and depth to rock under the toe of a fill that is being steepened; the bearing stratum for a light-tower or signal foundation; the subgrade for heavy-duty pavement; the soft-soil depth for undercut limits; and conditions below a proposed ditch grade.

Table 3.3-1. Matching the exploration to the question
QuestionExploration that answers it
Will a steepened 1.5H:1V fill be stable?Borings at the toe of the new slope to rock or below the critical slip surface; Shelby tubes in soft clay for strength; rock core where refusal is shallow
What will carry a high-mast light tower?One boring per tower to below the expected shaft tip (35 ft in one recent program); SPT at 5-ft intervals
What subgrade will heavy pavement sit on?Shallow borings on a grid (10 ft) with dynamic cone penetrometer (DCP) testing to 5 ft; bulk samples for Proctor and CBR
How deep is the soft soil to be undercut?Hand-auger probes between borings
What is below a new ditch grade?Short borings or hand augers to below the proposed invert (6 ft in one recent program)
What is the groundwater regime?Water at drilling, completion and 24 hours; observation wells or piezometers where seepage controls the design
The parts of a geotechnical investigation. The drilling scope is the field portion, but it is written backward from the analyses the report must support.
Figure 3.3-1. The parts of a geotechnical investigation. The drilling scope is the field portion, but it is written backward from the analyses the report must support.
3.3.1 Boring Layout and Spacing

Lay borings out on the map file from the desktop study (Chapter 3.2), on the features that control design, and away from utilities and property lines. Name them by purpose and number them in one direction along the line (for example west to east) so that field staff, the driller and the report use the same order. Use new prefixes that cannot be confused with legacy borings at the same site.

Table 3.3-2. Typical layouts for railroad sites
FeatureTypical layoutSource
Embankment or cut slopeBorings at the shoulder or crest and at the toe; 80 to 165 ft apart at critical areas, wider in uniform ground; a railroad's minimum is a three-boring series about every quarter mileLook, Table 1.8; a Class I railroad's public projects requirements
Track subgrade (siding, new main)One boring every 500 ft in strong soil, 200 ft in medium and 100 ft in weak soil, plus at cuts, fills and culverts; hand-auger or DCP probes betweenLi and others (2016)
Light towers, signals, bridgesOne boring per foundation; at each bridge supportLook, Table 1.8
Pavement and yardsGrid, commonly 300 to 500 ft; denser in heavy-load zones; check grid points against soil map unitsPractice
CulvertsUnder 66 ft: one boring; 66 to 130 ft: one at each end; longer: each end and every 66 ftLook, Table 1.8

Section 3.9.5.3 gives the full criteria, the sources and the planner calculator.

A grid laid on a large wet parcel should be checked against the soil map units before it is priced. On one 123-acre marsh parcel a 500 x 500 ft grid gave 28 borings, 17 in a loamy fill unit and 11 in an undrained clayey unit along the edges; the soft clay unit became the critical case for settlement, and the earlier option of one boring per 50,000 sq ft was dropped as too dense for the question being asked.

