3.1.1 Understanding the Request

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell
3.1.1 Understanding the Request

Start by writing down, in one paragraph, what the client is trying to decide. Requests rarely say this directly. "Schedule the additional borings needed for the steeper side slopes" really means "tell us whether steepening the fill is cheaper than buying the neighbor's land." "Survey, geotech and environmental for a parking expansion" really means "tell us what it will take to build heavy-duty pavement and light towers on this ground." The scope follows from that sentence, not from the list of tasks in the email.

3.1.1.1 Questions to Answer Before Writing Scope

Table 3.1-6. Questions to answer before scoping
QuestionWhy it mattersWhere the answer usually comes from
What is being built or protected, and what loads does it carry?Sets boring depths, tests and analyses (track, pavement for container handlers, light towers, walls, culverts)Request email, concept plans, client project manager
What decision will the report support?Keeps the scope aimed at the question, such as slope steepening versus property purchaseConversation with the client project manager
What has already been done at or near the site?Legacy borings can reduce the program or show where the gaps arePrevious reports, project files, public well and boring databases
Are there ground rules?Some clients fix the number of light towers, ban infiltration tests in high groundwater or cap the budgetRequest email
What is the budget limit and the schedule?Determines whether locations are priced together or separately and when field work can happenClient project manager
Is the work sole-sourced or competitive?Sole-sourced work should carry conservative assumptions rather than a cut scopeRequest email
Who else is on the team?Survey, environmental, drainage and structures scopes must not overlap or leave gapsInternal project manager

Record the request, the date and who sent it at the top of the proposal file. When the scope changes during development (borings added, depths cut, a location dropped), date each change and say who agreed to it. That history is what lets the team explain the final number and later defend it.

Example. On an intermodal parking expansion the request gave three ground rules: assume eight high-mast light towers at about 500 ft spacing, perform no infiltration tests because groundwater is very high, and keep assumptions conservative because the work was sole-sourced. Each rule changed the boring layout and the lab program before a single quote was requested.