3.1.4 Schedule and Phasing

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell
3.1.4 Schedule and Phasing

Phase the work so that each phase answers a question before the next is committed. On a site with two parcels the client may authorize one or both, so each is estimated separately. On a ground hazard program the desktop study and risk rating (Chapters 3.2 and 3.8) decide which sites go to field assessment and which go to borings.

Table 3.1-10. Typical durations for a small railroad geotechnical program
StepTypical durationControlling factor
Proposal preparation1 to 2 weeks (a two-week turnaround is common)Subconsultant quotes
Client approval and notice to proceed1 to 4 weeksClient budget approval
One-call locate, flagging request, right-of-entry1 to 3 weeksFlagging availability; property owners
Reconnaissance and clearing1 to 5 daysVegetation, wetlands, nesting season
Drilling1 to 10 daysNumber of borings, train traffic, access
Laboratory testing2 to 4 weeksConsolidation and triaxial tests
Analysis and report2 to 4 weeks after laboratory dataReview cycle

Two calendar constraints come up often on railroad work: flagging crews tend to start their work week on a Tuesday, and clearing near trees should be done outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them) or after a nest check.