Most railroad geotechnical work is estimated as time and materials against the client's rate schedule, with subconsultant costs passed through. The estimate itself is built task by task (Chapter 3.7). When a client sets a budget limit, test the scope against it early: in one recent case the first location fit under the limit and the two locations together did not, so they were priced as separate lines and the client was told which one fit.
Lab testing should be carried once. Where the drilling subconsultant's quote includes laboratory testing, zero the consultant's own laboratory lines so the client is not billed twice.