Chapter 8.2 — Change Orders

Handling changes in scope, conditions or schedule after the work has started, without stopping the work or losing the money.
Author: Daniel P. Colwell

This chapter covers when a change order is needed, how to recognize and document the change, how to price it, and how to get it approved. Most changes on railroad geotechnical work come from a short list of causes, and most disputes come from changes that were not written down when they happened.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
8.2.0 Purpose and Overview

A change order adjusts the scope, fee or schedule of an agreement after it has been signed. It is not a penalty or a failure of the estimate; it is how the agreement keeps up with the site. The aim is to recognize a change early, tell the client before the cost is spent, and agree the adjustment in writing.

Recognize
Something differs from the scope or assumptions
▬▸
Notify
Tell the client project manager the same day
▬▸
Document
What, why, when, who; photos and logs
▬▸
Price
Quantities and rates from the estimate
▬▸
Approve
Written agreement before or promptly after the work
▬▸
Track
Budget tracking by task
8.2.1 Common Triggers
Table 8.2-1. Common causes of change on railroad geotechnical work
CauseExampleAssumption it departs from (Chapter 3.1)
Train standby beyond the assumptionHeavy traffic gives far more standby than the hours per day assumedStandby hours per day
Added borings or depthsA design check finds a reach with embankment work and no borings; three borings are addedBoring plan
Differing site conditionsCemented slag or shallow rock causes refusal and offsets; soft clay continues below the planned depthExpected profile
AccessWet ground needs mats; borings plot outside the right-of-way and need a permit or right-of-entryAccess and right-of-entry
Impacted materialOdor or screening readings require drummed cuttings and extra testsCuttings spread on site
Additional analyses or deliverablesClient adds an alternative or asks for a report instead of a memorandumDeliverable
ScheduleFlagging or client approvals delay mobilization; a second mobilization is neededSchedule and number of setups
Standby assumed for budgeting, hours per drilling day3.5 hrTypical drilling day, hours10 hrStandby can be a third of the day on a busy line
Figure 8.2-1. On one line the average train standby was about 3.5 hours per drilling day, more than a third of a 10-hour day. Stating that figure as an assumption makes any excess a clear change rather than a dispute.
8.2.2 Notification and Documentation

Tell the client project manager as soon as a change is recognized, by phone and then in a short email, before the extra cost is spent where possible. Field staff call the project manager before leaving site each day; that call is where most changes are first heard.

Table 8.2-2. What to record for every change
RecordSource
What changed, where and whenField log, daily log, boring logs, photos
Why (the cause and the assumption it departs from)Proposal assumptions; RFP
Who was told, when, and what they saidEmail, phone record
Quantities (hours, footage, days, mats, tests)Daily logs; driller's field tickets; standby summary
Effect on schedule and deliverablesProject manager
Keep a standby log. Record train standby by day and by boring (start, end, reason) on the daily log and have the driller's ticket match it. A standby summary from past invoices on the same line is also the best basis for the next estimate.
8.2.3 Pricing a Change

Price a change with the same rates and structure as the original estimate (Chapter 3.7), so it can be checked line by line. Subconsultant changes are priced from their quote (standby rate, footage rate, mobilization). Show the net change and the new total.

Table 8.2-3. Change pricing summary (form)
LineAmount
Original agreement amount$
Net increase or decrease of this change$
Total of previous changes$
Total of all changes to date$
New agreement amount$
Change in time (working days)

The same summary appears on standard construction change order forms; it lets the client see the cumulative effect of every change.

When a revision reduces the cost (for example, laboratory quantities reset to match the RFP, or a location dropped), issue it the same way. A credit documented promptly builds the trust that makes the next increase easier to approve.

8.2.4 Approval Workflow
Table 8.2-4. Approval workflow
StepWhoOutput
Identify and notifyField engineer or project managerPhone call and email to the client project manager
Prepare the changeProject managerDescription, reason, cost breakdown, schedule effect
Internal reviewGeotechnical lead and the consultant's project manager for the clientAgreed scope and number
Client approvalClient project managerSigned change order or written approval
Subconsultant changeProject managerRevised subconsultant authorization
TrackProject managerBudget tracking updated by task

Where the work must continue to avoid a second mobilization (refusal on the last boring, an extra day of standby), get approval by email on the day and follow with the formal change. Do not stop a rig waiting for paperwork unless the client asks.

8.2.5 Schedule Effects

State the effect of the change on the deliverables: new laboratory dates, a later report, an added memorandum. Where the change is a client decision (a second location authorized later, a deliverable upgraded), restate the schedule from the approval date.

8.2.6 Change Order Form

A change order form needs only five parts: a description of the change (by item), the reason, how the cost is to be settled (with a breakdown by item, unit, quantity, unit price and amount), the cost summary of Table 8.2-3, and the effect on time, with signature lines for both parties and a distribution list. Keep the form to one page plus the breakdown.

Table 8.2-5. Change order breakdown (form)
ItemDescriptionUnitQuantityUnit priceAmount
1Train standby beyond assumptionhr
2Additional boring footageft
3Additional mobilizationea
4Engineering and reportinghr
Total this change$
8.2.7 Cross-References
Table 8.2-6. Related chapters
TopicRefer to
Assumptions and change triggers in the proposalChapter 3.1
ContingenciesChapter 3.3, Table 3.3-10
Cost estimate and budget trackingChapter 3.7
Exploration versus investigationChapter 8.1
MemorandumsChapter 8.3