↑ Parent Menu⌂ Main Menu
← Chapter 3.1 Scoping Proposals
GHRM
Railway Ground Hazard Risk Management · 3.0 · Risk Management
Sections · open a dropdown to go to a section or subsection

3.1.6 Risk Allocation and Contract Terms

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell
3.1.6 Risk Allocation and Contract Terms

The proposal also allocates risk. Railroad master service agreements usually govern insurance, safety training and payment, but three items should be checked on every job:

  • Differing site conditions. State that the scope is based on the conditions expected from the desktop study, and that refusal, obstructions, impacted material or conditions materially different from those expected will be handled as a change (Chapter 8.2).
  • Subconsultant terms. Subconsultants need insurance that meets the railroad agreement, with both the railroad and the consultant named as additional insured, and a rider if their policy excludes work within 50 ft of track. Payment terms that hold payment until the client pays should be disclosed in the request for quotes.
  • Standard of care and reliance. Make clear what the deliverable is (exploration data or investigation recommendations) and who may rely on it (Chapter 8.1).
Change order triggers belong in the proposal. If standby is assumed at 3.5 hours a day, say so; then extra standby is plainly a change rather than a dispute.
← Previous · 2.0 The Underworld Chapter 2.13 — Residual, Tropical and Arid Soils
Next · 3.0 Risk Management → Chapter 3.2 — Desktop Study