Phase the work so that each phase answers a question before the next is committed. On a site with two parcels the client may authorize one or both, so each is estimated separately. On a ground hazard program the desktop study and risk rating (Chapters 3.2 and 3.8) decide which sites go to field assessment and which go to borings.
| Step | Typical duration | Controlling factor |
|---|---|---|
| Proposal preparation | 1 to 2 weeks (a two-week turnaround is common) | Subconsultant quotes |
| Client approval and notice to proceed | 1 to 4 weeks | Client budget approval |
| One-call locate, flagging request, right-of-entry | 1 to 3 weeks | Flagging availability; property owners |
| Reconnaissance and clearing | 1 to 5 days | Vegetation, wetlands, nesting season |
| Drilling | 1 to 10 days | Number of borings, train traffic, access |
| Laboratory testing | 2 to 4 weeks | Consolidation and triaxial tests |
| Analysis and report | 2 to 4 weeks after laboratory data | Review cycle |
Two calendar constraints come up often on railroad work: flagging crews tend to start their work week on a Tuesday, and clearing near trees should be done outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them) or after a nest check.