Clearance from utilities. Keep borings at least 25 ft from utilities shown on the railroad valuation maps unless the utility owner agrees otherwise, and re-plot the plan after the maps arrive. In practice this moves several borings on almost every yard project.
3.3.2 Boring Depth Criteria
Table 3.3-3. Boring depth criteria
FeatureMinimum depthExtend ifSource
Embankment toe or slopeBelow the deepest credible slip surface; 0.5 to 2 times the slope height below the toe (1.5 H is a common choice), or to rockSoft or organic soils continueDas; Look
Track subgrade10 to 15 ft below proposed grade; to rock in shallow-rock cutsSoft soils, fat clays or groundwater near the surfaceLi and others
Pavement10 ft below finished grade (DCP to 5 ft)Organics or soft fill continue below 10 ftEM 1110-1-1804
Drilled shafts and light towersExpected tip depth plus at least 10 ft, or 3 shaft diameters, whichever is deeper; poles by height in LookWeak stratum below the bearing layerA Class I railroad's bridge requirements; Look
Spread footingsAbout 2 times the footing width below the base, checked by the ASCE stress ruleCompressible layers within the stress zoneA Class I railroad; Das
Culverts2 to 4 times the span below the invert, and through compressible soilsHigh fill over soft groundLook
RockCore about 10 ft into rock to confirm it is not a boulderVoids or clay seams in karstLook
trial slip surfaceShoulderthrough fill and soft soilsUpslope toe1.5 H below toe or to rockDownslope toe1.5 H below toe or to rockH = slope heightbelow the deepest credible slip surfaceFoundation soil
Figure 3.3-2. Boring locations and depths on a railroad embankment. The shoulder boring is taken through the fill and any soft soils below it; the toe borings extend at least 1.5 times the slope height below the toe, or to rock, so that they reach below the deepest credible slip surface.
Light-tower borings (8 x 35 ft)280 ftPavement borings (11 x 10 ft)110 ftSlope-toe borings (8 x 15 ft)120 ftDitch borings (2 x 6 ft)12 ftRock core contingency15 ftDrilled footage by boring type, two recent programs
Figure 3.3-3. Footage by boring type in two recent railroad programs (390 ft and 147 ft). Foundation borings dominate the footage even when shallow subgrade borings dominate the count.
3.3.3 Sampling and In Situ Testing
Table 3.3-4. Sampling and field tests
MethodUseSpecification notes
Standard Penetration Test (SPT)All soils; strength and density correlations5-ft intervals as a default; continuous in the upper 10 ft or where conditions change; record hammer type and efficiency
Shelby (thin-wall) tubesSoft to stiff clay and silt; consolidation and strength tests3-in. diameter; two per boring where soft clay is found; from an offset boring if needed; sealed and kept upright
Rock coringRock quality, strength, joints, voidsNQ (about 2 in.) core; RQD and recovery; coring contingency where refusal depth is uncertain
Dynamic cone penetrometer (DCP)Pavement subgrade strength; CBR correlationTo 5 ft beside pavement borings; usually covered by the driller's day rate
Pocket penetrometer and torvaneField strength of cohesive samplesEvery cohesive SPT and tube end
Bulk samplesProctor, CBR, resilient modulusAbout 50 lb per sample from the subgrade zone
Photo-ionization detector (PID)Screening in fill, slag and odor areasEvery sample in fill; drum cuttings if readings or odors indicate impacted material
Hand-auger probesSoft-soil depth, ditch conditionsBetween borings; cheap and fast where access is poor
Borehole drilling and sampling. The sampling plan is part of the drilling scope and must be written into the RFP so the driller brings the right tools.
Figure 3.3-4. Borehole drilling and sampling. The sampling plan is part of the drilling scope and must be written into the RFP so the driller brings the right tools.
3.3.4 Groundwater Observation and Instrumentation

Record groundwater at first encounter, at completion and, where it matters, after 24 hours. On soft-ground and slope projects a 24-hour reading is worth the short return trip. Where seepage or pore pressure controls design (slopes, levee-like fills, culverts), add observation wells or vibrating-wire piezometers and leave them in place; on unstable slopes add an inclinometer at the critical section (Chapter 5.3).

