3.1.3 Assumptions, Exclusions and Limitations

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell
3.1.3 Assumptions, Exclusions and Limitations

The assumption list is the part of the proposal the client reads most carefully and the part that protects the scope later. Every item that could change the cost belongs on it. Write each assumption as a plain statement the client can agree or disagree with.

Table 3.1-9. Standard assumptions for railroad geotechnical proposals
TopicTypical assumptionWhy it is stated
AccessBorings are accessible to a truck-mounted rig from public roads or the railroad right-of-way; clearing, matting or a track rig is priced separately where notedClearing and mats can exceed the drilling cost on wooded or wet sites (Chapter 3.6)
Right-of-entryThe railroad will provide right-of-entry on its property; entry onto other property, if needed, will be arranged by the railroad or priced as additional workBoring locations often plot outside the property line once surveyed
Track protectionFlagging and track protection will be provided by the railroad at no cost to the consultantFlagging availability drives the schedule
Train standbyStandby time for trains is budgeted at an assumed number of hours per day (for example 3.5 hours, from past work on the line)Standby is often the largest variable cost
UtilitiesPublic utilities will be located through the one-call system; railroad signal and communication lines will be located by the railroadBorings must be kept a set distance from utilities
Boring locationsLocations may be adjusted in the field for access and utilities; ground elevations will be surveyed or taken from lidarAvoids disputes when borings move
Groundwater and cuttingsCuttings will be spread on site unless screening indicates impacted material, in which case drumming and disposal are additional workFill sites with odor or slag may need drummed cuttings
LaboratoryQuantities are estimates; the tests performed will be selected after the borings are loggedLets the engineer target the tests
ScheduleField work can begin within a stated time after notice to proceed, weather and flagging permittingSets expectations
ExclusionsEnvironmental sampling, wetland delineation, survey, infiltration testing or design by others are excluded unless listedPrevents scope creep
Be conservative where the work is sole-sourced. A client that has chosen the consultant does not need the lowest number; it needs a number that will hold. Carry realistic standby, a mobilization for each separate setup, and a coring contingency where rock may be shallow.