3.1.0 Purpose and Overview

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell
3.1.0 Purpose and Overview

A proposal does several jobs at once. To the client it is an offer: a scope, a deliverable, a schedule and a fee. To the firm it is a decision about whether that fee can deliver those services to the standard of care. To the project team it is the plan of the work, and the first engineering product on the job, because it fixes what will be explored, tested and analyzed and therefore what the final report can and cannot say. Once signed, it is the contract baseline: its assumptions define what the fee covers and what counts as a change. Table 3.1-1 lists these purposes.

Table 3.1-1. The purposes a proposal serves
PurposeAudienceWhat it has to do
Offer of servicesClientState the scope, deliverable, schedule and fee clearly enough to be accepted and priced competitively
Internal risk assessmentThe firmDecide whether the fee and schedule can deliver the requested services to the standard of care, given what is not known about the site
Plan of the workProject teamFix what will be explored, tested and analyzed, and therefore what the final report can and cannot say
Contract baselineBoth partiesRecord the assumptions and exclusions the fee rests on, so that a change in conditions is recognized as a change (Chapter 8.2)
Statement of known riskClientTell the client, before work starts, which ground and site questions will remain open after the proposed work

Why an internal risk assessment is always done

Two pressures meet in every proposal. The first is uncertainty: the ground has not been explored, the records may be thin, and access, track time and the client’s real question may not be clear from the request. The second is price: most work is won on a competitive fee, or negotiated against a budget the client already has in mind. A thin scope saves money at the proposal stage and costs it back later in change orders, return trips and hedged recommendations. A padded scope loses the work. Under a fixed fee, whatever the proposal fails to anticipate is paid for by the firm.

For that reason an internal risk assessment is made on every proposal, including a sole-sourced estimate requested by email. It is not shown to the client. It compares two things: what the client expects (the decision to be supported, the deliverable, the schedule, the budget and how firm an answer is wanted) and the level of effort needed to deliver it. Where the two do not line up, the gap is the proposal’s risk. Table 3.1-2 lists the usual places a mismatch appears.

Table 3.1-2. Client expectations set against the level of effort they require
ItemClient expectationLevel of effort it requiresSign of a mismatch
Decision to be supportedReplace, repair or monitor; design-level or screeningExploration depth and analysis matched to that decisionA design-level answer requested on a screening budget
DeliverableLetter, data report, full recommendations report, design inputEngineering and review hours (Chapter 3.7)“Brief letter” that must carry design parameters
ScheduleReport date, often tied to a work windowTrack time, drilling availability, lab turnaroundReport due before lab results can exist
BudgetStated or implied ceilingSum of tasks at realistic production ratesFee forced down by removing borings rather than tasks
Site accessAssumed easyHi-rail or track-mounted rig, flagging, right-of-entry, clearing (Chapter 3.6)No access route visible in imagery
Certainty of the answerA firm recommendationEnough data to support it without hedgingVariable ground with one boring proposed

Applying the risk rating to the proposal

The risk rating theory of Chapter 3.8 applies directly. Each uncertainty is rated on the same 1-to-5 scales and scored with the same equation, R = F × S. Here F is the likelihood that the conditions or the effort will differ materially from what the fee assumes, and S is the consequence to the firm and the client if they do (Table 3.1-3). The scores fall into the five levels of Table 3.8-72, and each level calls for a particular proposal response (Table 3.1-4). As in the risk ratings, the worst item governs.