Grout every boring. Backfill borings full depth with cement-bentonite grout near track, in fills over soft ground and wherever groundwater may be impacted. Cuttings alone can leave a soft column or a vertical drain under the track.
3.3.5 Railroad Constraints
Table 3.3-5. Railroad-specific constraints on drilling
ConstraintWhat to plan
Track protection and flaggingRequest flagging through the railroad early; flagging crews often start their week on Tuesday; budget train standby (3.5 hours per day was the average on one line)
Fouling zoneNo drilling within the fouling distance of track without protection; plan locations off the ballast shoulder where possible
Safety training and badgingRailroad contractor safety training and badges for every person on site, including the driller
UtilitiesPublic one-call ticket (by the driller); railroad signal and communication lines located by the railroad; 25-ft clearance from valuation-map utilities
InsuranceDriller's insurance to meet the railroad agreement, naming the railroad and the consultant; a rider if the policy excludes work within 50 ft of track
AccessDrive on the right-of-way, never on ballast; separate setups for distant reaches (Chapter 3.6)
PropertyConfirm the right-of-way width at each boring; right-of-entry from neighbors if a boring plots outside it
3.3.6 Drilling Methods and Equipment
Table 3.3-6. Drilling methods
MethodBest forLimits
Solid or continuous flight auger (CFA)Shallow borings above groundwaterSamples disturbed; holes collapse below water
Hollow-stem auger (HS)Most soil borings; SPT and tubes through the stemHeave in loose saturated sand; refusal on cobbles and cemented slag
Mud rotary (RW)Deep borings below water; loose sandsWater source needed; mud handling
Air rotary (RA)Fractured or honeycombed rock where water is lostDust; sample quality
Rock coring (NQ)Rock quality and strengthWater source unless cored with air
Dual-wall percussion, ODEX, sonicCobbles, boulders, rubble fillHigher cost; limited availability
Table 3.3-7. Rig types and access
RigUse
Truck-mountedPaved yards, roads, gravel lots, firm shoulders
Track-mounted (rubber tracks)Soft ground, slopes, brush; most railroad toe borings
ATV with balloon tiresWet fields and marsh, light footprint
Hi-railOn-track work inside a track window
Portable or tripodSteep or confined sites; hand-carried
Common drilling methods. The method is chosen for the ground, the water and the access, and stated in the RFP.
Figure 3.3-5. Common drilling methods. The method is chosen for the ground, the water and the access, and stated in the RFP.
3.3.7 The Request for Proposal to Contract Drillers

The RFP turns the scope into something a driller can price. A standard RFP covers the items below; leaving any of them out invites a quote that cannot be compared with the others or a change order later.

Table 3.3-8. Contents of a contract drilling RFP
SectionContent
Project overview and locationPurpose, site, railroad, map file with proposed borings and access routes
AccessTruck or ATV rig; clearing by whom; water tank access; overhead and underground utilities
Driller's scopeOne-call locate; site reconnaissance with a flagman before drilling, with a call to the engineer before leaving site
Drilling and samplingBoring table (ID, location, depth, method, sampling); SPT interval; tubes; core size; water source or air coring; ability to drill cobbles and boulders
Site cleanup and backfillGrout or cuttings per railroad, local, state and federal requirements; disposal of excess cuttings
Samples and laboratoryPackaging and shipping; tests the driller may be asked to run (with standards) and how results are reported
Consultant's scopeUtility coordination with the railroad; flagging; field engineer to log and handle samples; landowner coordination
Cost tabulationLocate, reconnaissance, clearing, mobilization, drilling and coring per foot, tubes, backfill, standby per hour (assumed hours), per diem, shipping, laboratory tests, office time
DocumentationInsurance certificates; railroad safety training and badges; start date after notice to proceed
TermsPayment terms; insurance minimums and additional insured; rider for work near track
Revise the RFP, do not re-send it informally. When borings are added or depths change, issue a numbered revision with a short list of changes and the new totals (for example, Revision 2: 10 borings, 132 ft, 15 ft coring contingency, up to 16 Shelby tubes).
3.3.8 Laboratory Program, Quantities and Contingencies

Estimate the laboratory program from the analyses: index tests on most samples, strength and consolidation where the analyses need them, compaction and CBR for pavement, and corrosion tests on slag and cinder fill or where structures are buried. Lab quantities are estimates; the tests run are chosen after the logs are reviewed.

