A proposal does several jobs at once. To the client it is an offer: a scope, a deliverable, a schedule and a fee. To the firm it is a decision about whether that fee can deliver those services to the standard of care. To the project team it is the plan of the work, and the first engineering product on the job, because it fixes what will be explored, tested and analyzed and therefore what the final report can and cannot say. Once signed, it is the contract baseline: its assumptions define what the fee covers and what counts as a change. Table 3.1-1 lists these purposes.
| Purpose | Audience | What it has to do |
|---|---|---|
| Offer of services | Client | State the scope, deliverable, schedule and fee clearly enough to be accepted and priced competitively |
| Internal risk assessment | The firm | Decide whether the fee and schedule can deliver the requested services to the standard of care, given what is not known about the site |
| Plan of the work | Project team | Fix what will be explored, tested and analyzed, and therefore what the final report can and cannot say |
| Contract baseline | Both parties | Record the assumptions and exclusions the fee rests on, so that a change in conditions is recognized as a change (Chapter 8.2) |
| Statement of known risk | Client | Tell the client, before work starts, which ground and site questions will remain open after the proposed work |
Two pressures meet in every proposal. The first is uncertainty: the ground has not been explored, the records may be thin, and access, track time and the client’s real question may not be clear from the request. The second is price: most work is won on a competitive fee, or negotiated against a budget the client already has in mind. A thin scope saves money at the proposal stage and costs it back later in change orders, return trips and hedged recommendations. A padded scope loses the work. Under a fixed fee, whatever the proposal fails to anticipate is paid for by the firm.
For that reason an internal risk assessment is made on every proposal, including a sole-sourced estimate requested by email. It is not shown to the client. It compares two things: what the client expects (the decision to be supported, the deliverable, the schedule, the budget and how firm an answer is wanted) and the level of effort needed to deliver it. Where the two do not line up, the gap is the proposal’s risk. Table 3.1-2 lists the usual places a mismatch appears.
| Item | Client expectation | Level of effort it requires | Sign of a mismatch |
|---|---|---|---|
| Decision to be supported | Replace, repair or monitor; design-level or screening | Exploration depth and analysis matched to that decision | A design-level answer requested on a screening budget |
| Deliverable | Letter, data report, full recommendations report, design input | Engineering and review hours (Chapter 3.7) | “Brief letter” that must carry design parameters |
| Schedule | Report date, often tied to a work window | Track time, drilling availability, lab turnaround | Report due before lab results can exist |
| Budget | Stated or implied ceiling | Sum of tasks at realistic production rates | Fee forced down by removing borings rather than tasks |
| Site access | Assumed easy | Hi-rail or track-mounted rig, flagging, right-of-entry, clearing (Chapter 3.6) | No access route visible in imagery |
| Certainty of the answer | A firm recommendation | Enough data to support it without hedging | Variable ground with one boring proposed |
The risk rating theory of Chapter 3.8 applies directly. Each uncertainty is rated on the same 1-to-5 scales and scored with the same equation, R = F × S. Here F is the likelihood that the conditions or the effort will differ materially from what the fee assumes, and S is the consequence to the firm and the client if they do (Table 3.1-3). The scores fall into the five levels of Table 3.8-72, and each level calls for a particular proposal response (Table 3.1-4). As in the risk ratings, the worst item governs.
| Rating | F: likelihood that conditions or effort differ materially from what the fee assumes | S: consequence if they do |
|---|---|---|
| 1 | Rare: recent borings at the site; simple, documented geology; access confirmed | Negligible: absorbed in normal margin (less than about 2% of fee) |
| 2 | Unlikely: good nearby data and simple geology; access route visible | Minor: 2–5% of fee or a few days of schedule |
| 3 | Possible: regional data only; moderate variability expected | Moderate: 5–15% of fee; schedule slip; a change order needed |
| 4 | Likely: little or no data; variable or problem geology; access unknown | Major: 15–30% of fee; remobilization; recommendations must be qualified |
| 5 | Almost certain: no data and known difficult conditions | Severe: more than 30% of fee; standard of care cannot be met as scoped; safety, liability or relationship at stake |
| Level | R = F × S | Proposal response |
|---|---|---|
| 1 Low | 1–2 | Price as scoped; standard assumptions |
| 2 Guarded | 3–5 | Price as scoped; name the item in the assumptions |
| 3 Elevated | 6–10 | Scope it, or carry it with a stated assumption, an optional task or a contingency allowance |
| 4 High | 12–16 | Do more desktop work before pricing; then scope it directly, phase the work, or price it on unit rates |
| 5 Severe | 20–25 | Do not price as a fixed fee. Propose a Phase 1 study only, time and materials, or decline |
The first rating is made from the request alone, and it is usually High, because almost nothing is known. Pricing at that point means either padding every task or gambling on the ground. The next step is a desktop study (Chapter 3.2) sized to the proposal: geology and soil maps, legacy borings, as-built plans, imagery and lidar, hazard databases and the railroad’s own history of the site. It costs hours, not days, and it settles what public and railroad records can settle.