Table 3.1-3. Likelihood and severity scales for proposal risk (same 1-to-5 scales as Section 3.8.22)
RatingF: likelihood that conditions or effort differ materially from what the fee assumesS: consequence if they do
1Rare: recent borings at the site; simple, documented geology; access confirmedNegligible: absorbed in normal margin (less than about 2% of fee)
2Unlikely: good nearby data and simple geology; access route visibleMinor: 2–5% of fee or a few days of schedule
3Possible: regional data only; moderate variability expectedModerate: 5–15% of fee; schedule slip; a change order needed
4Likely: little or no data; variable or problem geology; access unknownMajor: 15–30% of fee; remobilization; recommendations must be qualified
5Almost certain: no data and known difficult conditionsSevere: more than 30% of fee; standard of care cannot be met as scoped; safety, liability or relationship at stake
Table 3.1-4. Proposal response by risk level (levels and score ranges from Table 3.8-72)
LevelR = F × SProposal response
1 Low1–2Price as scoped; standard assumptions
2 Guarded3–5Price as scoped; name the item in the assumptions
3 Elevated6–10Scope it, or carry it with a stated assumption, an optional task or a contingency allowance
4 High12–16Do more desktop work before pricing; then scope it directly, phase the work, or price it on unit rates
5 Severe20–25Do not price as a fixed fee. Propose a Phase 1 study only, time and materials, or decline

Desktop study first, then scope the residual uncertainty

The first rating is made from the request alone, and it is usually High, because almost nothing is known. Pricing at that point means either padding every task or gambling on the ground. The next step is a desktop study (Chapter 3.2) sized to the proposal: geology and soil maps, legacy borings, as-built plans, imagery and lidar, hazard databases and the railroad’s own history of the site. It costs hours, not days, and it settles what public and railroad records can settle.

The items are then rated again. Whatever the desktop study could not settle is the residual uncertainty, and the residual uncertainty is the scope of work. Each boring, sample, test and analysis in the proposal should answer one of the residual items, and each residual item should be answered by something in the scope or carried by a stated assumption, optional task or contingency. Fieldwork is not proposed for what the desk work already answered. Figure 3.1-1 shows the sequence.

Uncertainty in the requestGround, groundwater, access, history and client expectations all unknownAfter the desktop studyResidual uncertainty: what public and railroad records cannot settleSettled at desk cost:not proposed as fieldwork= Proposed scope of workBorings, sampling, lab and analyses aimed only at the residualLeft after the scopeCarried in writing, not in the fee:Exclusions, optional tasks, contingency and the change-order clause(Sections 3.1.3 and 3.1.6, Chapter 8.2)Rule:research what can be known; drill what cannot; write down what is left.Bar length is schematic. Each bar is the same list of uncertainties, re-rated with R = F × S (Section 3.8.22).
Figure 3.1-1. How the proposal narrows uncertainty. The desktop study removes what can already be known, the scope of work is built from what remains, and the proposal’s assumptions carry the rest.

How the proposal is put together

1. Read the request
Client expectations: the decision, deliverable, schedule, budget (Section 3.1.1)
▬▸
2. First risk rating
Rate each uncertainty F × S before any research
▬▸
3. Desktop study
Geology, soils, legacy borings, imagery, access, history (Chapter 3.2)
▬▸
4. Re-rate
What the desktop study settled; list the residual uncertainty
▬▸
5. Scope the residual
Borings, sampling, lab and analyses aimed at what is still unknown (Sections 3.1.2, Chapter 3.3)
▬▸
6. Quotes and estimate
Subconsultants, labor, track time (Section 3.1.5, Chapter 3.7)
▬▸
7. Decide and send
Assumptions, exclusions, contingency, go or no-go (Sections 3.1.3, 3.1.6, 3.1.7)

Most railroad requests arrive as a short email from the client’s project manager rather than a formal request for proposal. Many are sole-sourced and ask for a cost estimate with a bullet list of assumptions, not a full proposal document. The process is the same for both; only the amount written out for the client differs. The internal ratings are kept in the project file either way.

Table 3.1-5. Proposal stages, outputs and who does the work
StageOutputTypical leadWhere
Read the requestOne-paragraph statement of the problem, the decision the work supports and the client’s expectationsProject managerSection 3.1.1
First risk ratingList of uncertainty items, each rated F and SProject manager with geotechnical leadThis section; Section 3.8.22
Desktop studySite map (KMZ), legacy boring and well logs, soil and geology summary, imagery, access, site historyProject or design engineerChapter 3.2
Re-rateResidual uncertainty list with revised F and SGeotechnical leadSection 3.2.6
Scope the residualBoring plan, depths and sampling, lab program, analyses, deliverableProject manager with geotechnical leadSection 3.1.2; Chapter 3.3
Quotes and estimateDrilling and laboratory quotes; task-by-task hours, track time, travelProject managerSection 3.1.5; Chapter 3.7
Decide and sendAssumptions and exclusions, contingency, go or no-go; estimate or proposal to the clientProject managerSection 3.1.3, 3.1.6, 3.1.7

