Before the estimate goes out, walk the checklist below. It follows the order of the proposal checklist and the railroad project checklist used in practice.
| Step | Check |
|---|---|
| Read the request | Overview, location and scope written down; ground rules listed |
| Site location and extent | Latitude and longitude, city, county and state; study-area polygon in a KMZ |
| Desktop review | Imagery, soil survey, quadrangle maps (current and historical), geology, well logs, legacy reports (Chapter 3.2) |
| Special conditions | Seismic, expansive or collapsible soils, karst, fill, organics, contamination |
| Boring location plan | Borings named and located; depths, sampling and purpose stated for each |
| Laboratory program | Tests and quantities tied to the analyses |
| Rig and access | Rig type, drilling method, clearing and mats, water source (Chapter 3.6) |
| Contract driller | RFP sent; quote received and checked against the RFP quantities |
| Questions | Open items listed for the client |
| Draft estimate and scope | Labor, subconsultants, travel; assumptions list |
| Final | Totals checked; within any budget limit; quote and estimate agree; files saved to the proposal folder |