Table 3.3-9. Example laboratory quantities for a 10-boring slope program
TestQuantityPurpose
Moisture content55All samples
Atterberg limits7Classification, strength correlations
Percent finer than No. 2007Classification
Organic content2Where organics are found
Shelby tube extrusion16Logging and specimen selection
Unconfined compression4Undrained strength
Consolidation1 to 2Settlement of soft fat clay
CU triaxial or direct shear2Drained strength for slope stability
Rock unconfined compressionAs coredRock strength
Table 3.3-10. Contingencies to carry
ItemTypical allowanceWhy
Train standbyHours per day from past work on the lineLargest variable cost on busy lines
Refusal and offsetsHalf a day where cemented slag, cobbles or shallow rock are expectedMoves and re-drills
Rock coring5 ft at selected borings, plus a total contingencyRock depth uncertain
Separate setupsOne mobilization per distant reachReaches miles apart need a new setup
Mats and clearingFrom the reconnaissance (Chapter 3.6)Wet or wooded access
3.3.9 Cross-References
Table 3.3-11. Related chapters
TopicRefer to
Desktop studyChapter 3.2
ReconnaissanceChapter 3.4
Access and clearingChapter 3.6
Cost estimateChapter 3.7
Investigation planning and scopeChapter 3.9
Borings and samplingChapter 4.1
In situ testingChapter 5.1
Laboratory testingChapter 5.2
Construction monitoring and instrumentationChapter 5.3
3.3.10 Pipeline and Casing Crossings Under Track

Utility crossings are one of the most common reasons for borings on railroad right-of-way, and one of the most common causes of track settlement when the bore is poorly controlled. AREMA Chapter 1, Part 5, sets the depth, casing and length requirements, and railroad pipeline specifications add the boring program: borings on each side of the track on the crossing centerline, sampled continuously to 5 ft below the proposed invert (rock cored), and grouted full depth. A 2020 conference paper on trenchless risks stresses settlement monitoring of the ground, not just the rails, since loaded rails can bridge a void until it collapses.

3.3.10.1 Requirements

Table 3.3-12. AREMA pipeline crossing requirements (Chapter 1, Part 5)
ItemRequirement
Casing depth5 1/2 ft base of rail to top of casing (4 1/2 ft under secondary or industry track); 3 ft below ground or ditch elsewhere
Uncased steel carrier (secondary or industry track)10 ft below base of rail; 6 ft below ground or ditch elsewhere
Casing length, each side, measured from the centerline of the outside trackGreatest of 2 ft beyond toe of slope, 3 ft beyond ditch, 25 ft (sealed ends) or 45 ft (open ends)
Steel casing inside diameterCarrier OD (joints, couplings) + 2 in. under 6 in.; + 4 in. for 6 in. and over
Steel casing materialMinimum yield 35,000 psi; wall per Table 1-5-1 (thicker if uncoated and unprotected)
Bored holeAbout the pipe OD; more than about 1 in. oversize calls for remedial measures (grouting)
Table 3.3-13. Cooper E80 live load including 50% impact (AREMA Table 1-4-24)
Cover from base of tie (ft)2581012152030
Live load (psf)3,8002,4001,6001,100800600300100

Over 30 ft of cover, use dead load only.

3.3.10.2 Worked example: 30 in. casing under two main tracks

Table 3.3-14. Calculator output
ItemResult
Depth, base of rail to top of casing6.50 ft
E80 live load at 5.85 ft of cover2,173 psf
Total vertical pressure (with 120 pcf soil)2,953 psf
Casing wall, coated0.406 in.
Casing inside diameter for a 24 in. carrier29.19 in.
Casing length (sealed, tracks 14 ft apart)64 ft
Bore overcut on diameter1.00 in.
Boring depth (invert + 5 ft)14.0 ft

The 31 in. bore is at the limit of the AREMA overcut; the annulus should be grouted as the casing advances, and settlement points should be set on the ground at the track before boring starts.

Open the pipeline crossing calculator →
Depth checks, E80 live load at the pipe, minimum casing wall, casing size and length, bore overcut and boring depth.

3.3.10.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • AREMA Manual for Railway Engineering, Chapter 1 Roadway and Ballast (2012, Volume 1), Part 5 Utilities (Table 1-5-1, depth, length and casing requirements) and Part 4 Culverts (Tables 1-4-24 and 1-4-53).Official page ↗
  • A Class I railroad's pipeline occupancy specification (2018), Carriers folder: soil investigation, boring and sampling requirements.Find source ↗
  • A regional railroad holding company's utility specifications, Carriers folder.Find source ↗
  • AREMA conference papers: controlling risks of trenchless pipe construction beneath railways (2020); pipe ramming and the US rail system (2014).Find source ↗