This chapter covers when a change order is needed, how to recognize and document the change, how to price it, and how to get it approved. Most changes on railroad geotechnical work come from a short list of causes, and most disputes come from changes that were not written down when they happened.
A change order adjusts the scope, fee or schedule of an agreement after it has been signed. It is not a penalty or a failure of the estimate; it is how the agreement keeps up with the site. The aim is to recognize a change early, tell the client before the cost is spent, and agree the adjustment in writing.
| Cause | Example | Assumption it departs from (Chapter 3.1) |
|---|---|---|
| Train standby beyond the assumption | Heavy traffic gives far more standby than the hours per day assumed | Standby hours per day |
| Added borings or depths | A design check finds a reach with embankment work and no borings; three borings are added | Boring plan |
| Differing site conditions | Cemented slag or shallow rock causes refusal and offsets; soft clay continues below the planned depth | Expected profile |
| Access | Wet ground needs mats; borings plot outside the right-of-way and need a permit or right-of-entry | Access and right-of-entry |
| Impacted material | Odor or screening readings require drummed cuttings and extra tests | Cuttings spread on site |
| Additional analyses or deliverables | Client adds an alternative or asks for a report instead of a memorandum | Deliverable |
| Schedule | Flagging or client approvals delay mobilization; a second mobilization is needed | Schedule and number of setups |
Tell the client project manager as soon as a change is recognized, by phone and then in a short email, before the extra cost is spent where possible. Field staff call the project manager before leaving site each day; that call is where most changes are first heard.
| Record | Source |
|---|---|
| What changed, where and when | Field log, daily log, boring logs, photos |
| Why (the cause and the assumption it departs from) | Proposal assumptions; RFP |
| Who was told, when, and what they said | Email, phone record |
| Quantities (hours, footage, days, mats, tests) | Daily logs; driller's field tickets; standby summary |
| Effect on schedule and deliverables | Project manager |
Price a change with the same rates and structure as the original estimate (Chapter 3.7), so it can be checked line by line. Subconsultant changes are priced from their quote (standby rate, footage rate, mobilization). Show the net change and the new total.
| Line | Amount |
|---|---|
| Original agreement amount | $ |
| Net increase or decrease of this change | $ |
| Total of previous changes | $ |
| Total of all changes to date | $ |
| New agreement amount | $ |
| Change in time (working days) |
The same summary appears on standard construction change order forms; it lets the client see the cumulative effect of every change.
When a revision reduces the cost (for example, laboratory quantities reset to match the RFP, or a location dropped), issue it the same way. A credit documented promptly builds the trust that makes the next increase easier to approve.
| Step | Who | Output |
|---|---|---|
| Identify and notify | Field engineer or project manager | Phone call and email to the client project manager |
| Prepare the change | Project manager | Description, reason, cost breakdown, schedule effect |
| Internal review | Geotechnical lead and the consultant's project manager for the client | Agreed scope and number |
| Client approval | Client project manager | Signed change order or written approval |
| Subconsultant change | Project manager | Revised subconsultant authorization |
| Track | Project manager | Budget tracking updated by task |
Where the work must continue to avoid a second mobilization (refusal on the last boring, an extra day of standby), get approval by email on the day and follow with the formal change. Do not stop a rig waiting for paperwork unless the client asks.
State the effect of the change on the deliverables: new laboratory dates, a later report, an added memorandum. Where the change is a client decision (a second location authorized later, a deliverable upgraded), restate the schedule from the approval date.
A change order form needs only five parts: a description of the change (by item), the reason, how the cost is to be settled (with a breakdown by item, unit, quantity, unit price and amount), the cost summary of Table 8.2-3, and the effect on time, with signature lines for both parties and a distribution list. Keep the form to one page plus the breakdown.
| Item | Description | Unit | Quantity | Unit price | Amount |
|---|---|---|---|---|---|
| 1 | Train standby beyond assumption | hr | |||
| 2 | Additional boring footage | ft | |||
| 3 | Additional mobilization | ea | |||
| 4 | Engineering and reporting | hr | |||
| Total this change | $ |
| Topic | Refer to |
|---|---|
| Assumptions and change triggers in the proposal | Chapter 3.1 |
| Contingencies | Chapter 3.3, Table 3.3-10 |
| Cost estimate and budget tracking | Chapter 3.7 |