The assumption list is the part of the proposal the client reads most carefully and the part that protects the scope later. Every item that could change the cost belongs on it. Write each assumption as a plain statement the client can agree or disagree with.
| Topic | Typical assumption | Why it is stated |
|---|---|---|
| Access | Borings are accessible to a truck-mounted rig from public roads or the railroad right-of-way; clearing, matting or a track rig is priced separately where noted | Clearing and mats can exceed the drilling cost on wooded or wet sites (Chapter 3.6) |
| Right-of-entry | The railroad will provide right-of-entry on its property; entry onto other property, if needed, will be arranged by the railroad or priced as additional work | Boring locations often plot outside the property line once surveyed |
| Track protection | Flagging and track protection will be provided by the railroad at no cost to the consultant | Flagging availability drives the schedule |
| Train standby | Standby time for trains is budgeted at an assumed number of hours per day (for example 3.5 hours, from past work on the line) | Standby is often the largest variable cost |
| Utilities | Public utilities will be located through the one-call system; railroad signal and communication lines will be located by the railroad | Borings must be kept a set distance from utilities |
| Boring locations | Locations may be adjusted in the field for access and utilities; ground elevations will be surveyed or taken from lidar | Avoids disputes when borings move |
| Groundwater and cuttings | Cuttings will be spread on site unless screening indicates impacted material, in which case drumming and disposal are additional work | Fill sites with odor or slag may need drummed cuttings |
| Laboratory | Quantities are estimates; the tests performed will be selected after the borings are logged | Lets the engineer target the tests |
| Schedule | Field work can begin within a stated time after notice to proceed, weather and flagging permitting | Sets expectations |
| Exclusions | Environmental sampling, wetland delineation, survey, infiltration testing or design by others are excluded unless listed | Prevents scope creep |