How the rest of this chapter does it

  • Section 3.1.1: reading the request and pinning down the client’s expectations, the first half of the comparison.
  • Section 3.1.2: building the scope from the residual uncertainty, with Chapter 3.3 for boring layout, depth and sampling.
  • Section 3.1.3: writing down what the scope does not cover, so that it is carried by the contract rather than the fee.
  • Section 3.1.4: phasing, which is the usual answer to a High rating that the desktop study cannot bring down.
  • Section 3.1.5: choosing fixed fee, unit rates or time and materials to suit the residual risk, with Chapter 3.7 for the estimate itself.
  • Section 3.1.6: how contract terms share the risk that remains, with Chapter 8.2 for change orders.
  • Section 3.1.7: the review before sending, including the go or no-go decision.
Rate before you research, research before you scope, and scope only what the research could not answer. Whatever is left goes in the assumptions, in writing.

Worked example

The example shows the ratings at the three points where they change: as the request arrives, after the desktop study and after the scope is drafted. It is laid out in five parts: what is known (Given), what is wanted (Required), the equations, a flow chart of the steps with a spot check at each step, and the solution with what it means for the proposal.
Example 3.1-1: Rating a Culvert Replacement Request Before and After the Desktop Study

A Class I railroad located in Middle Tennessee asks, by email, for a fixed-fee proposal for a geotechnical exploration and recommendations to replace a 60-inch corrugated metal pipe culvert under a 25-ft main-line embankment. The report is wanted in four weeks; no budget is stated. Before any research, the proposal team lists six things it does not know and rates each with the scales in Table 3.1-3. It rates them again after the desktop study and again after drafting the scope.

Mapped limestone (karst region): depth and soundness unknownMain track60-in. CMP?? fill strength25 ftponding upstreamGivenFixed fee; report in 4 weeksItems A–F, each with F and Son receipt, after desk, after scopeBase fee estimate $48,000p and C for residual items C and ERequiredR and level of each item, 3 stagesGoverning proposal levelScope or assumption for each itemContingency K; go or no-goBlack = given; red = required
Given and required for Example 3.1-1.

Given

ItemF / S on receiptDesktop findingF / S after deskF / S after scope
A Depth to rock under the culvert4 / 4Bridge plans 400 ft away show limestone at 18–22 ft2 / 41 / 4
B Groundwater and seepage through the fill3 / 3Imagery shows ponding upstream in wet seasons; no records3 / 32 / 2
C Fill type and strength4 / 3No construction records; fill origin unknown4 / 32 / 3
D Rig access and track time4 / 4Lidar and imagery show a farm road to the downstream toe; crest by hi-rail only2 / 32 / 2
E Karst: voids or pinnacled rock3 / 5State geologic map: limestone; sinkhole inventory: three within 0.5 mile3 / 52 / 4
F Report date versus lab turnaround4 / 3Not a desktop item; settled by a call with the client (Section 3.1.1)2 / 31 / 3
FeeBase fee estimate for the scoped work: $48,000
pC, CCItem C: probability 0.25 that the fill needs added consolidation testing and analysis costing $6,000
pE, CEItem E: probability 0.20 that a void or pinnacle needs two added borings and the resistivity survey, costing $18,000

Required

  • The risk score R and level of each item on receipt, after the desktop study and after the scope
  • The governing proposal level at each stage and the response it calls for (Table 3.1-4)
  • Which items become scope and which become stated assumptions
  • A contingency allowance for the residual cost exposure, and whether to submit a fixed fee

