3.1.2 Scope of Services and Deliverables

Turning a request into a clear, priced scope of services before any field work: what the client needs, what will be delivered, what is assumed, and how the work is phased.
Author: Daniel P. Colwell
3.1.2 Scope of Services and Deliverables

The scope is written by task, in the order the work will be done, so that the cost estimate (Chapter 3.7) can follow it line for line. A typical railroad geotechnical scope has the tasks below; ground hazard assignments add the risk assessment task.

Table 3.1-7. Standard task structure for geotechnical and ground hazard scopes
TaskContentNotes
A. Project managementSetup, coordination, client meetings, invoicing, quality controlUsually 8 to 12% of labor hours
B. Ground hazard risk managementDesktop study, field assessment, risk rating, alternatives (Chapters 3.2, 3.8 and 3.8)Only on ground hazard work
C. Engineer reconnaissanceSite visit to confirm access, utilities and boring locations (Chapter 3.4)Travel and on-site time; one trip is normal
D. Subsurface field explorationUtility clearance, mobilization, drilling oversight, logging, demobilizationDriller is a subconsultant; the field engineer is with the rig every day
E. Laboratory testingIndex, strength, consolidation, compaction, corrosion testsIn-house or by the drilling subconsultant's laboratory
F. Geotechnical engineeringTyped logs, analysis, report or memorandumDeliverable is set by the client's question (Chapter 8.1)
G to M. Other disciplinesPavement design, survey, hydrology, structures, permitting, bid package, construction quality assuranceOnly if requested; coordinate with those teams

3.1.2.1 Describing the Field Program

The field program is described in enough detail that a reviewer could price it: number of borings, depth of each, sampling interval, special sampling (Shelby tubes, rock core, bulk samples), field tests (dynamic cone penetrometer, pocket penetrometer, vane), groundwater readings, screening (photo-ionization detector where fill or odors are expected), backfill method and the number of drilling days. Name the borings in the proposal (for example HML-1 to HML-8 and PB-1 to PB-11) so they can be traced into the field and the report.

Table 3.1-8. Example field programs from two recent railroad proposals
ItemParking and light towers on filled marshlandSteepened siding fill on a hillside
Borings8 light-tower borings to 35 ft; 11 pavement borings to 10 ft (390 ft)8 toe borings to 15 ft; 2 ditch borings to 6 ft (132 ft)
SamplingSPT; DCP to 5 ft in pavement borings; 3 bulk samples for Proctor and CBRContinuous SPT; Shelby tubes in soft clay; NQ core where refusal is shallow (15 ft contingency)
Screening and waterPID on every boring; groundwater at drilling and completionWater at drilling, completion and 24 hours
Rig and daysOne truck rig; about 7 drilling daysTrack or ATV rig with mats; about 2.5 drilling days plus a separate setup
LaboratoryMoisture, Atterberg, -200 and hydrometer, organics, UC, consolidation on peat, Proctor and CBR, corrosion suite on slagMoisture, Atterberg, -200, organics, UC, consolidation, CU triaxial or direct shear, rock UCS
EngineeringDrilled-shaft axial and lateral design; pavement subgrade parameters; undercut; settlement over organicsGlobal stability of 1.5H:1V slopes; shot-rock toe key versus geogrid; quantities by reach
DeliverableGeotechnical reportMemorandum addendum to the earlier report

3.1.2.2 Deliverables

Say what will be delivered, in what form and when: a data report (exploration), a geotechnical report with recommendations (investigation), or a memorandum (Chapters 8.1 and 8.3). State whether typed logs, laboratory sheets, analysis output and quantity tables are included. On ground hazard work, say whether the deliverable includes risk ratings and stabilization alternatives with costs.

A site investigation checklist of the kind used to make sure no part of the program is left out of the scope.
Figure 3.1-2. A site investigation checklist of the kind used to make sure no part of the program is left out of the scope.