The scope is written by task, in the order the work will be done, so that the cost estimate (Chapter 3.7) can follow it line for line. A typical railroad geotechnical scope has the tasks below; ground hazard assignments add the risk assessment task.
| Task | Content | Notes |
|---|---|---|
| A. Project management | Setup, coordination, client meetings, invoicing, quality control | Usually 8 to 12% of labor hours |
| B. Ground hazard risk management | Desktop study, field assessment, risk rating, alternatives (Chapters 3.2, 3.8 and 3.8) | Only on ground hazard work |
| C. Engineer reconnaissance | Site visit to confirm access, utilities and boring locations (Chapter 3.4) | Travel and on-site time; one trip is normal |
| D. Subsurface field exploration | Utility clearance, mobilization, drilling oversight, logging, demobilization | Driller is a subconsultant; the field engineer is with the rig every day |
| E. Laboratory testing | Index, strength, consolidation, compaction, corrosion tests | In-house or by the drilling subconsultant's laboratory |
| F. Geotechnical engineering | Typed logs, analysis, report or memorandum | Deliverable is set by the client's question (Chapter 8.1) |
| G to M. Other disciplines | Pavement design, survey, hydrology, structures, permitting, bid package, construction quality assurance | Only if requested; coordinate with those teams |
The field program is described in enough detail that a reviewer could price it: number of borings, depth of each, sampling interval, special sampling (Shelby tubes, rock core, bulk samples), field tests (dynamic cone penetrometer, pocket penetrometer, vane), groundwater readings, screening (photo-ionization detector where fill or odors are expected), backfill method and the number of drilling days. Name the borings in the proposal (for example HML-1 to HML-8 and PB-1 to PB-11) so they can be traced into the field and the report.
| Item | Parking and light towers on filled marshland | Steepened siding fill on a hillside |
|---|---|---|
| Borings | 8 light-tower borings to 35 ft; 11 pavement borings to 10 ft (390 ft) | 8 toe borings to 15 ft; 2 ditch borings to 6 ft (132 ft) |
| Sampling | SPT; DCP to 5 ft in pavement borings; 3 bulk samples for Proctor and CBR | Continuous SPT; Shelby tubes in soft clay; NQ core where refusal is shallow (15 ft contingency) |
| Screening and water | PID on every boring; groundwater at drilling and completion | Water at drilling, completion and 24 hours |
| Rig and days | One truck rig; about 7 drilling days | Track or ATV rig with mats; about 2.5 drilling days plus a separate setup |
| Laboratory | Moisture, Atterberg, -200 and hydrometer, organics, UC, consolidation on peat, Proctor and CBR, corrosion suite on slag | Moisture, Atterberg, -200, organics, UC, consolidation, CU triaxial or direct shear, rock UCS |
| Engineering | Drilled-shaft axial and lateral design; pavement subgrade parameters; undercut; settlement over organics | Global stability of 1.5H:1V slopes; shot-rock toe key versus geogrid; quantities by reach |
| Deliverable | Geotechnical report | Memorandum addendum to the earlier report |
Say what will be delivered, in what form and when: a data report (exploration), a geotechnical report with recommendations (investigation), or a memorandum (Chapters 8.1 and 8.3). State whether typed logs, laboratory sheets, analysis output and quantity tables are included. On ground hazard work, say whether the deliverable includes risk ratings and stabilization alternatives with costs.