3.3.10 Pipeline and Casing Crossings Under Track

Deciding where, how deep and how many borings and tests a site needs, and writing it so a driller can price it.
Author: Daniel P. Colwell
3.3.10 Pipeline and Casing Crossings Under Track

Utility crossings are one of the most common reasons for borings on railroad right-of-way, and one of the most common causes of track settlement when the bore is poorly controlled. AREMA Chapter 1, Part 5, sets the depth, casing and length requirements, and railroad pipeline specifications add the boring program: borings on each side of the track on the crossing centerline, sampled continuously to 5 ft below the proposed invert (rock cored), and grouted full depth. A 2020 conference paper on trenchless risks stresses settlement monitoring of the ground, not just the rails, since loaded rails can bridge a void until it collapses.

3.3.10.1 Requirements

Table 3.3-12. AREMA pipeline crossing requirements (Chapter 1, Part 5)
ItemRequirement
Casing depth5 1/2 ft base of rail to top of casing (4 1/2 ft under secondary or industry track); 3 ft below ground or ditch elsewhere
Uncased steel carrier (secondary or industry track)10 ft below base of rail; 6 ft below ground or ditch elsewhere
Casing length, each side, measured from the centerline of the outside trackGreatest of 2 ft beyond toe of slope, 3 ft beyond ditch, 25 ft (sealed ends) or 45 ft (open ends)
Steel casing inside diameterCarrier OD (joints, couplings) + 2 in. under 6 in.; + 4 in. for 6 in. and over
Steel casing materialMinimum yield 35,000 psi; wall per Table 1-5-1 (thicker if uncoated and unprotected)
Bored holeAbout the pipe OD; more than about 1 in. oversize calls for remedial measures (grouting)
Table 3.3-13. Cooper E80 live load including 50% impact (AREMA Table 1-4-24)
Cover from base of tie (ft)2581012152030
Live load (psf)3,8002,4001,6001,100800600300100

Over 30 ft of cover, use dead load only.

3.3.10.2 Worked example: 30 in. casing under two main tracks

Table 3.3-14. Calculator output
ItemResult
Depth, base of rail to top of casing6.50 ft
E80 live load at 5.85 ft of cover2,173 psf
Total vertical pressure (with 120 pcf soil)2,953 psf
Casing wall, coated0.406 in.
Casing inside diameter for a 24 in. carrier29.19 in.
Casing length (sealed, tracks 14 ft apart)64 ft
Bore overcut on diameter1.00 in.
Boring depth (invert + 5 ft)14.0 ft

The 31 in. bore is at the limit of the AREMA overcut; the annulus should be grouted as the casing advances, and settlement points should be set on the ground at the track before boring starts.

Open the pipeline crossing calculator →
Depth checks, E80 live load at the pipe, minimum casing wall, casing size and length, bore overcut and boring depth.

3.3.10.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • AREMA Manual for Railway Engineering, Chapter 1 Roadway and Ballast (2012, Volume 1), Part 5 Utilities (Table 1-5-1, depth, length and casing requirements) and Part 4 Culverts (Tables 1-4-24 and 1-4-53).Official page ↗
  • A Class I railroad's pipeline occupancy specification (2018), Carriers folder: soil investigation, boring and sampling requirements.Find source ↗
  • A regional railroad holding company's utility specifications, Carriers folder.Find source ↗
  • AREMA conference papers: controlling risks of trenchless pipe construction beneath railways (2020); pipe ramming and the US rail system (2014).Find source ↗