Equations

  1. Eq. 1: R = F × S — risk score, 1 to 25 (Section 3.8.22)
  2. Eq. 2: Level = 1 Low (1–2), 2 Guarded (3–5), 3 Elevated (6–10), 4 High (12–16), 5 Severe (20–25) — Table 3.8-72
  3. Eq. 3: Proposal level = max(LevelA … LevelF) — the worst item governs, as in the risk ratings
  4. Eq. 4: K = Σ pi Ci — expected cost of the residual items carried as contingency (Section 8.2.8)

Steps

Step 1 · Rate the request as received (Eq. 1, Eq. 2)
Uses: F and S on receipt
A 4×4, B 3×3, C 4×3, D 4×4, E 3×5, F 4×3
A = 16 (High); B = 9 (Elevated); C = 12 (High); D = 16 (High); E = 15 (High); F = 12 (High)
Spot check: 15 lies in the 12–16 band (3×5 is listed as High in Table 3.8-72), and 9 lies in 6–10, Elevated.
↓
Step 2 · Governing level on receipt (Eq. 3)
Uses: levels from Step 1
Five of six items are High; none is Severe
Proposal level = 4 High → do the desktop study before pricing (Table 3.1-4)
Spot check: No item reaches 20, so a fixed fee is not ruled out; it is only premature.
↓
Step 3 · Re-rate after the desktop study (Eq. 1, Eq. 2)
Uses: F and S after desk
A 2×4, B 3×3, C 4×3, D 2×3, E 3×5, F 2×3
A = 8 (Elevated); B = 9 (Elevated); C = 12 (High); D = 6 (Elevated); E = 15 (High); F = 6 (Elevated)
Spot check: The desk work lowered F for A, D and F only. B, C and E are unchanged, because records cannot show groundwater, fill strength or voids. Those three are the residual uncertainty.
↓
Step 4 · Turn the residual into scope or assumptions
Uses: Step 3 levels; Table 3.1-4
Every item still Elevated or higher gets a line in the proposal: scope (A, B, C, E) or a stated assumption (D, F)
Scope: 2 borings to rock with 10 ft of core each, continuous SPT in fill, 1 piezometer, lab program; optional resistivity survey
Spot check: Nothing is proposed for what the desk work already settled: no boring is added to find rock depth beyond confirming it at the culvert.
↓
Step 5 · Re-rate what is left after the scope (Eq. 1, Eq. 2, Eq. 3)
Uses: F and S after scope
A 1×4, B 2×2, C 2×3, D 2×2, E 2×4, F 1×3
A = 4 (Guarded); B = 4 (Guarded); C = 6 (Elevated); D = 4 (Guarded); E = 8 (Elevated); F = 3 (Guarded); governing level = 3 Elevated
Spot check: The highest score is 8, inside 6–10, so the proposal is Elevated, not High: a fixed fee with stated assumptions and a contingency is appropriate.
↓
Step 6 · Contingency for the Elevated residual (Eq. 4)
Uses: pC, CC, pE, CE, base fee
K = 0.25 × $6,000 + 0.20 × $18,000 = $1,500 + $3,600
K = $5,100, or 10.6% of the $48,000 base fee
Spot check: 5,100 / 48,000 = 0.106. Item E alone is $3,600, 71% of K, which agrees with E being the highest residual score.
↓
Solution
High on receipt → desktop study → residual items B, C and E scoped, D and F assumed → Elevated after scope; go with a $48,000 fixed fee, a $5,100 contingency (or an optional task) and stated assumptions.

Solution

Submit a fixed fee of $48,000 with a $5,100 (about 11%) contingency allowance or an optional karst task, and stated assumptions for access, track time and the report date. As received, the request rated High on five of six items, which calls for more research, not a price. The desktop study, costing a few hours, settled rock depth, access and schedule. It could not settle groundwater, fill strength or karst, and those three items are exactly what the borings, piezometer, rock core and lab program are aimed at. What remains after that scope is Elevated, which a fixed fee can carry when the assumptions are written down.

The ratings also tell the client something. Item E stays Elevated even after the scope: two borings through a karst embankment can miss a void. Saying so in the proposal, with the resistivity survey offered as an option, sets the client’s expectation before the work starts rather than in a change order afterwards.