The items are then rated again. Whatever the desktop study could not settle is the residual uncertainty, and the residual uncertainty is the scope of work. Each boring, sample, test and analysis in the proposal should answer one of the residual items, and each residual item should be answered by something in the scope or carried by a stated assumption, optional task or contingency. Fieldwork is not proposed for what the desk work already answered. Figure 3.1-1 shows the sequence.
Most railroad requests arrive as a short email from the client’s project manager rather than a formal request for proposal. Many are sole-sourced and ask for a cost estimate with a bullet list of assumptions, not a full proposal document. The process is the same for both; only the amount written out for the client differs. The internal ratings are kept in the project file either way.
| Stage | Output | Typical lead | Where |
|---|---|---|---|
| Read the request | One-paragraph statement of the problem, the decision the work supports and the client’s expectations | Project manager | Section 3.1.1 |
| First risk rating | List of uncertainty items, each rated F and S | Project manager with geotechnical lead | This section; Section 3.8.22 |
| Desktop study | Site map (KMZ), legacy boring and well logs, soil and geology summary, imagery, access, site history | Project or design engineer | Chapter 3.2 |
| Re-rate | Residual uncertainty list with revised F and S | Geotechnical lead | Section 3.2.6 |
| Scope the residual | Boring plan, depths and sampling, lab program, analyses, deliverable | Project manager with geotechnical lead | Section 3.1.2; Chapter 3.3 |
| Quotes and estimate | Drilling and laboratory quotes; task-by-task hours, track time, travel | Project manager | Section 3.1.5; Chapter 3.7 |
| Decide and send | Assumptions and exclusions, contingency, go or no-go; estimate or proposal to the client | Project manager | Section 3.1.3, 3.1.6, 3.1.7 |
A Class I railroad located in Middle Tennessee asks, by email, for a fixed-fee proposal for a geotechnical exploration and recommendations to replace a 60-inch corrugated metal pipe culvert under a 25-ft main-line embankment. The report is wanted in four weeks; no budget is stated. Before any research, the proposal team lists six things it does not know and rates each with the scales in Table 3.1-3. It rates them again after the desktop study and again after drafting the scope.
| Item | F / S on receipt | Desktop finding | F / S after desk | F / S after scope |
|---|---|---|---|---|
| A Depth to rock under the culvert | 4 / 4 | Bridge plans 400 ft away show limestone at 18–22 ft | 2 / 4 | 1 / 4 |
| B Groundwater and seepage through the fill | 3 / 3 | Imagery shows ponding upstream in wet seasons; no records | 3 / 3 | 2 / 2 |
| C Fill type and strength | 4 / 3 | No construction records; fill origin unknown | 4 / 3 | 2 / 3 |
| D Rig access and track time | 4 / 4 | Lidar and imagery show a farm road to the downstream toe; crest by hi-rail only | 2 / 3 | 2 / 2 |
| E Karst: voids or pinnacled rock | 3 / 5 | State geologic map: limestone; sinkhole inventory: three within 0.5 mile | 3 / 5 | 2 / 4 |
| F Report date versus lab turnaround | 4 / 3 | Not a desktop item; settled by a call with the client (Section 3.1.1) | 2 / 3 | 1 / 3 |
| Fee | Base fee estimate for the scoped work: $48,000 | |||
| pC, CC | Item C: probability 0.25 that the fill needs added consolidation testing and analysis costing $6,000 | |||
| pE, CE | Item E: probability 0.20 that a void or pinnacle needs two added borings and the resistivity survey, costing $18,000 | |||
Submit a fixed fee of $48,000 with a $5,100 (about 11%) contingency allowance or an optional karst task, and stated assumptions for access, track time and the report date. As received, the request rated High on five of six items, which calls for more research, not a price. The desktop study, costing a few hours, settled rock depth, access and schedule. It could not settle groundwater, fill strength or karst, and those three items are exactly what the borings, piezometer, rock core and lab program are aimed at. What remains after that scope is Elevated, which a fixed fee can carry when the assumptions are written down.
The ratings also tell the client something. Item E stays Elevated even after the scope: two borings through a karst embankment can miss a void. Saying so in the proposal, with the resistivity survey offered as an option, sets the client’s expectation before the work starts rather than in a change order afterwards.